ISTQB Learning

Test your knowledge

0%
35
Created on By Admin

Exam 5

1 / 40

1. Which types of failures (1-4) fit which test levels (A-D) BEST?

1. Failures in system behavior as it deviates from the user’s business needs
2. Failures in communication between components
3. Failures in logic in a module
4. Failures in not correctly implemented business rules

A. Component testing
B. Component integration testing
C. System testing
D. Acceptance testing

Select ONE option.

2 / 40

2. How do testers add value to iteration and release planning?

Select ONE option.

3 / 40

3. Consider the following defect report for a web-based shopping application:

What is the MOST important information that is missing from this report?

Select ONE option.

4 / 40

4. High-level test conditions are being used by testers to generate test cases and execute tests. Even though the test conditions remain the same, the test cases are varied each time. Which of the following ‘principles of testing’ is being addressed through the variation of test cases?

Select ONE option.

5 / 40

5. Which of the following is NOT an example of how configuration management supports testing?

Select ONE option.

6 / 40

6. Which of the following is an example of a test-first approach to development?

Select ONE option.

7 / 40

7. At the beginning of each iteration, the team estimates the amount of work (in person-days) they will need to complete during the iteration. Let E(n) be the estimated amount of work for iteration n, and let A(n) be the actual amount of work done in iteration n. From the third iteration, the team uses the following estimation model based on extrapolation:

 

 

The graph shows the estimated and actual amount of work for the first four iterations.

What is the estimated amount of work for iteration #5?

Select ONE option.

8 / 40

8. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

9 / 40

9. Which of the following is a benefit of early and frequent stakeholder feedback?

Select ONE option.

10 / 40

10. A designer documents a design for a user interface that does not suitably address disabled users because the designer is tired. The programmer implements the user interface in line with the design but as they are working under severe time pressure, they do not include suitable exception handling in their program code for bonus calculations. When the operational system is used, complaints are made by some disabled users about the interface and the company is subsequently fined by the relevant regulatory authority. No one notices that bonus calculations are sometimes incorrect.

Which of the following statements is CORRECT?

Select ONE option.

11 / 40

11. Let the branch coverage metric be defined as BCov = (X / Y) * 100%.

What do X and Y represent in this formula?

Select ONE option.

12 / 40

12. Which of the following BEST define EXIT criteria in a testing project?

Select TWO options.

13 / 40

13. Which of the following is an example of why testing is necessary?

Select ONE option.

14 / 40

14. Which of the following is a benefit of early and frequent feedback?

Select ONE option.

15 / 40

15. The user reported a software failure. An engineer from the support team asked the user for the software version number where the failure was observed. Based on the version number, the team reassembled all the files that made up the release. This later allowed a developer to perform analysis, find the defect, and fix it.

Which of the following enabled the above activity to be performed by the team?

Select ONE options.

16 / 40

16. Which of the following CANNOT be examined by static testing?

Select ONE option.

17 / 40

17. You have been assigned as a tester to a team producing a new system incrementally. You have noticed that no changes have been made to the existing regression test cases for several iterations and no new regression defects were identified. Your manager is happy, but you are not. Which testing principle explains your skepticism?

Select ONE option.

18 / 40

18. Which of the following is an example of how product risk analysis may influence the thoroughness and scope of testing?

Select ONE option.

19 / 40

19. Given the following example defects:

i. Two different parts of the design specification disagree due to the complexity of the design
ii. A response time is too long and so makes users lose patience
iii. A path in the code cannot be reached during execution
iv. A variable is declared but never subsequently used in the program
v. The amount of memory needed by the program to generate a report is too high

Which of the following BEST identifies example defects that could be found by static testing (rather than dynamic testing)?

Select ONE option.

20 / 40

20. What is the MAIN difference between black-box test techniques and experience-based test techniques?

Select ONE option.

21 / 40

21. Which of the following is an example of how product risk analysis influences thoroughness and scope of testing?

Select ONE option.

22 / 40

22. Which of the following is true about exploratory testing?

Select ONE option.

23 / 40

23. Which of the following are product risks?

Select TWO options.

24 / 40

24. Which TWO of the following options are the exit criteria for testing a system?

Select TWO options.

25 / 40

25. Which of the following is NOT a valid purpose for a test report?

Select ONE options.

26 / 40

26. Which of the following statements about the different testing roles is MOST likely to be CORRECT?

Select ONE option.

27 / 40

27. Which of the following is MOST likely to be a risk of test automation?

Select ONE options.

28 / 40

28. Which of the following is MOST likely to impact how testing is performed for a given test object?

Select ONE option.

29 / 40

29. Given the following benefits and drawbacks of the independence of testing:

i. The testers work in a different location from the developers
ii. Testers question the assumptions programmers make while writing code
iii. A confrontational dynamic has been established between testers and developers
iv. Developers have convinced themselves that testers are mostly accountable for quality
v. Testers have different biases than those held by the developers

Which are MOST likely to be considered benefits?

Select ONE option.

30 / 40

30. Which of the following is a factor that contributes to a successful review?

Select ONE option.

31 / 40

31. You are designing test cases based on the following state transition diagram:

What is the MINIMUM number of test cases required to achieve 100% valid transitions coverage?

Select ONE option.

32 / 40

32. Which of the following are advantages of DevOps?

i. Faster product release and faster time to market
ii. Increases the need for repetitive manual testing
iii. Constant availability of executable software
iv. Reduction in the number of regression tests associated with code refactoring
v. Setting up the test automation framework is inexpensive since everything is automated

Select ONE option.

33 / 40

33. Which of the following BEST describes the way acceptance criteria can be documented?

Select ONE option.

34 / 40

34. Which test activity involves working with test data requirements, test conditions, test environment requirements and test cases?

Select ONE option.

35 / 40

35. Which of the following is a product quality metric?

Select ONE option.

36 / 40

36. You are preparing a test execution schedule for executing seven test cases TC 1 to TC 7.

The following figure includes the priorities of these test cases (1=highest priority, 3 = lowest priority).

The figure also shows the dependencies between test cases using arrows. For instance, the arrow from TC 4 to TC 5 means that TC 5 can only be executed if TC 4 was previously executed.

Which test case should be executed sixth?

Select ONE option.

37 / 40

37. You are testing a mobile application that allows users to find a nearby restaurant based on the type of food they want to eat. Consider the following list of test cases, priorities (i.e., a smaller number means a higher priority), and dependencies:

Which of the following test cases should be executed as the third one?

Select ONE option.

38 / 40

38. You have just started designing test cases for the following user story.

In all test cases the precondition is as follows: there are only two products available, products A and B. Product A costs $100 and product B costs $110.

Which of the following is the BEST example of a test case for this user story?

Select ONE option.

39 / 40

39. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

40 / 40

40. Your test suite S for a program P achieves 100% statement coverage. It consists of three test cases, each of which achieves 50% statement coverage.

Which of the following statements is CORRECT?

Select ONE option.

0%

Scroll to top