ISTQB Learning

Test your knowledge

0%
35
Created on By Admin

Exam 5

1 / 40

1. Which TWO of the following statements provide the BEST rationale for using exploratory testing?

Select TWO options.

2 / 40

2. Which of the following provides the BEST example of a scenario-oriented acceptance criterion?

Select ONE option.

3 / 40

3. Which of the following is an example of a test-first approach to development?

Select ONE option.

4 / 40

4. Which of the following statements about the chosen software development lifecycle is CORRECT?

Select ONE option.

5 / 40

5. You are working as a tester in the team that follows the V-model. The choice of software development lifecycle (SDLC) model impacts the timing of testing, which of the following statement is NOT true?

Select ONE option.

6 / 40

6. Which of the following is an example of a test-first approach to development?

Select ONE option.

7 / 40

7. What is the MAIN difference between black-box test techniques and experience-based test techniques?

Select ONE option.

8 / 40

8. Given the following testware:

1. Coverage items
2. Change requests
3. Test execution schedule
4. Prioritized test conditions

And the following test activities

A. Test analysis
B. Test design
C. Test implementation
D. Test completion

Which of the following BEST shows the testware produced by the activities?

Select ONE option.

9 / 40

9. Given the following benefits and drawbacks of the independence of testing:

i. The testers work in a different location from the developers
ii. Testers question the assumptions programmers make while writing code
iii. A confrontational dynamic has been established between testers and developers
iv. Developers have convinced themselves that testers are mostly accountable for quality
v. Testers have different biases than those held by the developers

Which are MOST likely to be considered benefits?

Select ONE option.

10 / 40

10. Consider the following test categories (1-4) and agile testing quadrants (A-D):

1. Usability testing
2. Component testing
3. Functional testing
4. Reliability testing

A. Agile testing quadrant Q1: technology facing, supporting the development team
B. Agile testing quadrant Q2: business facing, supporting the development team
C. Agile testing quadrant Q3: business facing, critique the product
D. Agile testing quadrant Q4: technology facing, critique the product

How do the following test categories map onto the agile testing quadrants?

Select ONE option.

11 / 40

11. Which of the following is NOT a valid purpose for a test report?

Select ONE options.

12 / 40

12. Which of the following statements about the value of static testing is CORRECT?

Select ONE option.

13 / 40

13. Given the following example defects:

i. Two different parts of the design specification disagree due to the complexity of the design
ii. A response time is too long and so makes users lose patience
iii. A path in the code cannot be reached during execution
iv. A variable is declared but never subsequently used in the program
v. The amount of memory needed by the program to generate a report is too high

Which of the following BEST identifies example defects that could be found by static testing (rather than dynamic testing)?

Select ONE option.

14 / 40

14. Which of the following is MOST likely to describe a task performed by someone in a test management role?

Select ONE option.

15 / 40

15. Given the following review types:

1. Technical review
2. Informal review
3. Inspection
4. Walkthrough

And the following descriptions:

A. Includes objectives such as gaining consensus, generating new ideas, and motivating authors to improve
B. Includes objectives such as educating reviewers, gaining consensus, generating new ideas and detecting potential defects
C. The main objective is detecting potential defects and it requires metrics collection to support process improvement
D. The main objective is detecting potential defects and it generates no formal documented output

Which of the following BEST matches the review types and the descriptions?

Select ONE option.

16 / 40

16. Which of the following is NOT true regarding the test pyramid?

Select ONE option.

17 / 40

17. Which of the following test activities are MOST likely to involve the application of boundary value analysis and equivalence partitioning?

Select TWO options.

18 / 40

18. During risk analysis the team considered the following risk: “The system allows too high a discount for a customer”. The team estimated the risk impact to be very high.

What can one say about the risk likelihood?

Select ONE option.

19 / 40

19. Which of the following options shows an example of test activities that contribute to success?

Select ONE option.

20 / 40

20. How do testers add value to iteration and release planning?

Select ONE option.

21 / 40

21. Which of the following is an advantage of the whole-team approach?

Select ONE option.

22 / 40

22. Which of the following statements BEST describes the difference between testing and debugging?

Select ONE option.

23 / 40

23. Let the branch coverage metric be defined as BCov = (X / Y) * 100%.

What do X and Y represent in this formula?

Select ONE option.

24 / 40

24. Consider the following rule: “for every SDLC activity there is a corresponding test activity”. In which SDLC models does this rule hold?

Select ONE option.

25 / 40

25. You need to update one of the automated test scripts to be in line with a new requirement. Which process indicates that you create a new version of the test script in the test repository?

Select ONE option.

26 / 40

26. Which of the following is a characteristic of experience-based test techniques?

Select ONE option.

27 / 40

27. You were given a task to analyze and fix causes of failures in a new system to be released.

Which activity are you performing?

Select ONE option.

28 / 40

28. You have been assigned as a tester to a team producing a new system incrementally. You have noticed that no changes have been made to the existing regression test cases for several iterations and no new regression defects were identified. Your manager is happy, but you are not. Which testing principle explains your skepticism?

Select ONE option.

29 / 40

29. You are working on a project to develop a system to analyze driving test results. You have been asked to design test cases based on the following decision table.

What test data will show that there are contradictory rules in the decision table?

Select ONE option.

30 / 40

30. What task may management take on during a formal review?

Select ONE option.

31 / 40

31. Which of the following is a factor that contributes to a successful review?

Select ONE option.

32 / 40

32. Which of the following is an advantage of the whole-team approach?

Select ONE option.

33 / 40

33. Which of the following is NOT a benefit of static testing?

Select ONE option.

34 / 40

34. Consider the following acceptance criteria for a user story written from the perspective of an online store owner.

Given that the user is logged in and on the homepage,
When the user clicks on the "Add Item" button,
Then the "Create Item" form should appear,
And the user should be able to input a name and price for the new item.

In what format is this acceptance criteria written?

Select ONE option.

35 / 40

35. You are testing a mobile application that allows customers to access and manage their bank accounts. You are running a test suite that involves evaluating each screen, and each field on each screen, against a general list of user interface best practices derived from a popular book on the topic that maximizes attractiveness, ease-of-use, and accessibility for such applications. Which of the following options BEST categorizes the test technique you are using?

Select ONE option.

36 / 40

36. Which of the following is a benefit of early and frequent stakeholder feedback?

Select ONE option.

37 / 40

37. Which of the following is a benefit of early and frequent feedback?

Select ONE option.

38 / 40

38. Which of the following is MOST likely to be a risk of test automation?

Select ONE options.

39 / 40

39. You want to estimate the test effort for the new project using estimation based on ratios. You calculate the test-to-development effort ratio using averaged data for both development effort and test effort from four historical projects similar to the new one. The table shows this historical data.

The estimated development effort for the new project is $800,000. What is your estimate of the test effort in this project?

Select ONE option.

40 / 40

40. A phone ringing in a neighboring cubicle distracts a programmer causing him to improperly program the logic that checks the upper boundary of an input variable. Later, during system testing, a tester notices that this input field accepts invalid input values.

Which of the following correctly describes an incorrectly coded upper bound?

Select ONE option.

0%

Scroll to top