ISTQB Learning

Test your knowledge

0%
35
Created on By Admin

Exam 5

1 / 40

1. Which of the following is a benefit of early and frequent stakeholder feedback?

Select ONE option.

2 / 40

2. Which of the following test levels is MOST likely being performed if the testing is focused on validation and is not being performed by testers?

Select ONE option.

3 / 40

3. Which participant in the review process is responsible for ensuring that the review meetings run effectively and that everyone at the meetings can voice their opinions freely?

Select ONE option.

4 / 40

4. Which of the following statements about branch testing is CORRECT?

Select ONE option.

5 / 40

5. Which of the following options shows an example of test activities that contribute to success?

Select ONE option.

6 / 40

6. You have just started designing test cases for the following user story.

In all test cases the precondition is as follows: there are only two products available, products A and B. Product A costs $100 and product B costs $110.

Which of the following is the BEST example of a test case for this user story?

Select ONE option.

7 / 40

7. Which of the following statements is CORRECT?

Select ONE option.

8 / 40

8. Which of the following is an example of a test-first approach to development?

Select ONE option.

9 / 40

9. Which of the following is MOST likely to be a benefit of test automation?

Select ONE option.

10 / 40

10. Which of the following BEST describes the concept behind error guessing?

Select ONE option.

11 / 40

11. The following list contains risks that have been identified for a new software product to be developed:

i. Management moves two experienced testers to another project
ii. The system does not comply with functional safety standards
iii. System response time exceeds user requirements
iv. Stakeholders have inaccurate expectations
v. Disabled people have problems when using the system

Which of them are project risks?

Select ONE option.

12 / 40

12. Which of the following BEST describes retrospectives?

Select ONE option.

13 / 40

13. The user reported a software failure. An engineer from the support team asked the user for the software version number where the failure was observed. Based on the version number, the team reassembled all the files that made up the release. This later allowed a developer to perform analysis, find the defect, and fix it.

Which of the following enabled the above activity to be performed by the team?

Select ONE options.

14 / 40

14. Which of the following activities in the test process makes the MOST use of test progress reports?

Select ONE option.

15 / 40

15. Which of the following BEST explains a benefit of independence of testing?

Select ONE option.

16 / 40

16. Which of the following statements BEST describes the difference between decision table testing and branch testing?

Select ONE option.

17 / 40

17. You are testing a mobile application that allows customers to access and manage their bank accounts. You are running a test suite that involves evaluating each screen, and each field on each screen, against a general list of user interface best practices derived from a popular book on the topic that maximizes attractiveness, ease-of-use, and accessibility for such applications. Which of the following options BEST categorizes the test technique you are using?

Select ONE option.

18 / 40

18. Consider the following user story:

As an Editor
I want to review content before it is published
so that I can assure the grammar is correct

and its acceptance criteria:

• The user can log in to the content management system with "Editor" role
• The editor can view existing content pages
• The editor can edit the page content
• The editor can add markup comments
• The editor can save changes
• The editor can reassign to the "content owner" role to make updates

Which of the following is the BEST example of an ATDD test for this user story?

Select ONE option.

19 / 40

19. Given the following risks:

1. Ineffective loop implementation causes long system responses
2. Consumers change their preferences
3. Flooding of the server room
4. Patients above a certain age receive inaccurate reports

And the following mitigation activities:

A. Risk acceptance
B. Performance testing
C. Using boundary value analysis as the test technique
D. Risk transfer

Which of the following BEST matches the risks with the mitigation activities?

Select ONE option.

20 / 40

20. Given the following descriptions of review activities:

1. Detected anomalies are deliberated upon, and determinations are reached regarding their status, ownership, and any further steps needed
2. Issues are recorded, and any needed updates are addressed prior to the acceptance of the work product
3. Reviewers employ techniques to come up with suggestions and questions about the work product and to spot anomalies
4. The objective of the review and its schedule are established to ensure a focused and efficient review
5. Participants are provided with access to the item being reviewed

Which of the following is the CORRECT sequence in the review process of the activities that correspond to the descriptions?

Select ONE option.

21 / 40

21. Which of the following is NOT a valid purpose for a test report?

Select ONE options.

22 / 40

22. In your project there has been a delay in the release of a brand-new application and test execution started late, but you have very detailed domain knowledge and good analytical skills. The full list of requirements has not yet been shared with the team, but management is asking for some test results to be presented.

Which test technique fits BEST in this situation?

Select ONE option.

23 / 40

23. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

24 / 40

24. The system for selling cinema tickets calculates the discount type based on the client’s birth year (BY) and on the current year (CY) as follows:

 

Let D be the difference between CY and BY, that is, D = CY – BY

• If D < 0 then print the error message “birth year cannot be greater than current year”

• If 0 ≤ D < 18 then apply the student discount

• If 18 ≤ D < 65 then apply no discount • If D ≥ 65 then apply the pensioner discount

Your test suite already contains two test cases:

• BY = 1990, CY = 2020, expected result: no discount
• BY = 2030, CY = 2029, expected result: print the error message

Which of the following test data sets should be added to achieve full valid equivalence partitioning coverage for the discount type?

Select TWO options.

25 / 40

25. Which of the following is NOT an example of the shift left approach?

Select ONE option.

26 / 40

26. Consider the following test categories (1-4) and agile testing quadrants (A-D):

1. Usability testing
2. Component testing
3. Functional testing
4. Reliability testing

A. Agile testing quadrant Q1: technology facing, supporting the development team
B. Agile testing quadrant Q2: business facing, supporting the development team
C. Agile testing quadrant Q3: business facing, critique the product
D. Agile testing quadrant Q4: technology facing, critique the product

How do the following test categories map onto the agile testing quadrants?

Select ONE option.

27 / 40

27. During a risk analysis the following risk was identified and assessed:

• Risk: Response time is too long to generate a report
• Risk likelihood: medium; risk impact: high
• Response to risk:

o An independent test team performs performance testing during system testing
o A selected sample of end users performs alpha and beta acceptance testing before the release

What measure is proposed to be taken in response to this analyzed risk?

Select ONE option.

28 / 40

28. Which of the following BEST describes how using checklist-based testing can result in increased coverage?

Select ONE option.

29 / 40

29. You are applying state transition testing to the hotel room reservation system modeled by the following state transition table, with 4 states and 5 different events:

Assuming all test cases start in the ‘Requesting’ state, which of the following test cases, represented as sequences of events, achieves the highest valid transitions coverage?

Select ONE option.

30 / 40

30. Which of the following are product risks?

Select TWO options.

31 / 40

31. You are testing a PIN validator, which accepts valid PINs and rejects invalid PINs. A PIN is a sequence of digits. A PIN is valid if it consists of four digits, at least two of which are different. You have identified the following valid equivalence partitions:

Variable: PIN code length

• The partition “length correct” - four-digit PINs
• The partition “length incorrect” - PINs with length other than 4

Variable: Number of different digits

• The partition “number of different digits correct” - PINs with at least two different digits
• The partition “number of different digits incorrect” - PINs with all digits being the same

Which of the following is a MINIMUM set of input test data that covers all identified equivalence partitions?

Select ONE option.

32 / 40

32. Given the following roles in reviews:

1. Scribe
2. Review leader
3. Facilitator
4. Manager

And the following responsibilities in reviews:

A. Ensures the effective running of review meetings and the setting up a safe review environment
B. Records review information, such as decisions and new anomalies found during the review meeting
C. Decides what is to be reviewed and provides resources, such as staff and time for the review
D. Takes overall responsibility for the review such as organizing when and where the review will take place

Which of the following BEST matches the roles and responsibilities?

Select ONE option.

33 / 40

33. Given the following test tasks:

1. Derive test cases from test conditions
2. Identify reusable testware
3. Organize test cases into test procedures
4. Evaluate test basis and test object

And the following test activities:

A. Test analysis
B. Test design
C. Test implementation
D. Test completion

Which of the following BEST matches the tasks with the activities?

Select ONE option.

34 / 40

34. Decide which of the following statements (i-v) are true for static testing.

i. Abnormal external behaviors are easier to identify with this testing
ii. Discrepancies from a coding standard are easier to find with this testing
iii. It identifies failures caused by defects when the software is run
iv. Its test objective is to identify defects as early as possible
v. Missing coverage for critical security requirements is easier to find and fix

Select ONE option.

35 / 40

35. Which of the following is an example of why testing is necessary?

Select ONE option.

36 / 40

36. Which test activity does a data preparation tool support?

Select ONE option.

37 / 40

37. Given the following testware:

1. Coverage items
2. Change requests
3. Test execution schedule
4. Prioritized test conditions

And the following test activities

A. Test analysis
B. Test design
C. Test implementation
D. Test completion

Which of the following BEST shows the testware produced by the activities?

Select ONE option.

38 / 40

38. Which of the following is NOT anticipated by the tester while applying error guessing?

Select ONE option.

39 / 40

39. Given the following descriptions:

1. Support workflow tracking
2. Facilitate communication
3. Virtual machines
4. Support reviews

And the following test tool categories:

A. Static testing tools
B. Tools supporting scalability and deployment standardization
C. DevOps tools
D. Collaboration tools

Which of the following BEST matches the descriptions and categories?

Explanation / Rationale

40 / 40

40. At the beginning of each iteration, the team estimates the amount of work (in person-days) they will need to complete during the iteration. Let E(n) be the estimated amount of work for iteration n, and let A(n) be the actual amount of work done in iteration n. From the third iteration, the team uses the following estimation model based on extrapolation:

 

 

The graph shows the estimated and actual amount of work for the first four iterations.

What is the estimated amount of work for iteration #5?

Select ONE option.

0%

Scroll to top