ISTQB Learning

Test your knowledge

0%
2
Created on By Admin

2018v3.1 - Exam 4

1 / 40

1. Which of the following is a common test metric often used to monitor BOTH test preparation and test execution?

Select ONE option.

2 / 40

2. A phone ringing momentarily distracts a programmer, causing the programmer to improperly program the logic that checks the upper boundary of an input variable. Later, during system testing, a tester notices that this input field accepts invalid input values. The improperly coded logic for the upper boundary check is:

Select ONE option.

3 / 40

3. You are reading a user story in the product backlog to prepare for a meeting with the product owner and a developer, noting potential defects as you go. Which of the following statements is true about this activity?

Select ONE option.

4 / 40

4. Which of the following provides the definition of the term test case?

Select ONE option.

5 / 40

5. You are defining the process for carrying out product risk analysis as part of each iteration on an Agile project. Which of the following is the proper place to document this process in a test plan?

Select ONE option.

6 / 40

6. What is decision coverage?

Select ONE option.

7 / 40

7. Which of the following is an example of a task that can be carried out as part of the test process?

Select ONE option.

8 / 40

8. A company's employees are paid bonuses if they work more than a year in the company and achieve a target which is individually agreed before.

These facts can be shown in a decision table:

Which of the following test cases represents a situation that can happen in real life, and is missing in the above decision table?

Select ONE option.

9 / 40

9. Given the following examples of entry and exit criteria:

1. The original testing budget of $30,000 plus contingency of $7,000 has been spent
2. 96% of planned tests for the drawing package have been executed and the remaining tests are now out of scope
3. The trading performance test environment has been designed, set-up and verified
4. Current status is no outstanding critical defects and two high-priority ones
5. The autopilot design specifications have been reviewed and reworked
6. The tax rate calculation component has passed unit testing.

Which of the following BEST categorizes them as entry and exit criteria:

Select ONE option.

10 / 40

10. Which one of the following is the characteristic of a metrics-based approach for test estimation?

Select ONE option.

11 / 40

11. The reviews being used in your organization have the following attributes:

• There is a role of a scribe
• The purpose is to detect potential defects
• The review meeting is led by the author
• Reviewers find potential defects by individual review
• A review report is produced

Which of the following review types is MOST likely being used?

Select ONE option.

12 / 40

12. Given the following statements about the relationships between software development activities and test activities in the software development lifecycle:

1. Each development activity should have a corresponding testing activity
2. Reviewing should start as soon as final versions of documents become available
3. The design and implementation of tests should start during the corresponding development activity
4. Testing activities should start in the early stages of the software development lifecycle

Which of the following CORRECTLY shows which are true and false?

Select ONE option.

13 / 40

13. Which of the following statements on the use of checklists in a formal review is CORRECT?

Select ONE option.

14 / 40

14. A daily radiation recorder for plants produces a sunshine score based on a combination of the number of hours a plant is exposed to the sun (below 3 hours, 3 to 6 hours or above 6 hours) and the average intensity of the sunshine (very low, low, medium, high).

Given the following test cases:

What is the minimum number of additional test cases that are needed to ensure full coverage of ALL VALID INPUT equivalence partitions?

Select ONE option.

15 / 40

15. Consider the following types of defects that a test level might focus on:

a) Defects in separately testable modules or objects
b) Not focused on identifying defects
c) Defects in interfaces and interactions
d) Defects in the whole test object

Which of the following list correctly matches test levels from the Foundation syllabus with the defect focus options given above?

Select ONE option.

16 / 40

16. Which of the following tools is most useful for reporting test metrics?

Select ONE option.

17 / 40

17. The project develops a "smart" heating thermostat. The control algorithms of the thermostat were modeled as Matlab/Simulink models and run on the internet connected server. The thermostat uses the specifications of the server to trigger the heating valves.

The test manager has defined the following test strategy/approach in the test plan:

1. The acceptance test for the whole system is executed as an experience-based test.
2. The control algorithms on the server are checked against standard of the energy saving regulation.
3. The functional test of the thermostat is performed as risk-based testing.
4. The security tests of data / communication via the internet are executed together with external security experts.

What four common types of test strategies/approaches did the test manager implement in the test plan?

Select ONE option.

18 / 40

18. Which one of the following is MOST likely to be a benefit of test execution tools?

Select ONE option.

19 / 40

19. Which one of the statements below describes the most common situation for a failure discovered during testing or in production?

Select ONE option.

20 / 40

20. What is checklist-based testing?

Select ONE option.

21 / 40

21. Which of the following statements CORRECTLY reflects the value of static testing?

Select ONE option.

22 / 40

22. You are engaged in planning a test effort for a new mobile banking application. As part of estimation, you first meet with the proposed testers and others on the project. The team is well-coordinated and has already worked on similar projects. To verify the resulting estimate, you then refer to some industry averages for testing effort and costs on similar projects, published by a reputable consultant.

Which statement accurately describes your estimation approach?

Select ONE option.

23 / 40

23. A video application has the following requirement: The application shall allow playing a video on the following display resolution:

1. 640x480
2. 1280x720
3. 1600x1200
4. 1920x1080

Which of the following list of test cases is a result of applying the equivalence partitioning test technique to test this requirement?

Select ONE option.

24 / 40

24. Which of the following BEST explains a benefit of independent testing?

Select ONE option.

25 / 40

25. As a test manager you are responsible for testing the following parts of requirements:

• R1 - Process anomalies
• R2 - Synchronization
• R3 - Approval
• R4 - Problem solving
• R5 - Financial data
• R6 - Diagram data
• R7 - Changes to the user profile

Notation: Logical requirement dependencies (A -> B means, that B depends on A):

Which one of the following options structures the test execution schedule according to the requirement dependencies?

Select ONE option.

26 / 40

26. You are running a performance test with the objective of finding possible network bottlenecks in interfaces between components of a system. Which of the following statements describes this test?

Select ONE option.

27 / 40

27. Which of the following are two factors that can be used to determine the level of risk?

Select ONE option.

28 / 40

28. Which of the following statements about test types and test levels is CORRECT?

Select ONE option.

29 / 40

29. You are testing a mobile app that allows users to find a nearby restaurant, based on the type of food they want to eat. Consider the following list of test cases, priorities (smaller number is high priority), and dependencies, in the following format:

Which of the following is a possible test execution schedule that considers both priorities and dependencies?

Select ONE option.

30 / 40

30. Which of the following statements is a valid objective for testing?

Select ONE option.

31 / 40

31. Which of the following descriptions of decision coverage is CORRECT?

Select ONE option.

32 / 40

32. Which of the following is LEAST likely to be an example of product risk analysis CORRECTLY influencing the testing?

Select ONE option.

33 / 40

33. In what way can testing be part of Quality Assurance?

Select ONE option.

34 / 40

34. Which of the following statements about test estimation approaches is CORRECT?

Select ONE option.

35 / 40

35. Which of the following should NOT be a trigger for maintenance testing?

Select ONE option.

36 / 40

36. Which of the following CORRECTLY matches the roles and responsibilities in a formal review?

37 / 40

37. Which of the following descriptions of statement coverage is CORRECT?

Select ONE option.

38 / 40

38. A smart home app measures the average temperature in the house over the previous week and provides feedback to the occupants on their environmental friendliness based on this temperature.

The feedback for different average temperature ranges (to the nearest °C) should be:

Up to 10°C - Icy Cool!
11°C to 15°C - Chilled Out!
16°C to 19°C - Cool Man!
20°C to 22°C - Too Warm!
Above 22°C - Hot & Sweaty!

Using BVA (only Min- and Max values), which of the following sets of test inputs provides the highest level of boundary coverage?

Select ONE option.

39 / 40

39. Which of the following is a true statement about exploratory testing?

Select ONE option.

40 / 40

40. Which of the following is an example of a failure in a car cruise control system?

Select ONE option.

0%

Scroll to top