ISTQB Learning

Test your knowledge

0%
35
Created on By Admin

Exam 5

1 / 40

1. A phone ringing in a neighboring cubicle distracts a programmer causing him to improperly program the logic that checks the upper boundary of an input variable. Later, during system testing, a tester notices that this input field accepts invalid input values.

Which of the following correctly describes an incorrectly coded upper bound?

Select ONE option.

2 / 40

2. Which of the following is a benefit of early and frequent stakeholder feedback?

Select ONE option.

3 / 40

3. Given the following review types:

1. Technical review
2. Informal review
3. Inspection
4. Walkthrough

And the following descriptions:

A. Includes objectives such as gaining consensus, generating new ideas, and motivating authors to improve
B. Includes objectives such as educating reviewers, gaining consensus, generating new ideas and detecting potential defects
C. The main objective is detecting potential defects and it requires metrics collection to support process improvement
D. The main objective is detecting potential defects and it generates no formal documented output

Which of the following BEST matches the review types and the descriptions?

Select ONE option.

4 / 40

4. Which of the following is a benefit of early and frequent stakeholder feedback?

Select ONE option.

5 / 40

5. Which TWO of the following statements provide the BEST rationale for using exploratory testing?

Select TWO options.

6 / 40

6. Which of the following is NOT an example of the shift left approach?

Select ONE option.

7 / 40

7. You are testing a user story with three acceptance criteria: AC1, AC2 and AC3. AC1 is covered by test case TC1, AC2 by TC2, and AC3 by TC3. The test execution history had three test runs on three consecutive versions of the software as follows:

Tests are repeated once you are informed that all defects found in the test run are corrected and a new version of the software is available.
Which of the above tests are executed as regression tests?

Select ONE option.

8 / 40

8. Which of the following statements about the value of static testing is CORRECT?

Select ONE option.

9 / 40

9. The following is a list of the work products produced in the SDLC.

i. Business requirements
ii. Schedule
iii. Test budget
iv. Third-party executable code
v. User stories and their acceptance criteria

Which of them can be reviewed?

Select ONE option.

10 / 40

10. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

11 / 40

11. Which work product can be used by an agile team to show the amount of work that has been completed and the amount of total work remaining for a given iteration?

Select ONE option.

12 / 40

12. Given the following testware:

1. Coverage items
2. Change requests
3. Test execution schedule
4. Prioritized test conditions

And the following test activities

A. Test analysis
B. Test design
C. Test implementation
D. Test completion

Which of the following BEST shows the testware produced by the activities?

Select ONE option.

13 / 40

13. During risk analysis the team considered the following risk: “The system allows too high a discount for a customer”. The team estimated the risk impact to be very high.

What can one say about the risk likelihood?

Select ONE option.

14 / 40

14. Which of the following is NOT an example of how configuration management supports testing?

Select ONE option.

15 / 40

15. Which of the following factors (i-v) have SIGNIFICANT influence on the test process?

i. The SDLC
ii. The number of defects detected in previous projects
iii. The identified product risks
iv. New regulatory requirements forcing formal white-box testing
v. The test environment setup

Select ONE option.

16 / 40

16. Which types of failures (1-4) fit which test levels (A-D) BEST?

1. Failures in system behavior as it deviates from the user’s business needs
2. Failures in communication between components
3. Failures in logic in a module
4. Failures in not correctly implemented business rules

A. Component testing
B. Component integration testing
C. System testing
D. Acceptance testing

Select ONE option.

17 / 40

17. Which collaborative user story writing practice enables the team to achieve a collective understanding of what needs to be delivered?

Select ONE option.

18 / 40

18. Your team uses the three-point estimation technique to estimate the test effort for a new high-risk feature. The following estimates were made:

• Most optimistic estimation: 2 person-hours
• Most likely estimation: 11 person-hours
• Most pessimistic estimation: 14 person-hours

What is the final estimate?

Select ONE option.

19 / 40

19. Which of the following is MOST likely to be performed as part of system testing?

Select ONE option.

20 / 40

20. Decide which of the following statements (i-v) are true for static testing.

i. Abnormal external behaviors are easier to identify with this testing
ii. Discrepancies from a coding standard are easier to find with this testing
iii. It identifies failures caused by defects when the software is run
iv. Its test objective is to identify defects as early as possible
v. Missing coverage for critical security requirements is easier to find and fix

Select ONE option.

21 / 40

21. The user reported a software failure. An engineer from the support team asked the user for the software version number where the failure was observed. Based on the version number, the team reassembled all the files that made up the release. This later allowed a developer to perform analysis, find the defect, and fix it.

Which of the following enabled the above activity to be performed by the team?

Select ONE options.

22 / 40

22. Which of the following are product risks?

Select TWO options.

23 / 40

23. Which test activity involves working with test data requirements, test conditions, test environment requirements and test cases?

Select ONE option.

24 / 40

24. Which of the following is true about exploratory testing?

Select ONE option.

25 / 40

25. You are using acceptance test-driven development and designing test cases based on the following user story:

Which test case is the MOST reasonable one to test AC3?

Select ONE option.

26 / 40

26. Which of the following is NOT a valid purpose for a test report?

Select ONE options.

27 / 40

27. The team wants to estimate the time needed for one tester to execute four test cases for a software component. The team has gathered the following measures of the effort used to execute a single test case:

• Best-case scenario: 1 hour
• Worst-case scenario: 8 hours
• Most likely scenario: 3 hours

Given that the three-point estimation technique is being used, what is the final estimate of the time needed to execute all four test cases?

Select ONE option.

28 / 40

28. The table shows the traceability matrix from test cases to requirements. “X” means that a given test case covers the corresponding requirement.

You want to prioritize the test cases following the additional coverage prioritization technique.

You execute all four test cases.

Which test case should be executed as the LAST one?

Select ONE options.

29 / 40

29. A storage system can store up to three elements and is modeled by the following state transition diagram. The variable N represents the number of currently stored elements.

Which of the following test cases, represented as sequences of events, achieves the highest level of valid transitions coverage?

Select ONE option.

30 / 40

30. You work in a team that develops a mobile application for food ordering. In the current iteration the team decided to implement the payment functionality.

Which of the following activities is a part of test analysis?

Select ONE option.

31 / 40

31. One of the ‘principles of testing’ states that exhaustive testing is impossible. Which of the following is an example of addressing this principle in practice?

Select ONE option.

32 / 40

32. Which of the following BEST describes retrospectives?

Select ONE option.

33 / 40

33. You are applying state transition testing to the hotel room reservation system modeled by the following state transition table, with 4 states and 5 different events:

Assuming all test cases start in the ‘Requesting’ state, which of the following test cases, represented as sequences of events, achieves the highest valid transitions coverage?

Select ONE option.

34 / 40

34. Which of the following statements BEST describes the acceptance test-driven development (ATDD) approach?

Select ONE option.

35 / 40

35. Which of the following is an example of a test-first approach to development?

Select ONE option.

36 / 40

36. Your team uses planning poker to estimate the test effort for a newly required feature. There is a rule in your team that if there is no time to reach full agreement and the variation in the results is small, applying rules like “accept the number with the most votes” can be applied.
After two rounds, the consensus was not reached, so the third round was initiated. You can see the test estimation results in the table below.

Which of the following is the BEST example of the next step?

Select ONE option.

37 / 40

37. Which of the following statements about the independence of testing is CORRECT?

Select ONE option.

38 / 40

38. At the beginning of each iteration, the team estimates the amount of work (in person-days) they will need to complete during the iteration. Let E(n) be the estimated amount of work for iteration n, and let A(n) be the actual amount of work done in iteration n. From the third iteration, the team uses the following estimation model based on extrapolation:

 

 

The graph shows the estimated and actual amount of work for the first four iterations.

What is the estimated amount of work for iteration #5?

Select ONE option.

39 / 40

39. What is the MAIN difference between black-box test techniques and experience-based test techniques?

Select ONE option.

40 / 40

40. Which of the following is MOST likely to be a challenge encountered when implementing DevOps?

Select ONE option.

0%

Scroll to top