ISTQB Learning

Test your knowledge

0%
35
Created on By Admin

Exam 5

1 / 40

1. Your organization’s test strategy suggests that once a system is going to be retired, data migration shall be tested. As part of what test type is this testing MOST likely to be performed?

Select ONE option.

2 / 40

2. Which of the following BEST describes retrospectives?

Select ONE option.

3 / 40

3. A designer documents a design for a user interface that does not suitably address disabled users because the designer is tired. The programmer implements the user interface in line with the design but as they are working under severe time pressure, they do not include suitable exception handling in their program code for bonus calculations. When the operational system is used, complaints are made by some disabled users about the interface and the company is subsequently fined by the relevant regulatory authority. No one notices that bonus calculations are sometimes incorrect.

Which of the following statements is CORRECT?

Select ONE option.

4 / 40

4. Your test suite S for a program P achieves 100% statement coverage. It consists of three test cases, each of which achieves 50% statement coverage.

Which of the following statements is CORRECT?

Select ONE option.

5 / 40

5. You are testing a user story with three acceptance criteria: AC1, AC2 and AC3. AC1 is covered by test case TC1, AC2 by TC2, and AC3 by TC3. The test execution history had three test runs on three consecutive versions of the software as follows:

Tests are repeated once you are informed that all defects found in the test run are corrected and a new version of the software is available.
Which of the above tests are executed as regression tests?

Select ONE option.

6 / 40

6. You are working as a tester in the team that follows the V-model. The choice of software development lifecycle (SDLC) model impacts the timing of testing, which of the following statement is NOT true?

Select ONE option.

7 / 40

7. Which of the following statements is CORRECT?

Select ONE option.

8 / 40

8. Consider the following acceptance criteria for a user story written from the perspective of an online store owner.

Given that the user is logged in and on the homepage,
When the user clicks on the "Add Item" button,
Then the "Create Item" form should appear,
And the user should be able to input a name and price for the new item.

In what format is this acceptance criteria written?

Select ONE option.

9 / 40

9. Which of the following statements BEST describes the difference between decision table testing and branch testing?

Select ONE option.

10 / 40

10. The following is a list of the work products produced in the SDLC.

i. Business requirements
ii. Schedule
iii. Test budget
iv. Third-party executable code
v. User stories and their acceptance criteria

Which of them can be reviewed?

Select ONE option.

11 / 40

11. You have been assigned as a tester to a team producing a new system incrementally. You have noticed that no changes have been made to the existing regression test cases for several iterations and no new regression defects were identified. Your manager is happy, but you are not. Which testing principle explains your skepticism?

Select ONE option.

12 / 40

12. You are testing a temperature control system for a horticultural cold storage facility. The system receives the temperature (in full degrees Celsius) as the input. If the temperature is between 0 and 2 degrees inclusive, the system displays the message “temperature OK”. For lower temperatures, the system displays the message "temperature too low" and for higher temperatures it displays the message “temperature too high”.

Using two-value boundary value analysis, which of the following sets of test inputs provides the highest level of boundary value coverage?

Select ONE option.

13 / 40

13. Which of the following is MOST likely to describe a task performed by someone in a test management role?

Select ONE option.

14 / 40

14. Which of the following is an example of how product risk analysis may influence the thoroughness and scope of testing?

Select ONE option.

15 / 40

15. Which of the following BEST explains a benefit of independence of testing?

Select ONE option.

16 / 40

16. You work as a tester in a project on a mobile application for food ordering for one of your clients. The client sent you a list of requirements. One of them, with high priority, says

“The order must be processed in less than 10 seconds in 95% of the cases”.

You created a set of test cases in which a number of random orders were made, the processing time measured, and the test results were checked against the requirements.

What test type did you perform?

Select ONE option.

17 / 40

17. One of the ‘principles of testing’ states that exhaustive testing is impossible. Which of the following is an example of addressing this principle in practice?

Select ONE option.

18 / 40

18. Consider the following part of a test plan.

Testing will be performed using component testing and component integration testing. The regulations require to demonstrate that 100% branch coverage is achieved for each component classified as critical.

Which part of the test plan does this part belong to?

Select ONE option.

19 / 40

19. Which of the arguments below would you use to convince your manager to organize retrospectives at the end of each release cycle?

Select ONE option.

20 / 40

20. Which of the following is MOST likely to be a risk of test automation?

Select ONE options.

21 / 40

21. In many software organizations the test department is called the Quality Assurance (QA) department. Is this sentence correct or not and why?

Select ONE option.

22 / 40

22. Which of the following factors (i-v) have SIGNIFICANT influence on the test process?

i. The SDLC
ii. The number of defects detected in previous projects
iii. The identified product risks
iv. New regulatory requirements forcing formal white-box testing
v. The test environment setup

Select ONE option.

23 / 40

23. Given the following testware:

1. Coverage items
2. Change requests
3. Test execution schedule
4. Prioritized test conditions

And the following test activities

A. Test analysis
B. Test design
C. Test implementation
D. Test completion

Which of the following BEST shows the testware produced by the activities?

Select ONE option.

24 / 40

24. Which of the following is MOST likely to be a benefit of test automation?

Select ONE option.

25 / 40

25. Which of the following provides the BEST example of a scenario-oriented acceptance criterion?

Select ONE option.

26 / 40

26. Consider the following defect report for a Book Lending System.

Which of the following is MOST likely to help the developer reproduce the failure quickly?

Select ONE options.

27 / 40

27. Which test activity involves working with test data requirements, test conditions, test environment requirements and test cases?

Select ONE option.

28 / 40

28. Which of the following statements about the independence of testing is CORRECT?

Select ONE option.

29 / 40

29. You are testing a system that calculates the final course grade for a given student.

The final grade is assigned based on the final result, according to the following rules:

• 0 – 50 points: failed
• 51 – 60 points: fair
• 61 – 70 points: satisfactory
• 71 – 80 points: good
• 81 – 90 points: very good
• 91 – 100 points: excellent

You have prepared the following set of test cases:

What is the 2-value Boundary Value Analysis (BVA) coverage for the final result that is achieved with the existing test cases?

Select ONE option.

30 / 40

30. Which of the following is an advantage of the whole team approach?

Select ONE option.

31 / 40

31. Which of the following BEST describe the collaborative approach to user story writing?

Select ONE option.

32 / 40

32. Which of the following is an example of why testing is necessary?

Select ONE option.

33 / 40

33. Which of the following is an example of a test-first approach to development?

Select ONE option.

34 / 40

34. Which of the following CANNOT be examined by static testing?

Select ONE option.

35 / 40

35. How do testers add value to iteration and release planning?

Select ONE option.

36 / 40

36. You were given a task to analyze and fix causes of failures in a new system to be released.

Which activity are you performing?

Select ONE option.

37 / 40

37. You run two test cases, T1 and T2, on the same code. Test T1 achieved 40% statement coverage and test T2 achieved 65% statement coverage.

Which of the following sentences must be necessarily true?

Select ONE option.

38 / 40

38. During risk analysis the team considered the following risk: “The system allows too high a discount for a customer”. The team estimated the risk impact to be very high.

What can one say about the risk likelihood?

Select ONE option.

39 / 40

39. Which of the following is NOT a purpose of a test plan?

Select ONE option.

40 / 40

40. Your team uses planning poker to estimate the test effort for a newly required feature. There is a rule in your team that if there is no time to reach full agreement and the variation in the results is small, applying rules like “accept the number with the most votes” can be applied.
After two rounds, the consensus was not reached, so the third round was initiated. You can see the test estimation results in the table below.

Which of the following is the BEST example of the next step?

Select ONE option.

0%

Scroll to top