ISTQB Learning

Test your knowledge

0%
2
Created on By Admin

2018v3.1 - Exam 4

1 / 40

1. The project develops a "smart" heating thermostat. The control algorithms of the thermostat were modeled as Matlab/Simulink models and run on the internet connected server. The thermostat uses the specifications of the server to trigger the heating valves.

The test manager has defined the following test strategy/approach in the test plan:

1. The acceptance test for the whole system is executed as an experience-based test.
2. The control algorithms on the server are checked against standard of the energy saving regulation.
3. The functional test of the thermostat is performed as risk-based testing.
4. The security tests of data / communication via the internet are executed together with external security experts.

What four common types of test strategies/approaches did the test manager implement in the test plan?

Select ONE option.

2 / 40

2. Which of the following lists contains only typical exit criteria from testing?

Select ONE option.

3 / 40

3. Which of the following statements on the use of checklists in a formal review is CORRECT?

Select ONE option.

4 / 40

4. Which of the following statements about test estimation approaches is CORRECT?

Select ONE option.

5 / 40

5. Which of the following statements about static testing are MOST true?

Select ONE options.

6 / 40

6. You have just completed a pilot project for a regression testing tool. You understand the tool much better and have tailored your testing process to it. You have standardized an approach to using the tool and its associated work products. Which of the following is a typical test automation pilot project goal that remains to be carried out?

Select ONE option.

7 / 40

7. What is checklist-based testing?

Select ONE option.

8 / 40

8. Which of the following CORRECTLY matches the roles and responsibilities in a formal review?

9 / 40

9. Which of the following is a true statement about exploratory testing?

Select ONE option.

10 / 40

10. You are working as a tester on an online banking system. Availability is considered one of the top products (quality) risks for the system. You find a reproducible failure that results in customers losing their connections to the bank Web site when transferring funds between common types of accounts and being unable to reconnect for between three and five minutes.

Which of the following would be a good summary for a defect report for this failure, one that captures both the essence of the failure and its impact on stakeholders?

Select ONE option.

11 / 40

11. Which of the following BEST describes the concept behind error guessing?

Select ONE option.

12 / 40

12. Mr. Test has been testing software applications on mobile devices for a period of 5 years. He has a wealth of experience in testing mobile applications and achieves better results in a shorter time than others. Over several months, Mr. Test did not modify the existing automated test cases and did not create any new test cases. This leads to fewer and fewer defects being found by executing the tests. What principle of testing did Mr. Test not observe?

Select ONE option.

13 / 40

13. Which one of the following is NOT included in a test summary report?

Select ONE option.

14 / 40

14. The following statement refers to decision coverage:

“When the code contains only a single ‘if’ statement and no loops or CASE statements, and its execution is not nested within the test, any single test case we run will result in 50% decision coverage.”

Which of the following statement is correct?

Select ONE option.

15 / 40

15. Which one of the following is the characteristic of a metrics-based approach for test estimation?

Select ONE option.

16 / 40

16. Which of the following is MOST likely to be used as a reason for using a pilot project to introduce a tool into an organization?

Select ONE option.

17 / 40

17. Which of the following tasks is MOST LIKELY to be performed by the test manager?

Select ONE option.

18 / 40

18. Which of the following should NOT be a trigger for maintenance testing?

Select ONE option.

19 / 40

19. Which one of the following options is categorized as a black-box test technique?

Select ONE option

20 / 40

20. Which of the following statements about the given state transition diagram and table of test cases is TRUE?

Select ONE option.

21 / 40

21. Which of the following statements is a valid objective for testing?

Select ONE option.

22 / 40

22. Which of the following statements comparing component testing and system testing is TRUE?

Select ONE option.

23 / 40

23. As a test manager you are responsible for testing the following parts of requirements:

• R1 - Process anomalies
• R2 - Synchronization
• R3 - Approval
• R4 - Problem solving
• R5 - Financial data
• R6 - Diagram data
• R7 - Changes to the user profile

Notation: Logical requirement dependencies (A -> B means, that B depends on A):

Which one of the following options structures the test execution schedule according to the requirement dependencies?

Select ONE option.

24 / 40

24. You are running a performance test with the objective of finding possible network bottlenecks in interfaces between components of a system. Which of the following statements describes this test?

Select ONE option.

25 / 40

25. Which of the following is a common test metric often used to monitor BOTH test preparation and test execution?

Select ONE option.

26 / 40

26. Given the following test activities and test tools:

1. Performance measurement and dynamic analysis
2. Test execution and logging
3. Management of testing and testware
4. Test design
A. Code coverage tools

B. Dynamic analysis tools
C. Test data preparation tools
D. Defect management tools

Which of the following BEST matches the activities and tools?

Select ONE option.

27 / 40

27. You are testing a mobile app that allows users to find a nearby restaurant, based on the type of food they want to eat. Consider the following list of test cases, priorities (smaller number is high priority), and dependencies, in the following format:

Which of the following is a possible test execution schedule that considers both priorities and dependencies?

Select ONE option.

28 / 40

28. Which one of the following is the description of statement coverage?

Select ONE option.

29 / 40

29. During an Agile development effort, a product owner discovers a previously unknown regulatory requirement that applies to most of the user stories within a particular epic. The user stories are updated to provide for the necessary changes in software behavior. The programmers on the team are modifying the code appropriately. As a tester on the team, what types of tests will you run?

Select ONE option.

30 / 40

30. Which of the following qualities is MORE likely to be found in a tester’s mindset rather than in a developer’s?

Select ONE option.

31 / 40

31. A fitness app measures the number of steps that are walked each day and provides feedback to encourage the user to keep fit.

The feedback for different numbers of steps should be:

Up to 1000 - Couch Potato!
Above 1000, up to 2000 - Lazy Bones!
Above 2000, up to 4000 - Getting There!
Above 4000, up to 6000 - Not Bad!
Above 6000 - Way to Go!

Which of the following sets of test inputs would achieve the BEST equivalence partition coverage?

Select ONE option.

32 / 40

32. Which one of the statements below describes the most common situation for a failure discovered during testing or in production?

Select ONE option.

33 / 40

33. A daily radiation recorder for plants produces a sunshine score based on a combination of the number of hours a plant is exposed to the sun (below 3 hours, 3 to 6 hours or above 6 hours) and the average intensity of the sunshine (very low, low, medium, high).

Given the following test cases:

What is the minimum number of additional test cases that are needed to ensure full coverage of ALL VALID INPUT equivalence partitions?

Select ONE option.

34 / 40

34. Which of the following is LEAST likely to be an example of product risk analysis CORRECTLY influencing the testing?

Select ONE option.

35 / 40

35. Consider the following types of defects that a test level might focus on:

a) Defects in separately testable modules or objects
b) Not focused on identifying defects
c) Defects in interfaces and interactions
d) Defects in the whole test object

Which of the following list correctly matches test levels from the Foundation syllabus with the defect focus options given above?

Select ONE option.

36 / 40

36. In a formal review, what is the role name for the participant who runs an inspection meeting?

Select ONE option.

37 / 40

37. You are working as a project manager on an in-house banking software project. To prevent rework and excessive find/fix/retest cycles, the following process has been put in place for resolving a defect once it is found in the test lab:

1. The assigned developer finds and fixes the defect, then creates an experimental build
2. A peer developer reviews, unit tests, and confirmation tests the defect fix on his/her desktop
3. A tester – usually the one who found the defect – confirmation tests the defect fix in the development environment
4. Once a day, a new release with all confirmed defect fixes included, is installed in the test environment
5. The same tester from step 3 confirmation tests the defect fix in the test environment

Nevertheless, a large number of defects which the testers confirmed as fixed in the development environment (in step 3) are somehow failing confirmation testing in the test environment, with the resulting rework and cycle time outcomes. You have the highest confidence in your testers and have ruled out mistakes or omissions in step 3.

Which of the following is the MOST likely part of the process to check next?

Select ONE option.

38 / 40

38. You will be invited to a review. The work product to be reviewed is a description of the in-house document creation process. The aim of the description is to present the work distribution between the different roles involved in the process in a way that can be clearly understood by everyone.

You will be invited to a checklist-based review. The checklist will also be sent to you. It includes the following points:

i. Is the person who performs the activity clearly identified for each activity?
ii. Are the entry criteria clearly defined for each activity?
iii. Are the exit criteria clearly defined for each activity?
iv. Are the supporting roles and their scope of work clearly defined for each activity?

In the following we show an excerpt of the work result to be reviewed, for which you should use the checklist above:

"After checking the customer documentation for completeness and correctness, the software architect creates the system specification. Once the software architect has completed the system specification, he invites testers and verifiers to the review. A checklist describes the scope of the review. Each invited reviewer creates review comments - if necessary - and concludes the review with an official review done-comment."

Which of the following statements about your review is correct?

Select ONE option.

39 / 40

39. A mass market operating system software product is designed to run on any PC hardware with an x86-family processor. You are running a set of tests to look for defects related to support of the various PCs that use such a processor and to build confidence that important PC brands will work. What type of test are you performing?

Select ONE option.

40 / 40

40. A smart home app measures the average temperature in the house over the previous week and provides feedback to the occupants on their environmental friendliness based on this temperature.

The feedback for different average temperature ranges (to the nearest °C) should be:

Up to 10°C - Icy Cool!
11°C to 15°C - Chilled Out!
16°C to 19°C - Cool Man!
20°C to 22°C - Too Warm!
Above 22°C - Hot & Sweaty!

Using BVA (only Min- and Max values), which of the following sets of test inputs provides the highest level of boundary coverage?

Select ONE option.

0%

Scroll to top