0% 3 12345678910111213141516171819202122232425262728293031323334353637383940 Created on June 25, 2024 By Admin 2018v3.1 - Exam 4 - 75 minutes Name 1 / 40 1. Consider the following types of defects that a test level might focus on: a) Defects in separately testable modules or objects b) Not focused on identifying defects c) Defects in interfaces and interactions d) Defects in the whole test object Which of the following list correctly matches test levels from the Foundation syllabus with the defect focus options given above? a) 1 = performance test; 2 = component test; 3 = system test; 4 = acceptance test b) 1 = component test; 2 = acceptance test; 3 = system test; 4 = integration test c) 1 = component test; 2 = acceptance test; 3 = integration test; 4 = system test d) 1 = integration test; 2 = system test; 3 = component test; 4 = acceptance test Select ONE option. Explanation / Rationale Performance testing is a test type, not a test level. Component testing focuses on defects in separately testable modules or objects, integration testing on defects in interfaces and interactions, system testing on defects in the whole test object, and acceptance testing is not typically focused on identifying defects. Thus: a) Is not correct b) Is not correct c) Is correct d) Is not correct 2 / 40 2. Which of the following BEST describes how value is added by maintaining traceability between the test basis and test artifacts? a) Maintenance testing can be fully automated based on changes to the initial requirements b) It is possible to determine if a new test case has increased coverage of the requirements c) Test managers can identify which testers found the highest severity defects d) Areas that may be impacted by side-effects of a change can be targeted by confirmation testing Select ONE option. Explanation / Rationale a) Is not correct. Traceability will allow existing test cases to be linked with updated and deleted requirements (although there is no support for new requirements), but it will not help with the automation of maintenance testing b) Is correct. If all test cases are linked with requirements, then whenever a new test case (with traceability) is added, it is possible to see if any previously uncovered requirements are covered by the new test case c) Is not correct. Traceability between the test basis and test artifacts will not provide information on which testers found high-severity defects, and, even if this information could be determined, it would be of limited value d) Is not correct. Traceability can help with identifying test cases affected by changes, however areas impacted by side-effects would be the focus of regression testing 3 / 40 3. An employee’s bonus is to be calculated. It cannot be negative, but it can be calculated down to zero. The bonus is based on the length of employment: • Less than or equal to 2 years • More than 2 years but less than 5 years • 5 to 10 years inclusively • Longer than 10 years What is the minimum number of test cases required to cover all valid equivalence partitions for calculating the bonus? a) 3 b) 5 c) 2 d) 4 Select ONE option. Explanation / Rationale a) Is not correct. One too few (see the four correct partitions in the correct answer) b) Is not correct. One too much (see the four correct partitions in the correct answer) c) Is not correct. Two too few (see the four correct partitions in the correct answer) d) Is correct. The 4 equivalence partitions correspond to the description in the question, i.e., at least one test case must be created for each equivalence partition: 1. Equivalence partition: 0 ≤ employment time ≤ 2 2. Equivalence partition: 2 < employment time < 5 3. Equivalence partition: 5 ≤ employment time ≤ 10 4. Equivalence partition: 10 < employment time 4 / 40 4. A mass market operating system software product is designed to run on any PC hardware with an x86-family processor. You are running a set of tests to look for defects related to support of the various PCs that use such a processor and to build confidence that important PC brands will work. What type of test are you performing? a) Performance test b) Processor test c) Functional test d) Portability test Select ONE option. Explanation / Rationale a) Is not correct. The test described is a non-functional test, it is a portability test, not a performance test b) Is not correct. Processor test is not a defined test type c) Is not correct. The test described is a non-functional test, specifically a portability test d) Is correct. Testing supported devices is a non-functional test, specifically a portability test 5 / 40 5. The reviews being used in your organization have the following attributes: • There is a role of a scribe • The purpose is to detect potential defects • The review meeting is led by the author • Reviewers find potential defects by individual review • A review report is produced Which of the following review types is MOST likely being used? a) Informal Review b) Walkthrough c) Technical Review d) Inspection Select ONE option. Explanation / Rationale Considering the attributes: • There is a role of a scribe – specified for walkthroughs, technical reviews, and inspections; thus, the reviews being performed cannot be informal reviews • The purpose is to detect potential defects – the purpose of detecting potential defects is specified for all types of review. • The review meeting is led by the author – this is not allowed for inspections and is typically not the author for technical reviews, but is part of walkthroughs, and allowed for informal reviews • Reviewers find potential issues by individual review - all types of reviews can include individual review (even informal reviews) • A review report is produced - all types of reviews can produce a review report, although it would be less likely for an informal review Thus: a) Is not correct b) Is correct c) Is not correct d) Is not correct 6 / 40 6. Which of the following BEST matches the descriptions with the different categories of test techniques? 1. Coverage is measured based on a selected structure of the test object 2. The processing within the test object is checked 3. Tests are based on defects’ likelihood and their distribution 4. Deviations from the requirements are checked 5. User stories are used as the test basis Using notation for the following 4 options: Black - Black-box test techniques White - White-box test techniques Experience - Experience-based test techniques a) Black – 4, 5 White – 1, 2; Experience – 3 b) Black – 3 White – 1, 2; Experience – 4, 5 c) Black – 4 White – 1, 2; Experience – 3, 5 d) Black – 1, 3, 5 White – 2; Experience – 4 Select ONE option. Explanation / Rationale The correct pairing of descriptions with the different categories of test techniques is: • Black-box test techniques Deviations from the requirements are checked (4) User stories are used as the test basis (5) • White-box test techniques Coverage is measured based on a selected structure of the test object (1) The processing within the test object is checked (2) • Experience-based test techniques Tests are based on defects’ likelihood and their distribution (3) Thus: a) Is correct b) Is not correct c) Is not correct d) Is not correct 7 / 40 7. You are working as a tester on an Agile team and have participated in over two dozen user story refinement sessions with the product owner and the developers on the team at the start of each iteration. As the reviews have gotten more effective at detecting defects in user stories and the product owner more proficient at correcting those defects, you and the team notice that the team’s velocity, as shown in your burndown charts, has started to increase. Which of the following is a benefit of static testing that is MOST DIRECTLY related to the team’s increased velocity? a) Increasing total cost of quality b) Reducing testing cost c) Increasing development productivity d) Reducing total cost of quality Select ONE option. Explanation / Rationale a) Is not correct. Reviews reduce, not increase, the total cost of quality b) Is not correct. Increasing velocity is a sign of increasing development productivity overall, not just testing, so B only partially applies c) Is correct. Velocity is a way of measuring productivity in Agile development d) Is not correct. The benefit mentioned here has to do with increasing overall development team productivity 8 / 40 8. Which of the following statements about test estimation approaches is CORRECT? a) With the metrics-based approach, the estimate is based on test measures from the project and so this estimate is only available after the testing starts b) With the expert-based approach, a group of expert users identified by the client recommends the necessary testing budget c) With the expert-based approach, the test managers responsible for the different testing activities predict the expected testing effort d) With the metrics-based approach, an average of the testing costs recorded from several past projects is used as the testing budget Select ONE option. Explanation / Rationale a) Is not correct. Estimates may be updated as more information becomes available, but estimates are needed to assist with planning before the testing starts b) Is not correct. In the expert-based approach, the experts need to be experts in testing, not in using the test object c) Is correct. Test Managers, who will be leading testers doing the testing, are considered experts in their respective areas and suitable for estimating the necessary resources needed d) Is not correct. While it is useful to know the testing costs from previous projects, a more sophisticated approach is needed than simply taking an average of past projects (the new project may not be like the previous projects, e.g., it may be far larger or far smaller than previous projects) 9 / 40 9. Which of the following statements about test types and test levels is CORRECT? a) Functional and non-functional testing can be performed at system and acceptance test levels, while white-box testing is restricted to component and integration testing b) Functional testing can be performed at any test level, while white-box testing is restricted to component testing c) It is possible to perform functional, non-functional and white-box testing at any test level d) Functional and non-functional testing can be performed at any test level, while white-box testing is restricted to component and integration testing Select ONE option. Explanation / Rationale a) Is not correct. It is possible to perform any of the test types (functional, non-functional, white-box) at any test level - so, although it is correct that functional and non-functional testing can be performed at system and acceptance test levels, it is incorrect to state that white-box testing is restricted to component and integration testing b) Is not correct. It is possible to perform any of the test types (functional, non-functional, white-box) at any test level - so, it is incorrect to state that white-box testing is restricted to component testing c) Is correct. It is possible to perform any of the test types (functional, non-functional, white-box) at any test level d) Is not correct. It is possible to perform any of the test types (functional, non-functional, white-box) at any test level - so, it is incorrect to state that white-box testing is restricted to component testing and integration testing 10 / 40 10. As a result of risk analysis, more testing is being directed to those areas of the system under test where initial testing found more defects than average. Which of the following testing principles is being applied? a) Beware of the pesticide paradox b) Testing is context dependent c) Absence-of-errors is a fallacy d) Defects cluster together Select ONE option. Explanation / Rationale a) Is not correct. ‘Beware of the pesticide paradox’ is concerned with re-running the same tests and their fault-finding effectiveness decreasing b) Is not correct. This testing principle is concerned with performing testing differently based on the context (e.g., games vs safety-critical) c) Is not correct. This testing principle is concerned with the difference between a tested and fixed system and a validated system. No ‘errors’ does not mean the system is fit for use d) Is correct. If clusters of defects are identified (areas of the system containing more defects than average), then testing effort should be focused on these areas 11 / 40 11. You are defining the process for carrying out product risk analysis as part of each iteration on an Agile project. Which of the following is the proper place to document this process in a test plan? a) Scope of testing b) Approach of testing c) Metrics of testing d) Configuration management of the test object Select ONE option. Explanation / Rationale a) Is not correct. While scope is a topic addressed in a test plan, the implementation of a risk-based testing strategy on this project is the approach, so this topic should be addressed in that section b) Is correct. Approach is a topic addressed in a test plan and the implementation of a risk-based testing strategy on this project is the approach c) Is not correct. While metrics for test monitoring and control is a topic addressed in a test plan, the implementation of a risk-based testing strategy on this project is the approach, so this topic should be addressed in that section d) Is not correct. Configuration management is not a topic addressed in a test plan 12 / 40 12. Which of the following is MOST likely to be an example of a PRODUCT risk? a) The expected security features may not be supported by the system architecture b) The developers may not have time to fix all the defects found by the test team c) The test cases may not provide full coverage of the specified requirements d) The performance test environment may not be ready before the system is due for delivery Select ONE option. Explanation / Rationale a) Is correct. If the expected security features are not supported by the system architecture, then the system could be seriously flawed. As the system being produced is the problem here, it is a product risk b) Is not correct. If the developers run over budget, or run out of time, that is a problem with the running of the project – it is a project risk c) Is not correct. If the test cases do not provide full coverage of the requirements, this means the testing may not fulfil the requirements of the test plan – it is a project risk d) Is not correct. If the test environment is not ready, this means the testing may not be done, or it may have to be done on a different environment and it is impacting how the project is run – it is a project risk 13 / 40 13. A phone ringing momentarily distracts a programmer, causing the programmer to improperly program the logic that checks the upper boundary of an input variable. Later, during system testing, a tester notices that this input field accepts invalid input values. The improperly coded logic for the upper boundary check is: a) The root-cause b) The failure c) The error d) The defect Select ONE option. Explanation / Rationale a) Is not correct. The root cause is the distraction that the programmer experienced while programming b) Is not correct. The accepting of invalid inputs is the failure c) Is not correct. The error is the mistaken thinking that resulted in putting the defect in the code d) Is correct. The problem in the code is a defect 14 / 40 14. The following statement refers to decision coverage: “When the code contains only a single ‘if’ statement and no loops or CASE statements, and its execution is not nested within the test, any single test case we run will result in 50% decision coverage.” Which of the following statement is correct? a) The statement is true. Any single test case provides 100% statement coverage and therefore 50% decision coverage b) The statement is true. Any single test case would cause the outcome of the “if” statement to be either true or false c) The statement is false. A single test case can only guarantee 25% decision coverage in this case d) The statement is false. The statement is too broad. It may be correct or not, depending on the tested software Select ONE option. Explanation / Rationale a) Is not correct. While the given statement is true, the explanation is not. The relationship between statement and decision coverage is misrepresented b) Is correct. Since any test case will cause the outcome of the “if” statement to be either TRUE or FALSE, by definition we achieved 50% decision coverage c) Is not correct. A single test case can give more than 25% decision coverage, this means according to the statement above always 50 % decision coverage d) Is not correct. The statement is specific and always true, because each test case achieves 50 % decision coverage 15 / 40 15. Which of the following is a typical objective of testing? a) To find defects and failures b) To validate the project plan works as required c) Ensuring of complete testing d) Comparing actual results with expected results Select ONE option. Explanation / Rationale a) Is correct. One of the major objectives of testing b) Is not correct. Validation of the project plan would be a project management activity c) Is not correct. Contradiction to principle #2; complete/exhaustive testing is not possible d) Is not correct. “Comparing actual results with expected results” is a test performing activity, but not a test objective 16 / 40 16. Consider the following list of undesirable outcomes that could occur on a mobile app development effort: A. Incorrect totals on screens B. Change to acceptance criteria during acceptance testing C. Users find the soft keyboard too hard to use with your app D. System responds too slowly to user input during search string entry E. Testers not allowed to report test results in daily standup meetings Which of the following properly classifies these outcomes as project and product risks? a) Product risks: B, E; Project risks: A, C, D b) Product risks: A, C, D; Project risks: B, E c) Product risks: A, C, D, E Project risks: B d) Product risks: A, C Project risks: B, D, E Select ONE option. Explanation / Rationale Product risks exist when a work product may fail to satisfy legitimate needs, while project risks are situations that could have a negative impact on the project’s ability to achieve its objectives. So: A. Incorrect totals on screens = product risk B. Change to acceptance criteria during acceptance testing = project risk C. Users find the soft keyboard too hard to use with your app = product risk D. System responds too slowly to user input during search string entry = product risk E. Testers not allowed to report test results in daily standup meetings = project risk Thus: a) Is not correct. This list is entirely backwards b) Is correct c) Is not correct. While E is about product quality and product risks, the failure to communicate test results is a project risk per the syllabus d) Is not correct. Product risks can be functional and non-functional, so d is also a product risk 17 / 40 17. Which one of the following is NOT included in a test summary report? a) Defining pass/fail criteria and objectives of testing b) Deviations from the test approach c) Measurements of actual progress against exit criteria d) Evaluation of the quality of the test object Select ONE option. Explanation / Rationale a) Is correct. This information has been defined earlier in the test project b) Is not correct. This information is included in a test report: information on what occurred during a test period c) Is not correct. This information is included in a test report: • Status of testing and product quality with respect to the exit criteria or definition of done • Metrics of defects, test cases, test coverage, activity progress, and resource consumption d) Is not correct. This information is included in a test report: Information and metrics to support recommendations and decisions about future actions, such as an assessment of defects remaining, the economic benefit of continued testing, outstanding risks, and the level of confidence in the tested software 18 / 40 18. Match the following test work products (1-4) with the right description (A-D). 1. Test suite 2. Test case 3. Test script 4. Test charter A. A set of test scripts to be executed in a specific test run B. A set of instructions for the execution of a test C. Contains expected results D. Documentation of test activities in session-based exploratory testing a) 1A, 2C, 3B, 4D b) 1D, 2B, 3A, 4C c) 1A, 2C, 3D, 4B d) 1D, 2C, 3B, 4A Select ONE option. Explanation / Rationale Glossary defines the following tests as: • Test suite: “A set of test scripts or test procedures to be executed in a specific test run.” (1A) • Test case: “A set of preconditions, inputs, actions (where applicable), expected results and post conditions, developed based on test conditions” (2C) • Test script: “A sequence of instructions for the execution of a test” (3B) • Test charter: “Documentation of test activities in session-based exploratory testing” (4D) Thus: a) Is correct b) Is not correct c) Is not correct d) Is not correct 19 / 40 19. Which one of the statements below describes the most common situation for a failure discovered during testing or in production? a) The product crashed when the user selected an option in a dialog box b) The wrong version of a compiled source code file was included in the build c) The computation algorithm used the wrong input variables d) The developer misinterpreted the requirement for the algorithm Select ONE option. Explanation / Rationale a) Is correct. A crash is clearly noticeable by the user b) Is not correct. This is a defect, not a failure since there is something wrong in the code. It may not result in a visible or noticeable failure, for example if the changes in the source code file are only in comments c) Is not correct. The use of wrong input variables may not result in a visible or noticeable failure, for example if nobody uses this particular algorithm; or if the wrong input variable has a similar value to the correct input variable; or if the FALSE result of the algorithm is not used d) Is not correct. This type of fault will not necessarily lead to a failure; for example, if no one uses this special algorithm 20 / 40 20. Which of the following provides the definition of the term test case? a) Subset of the value domain of a variable within a component or system in which all values are expected to be treated the same based on the specification b) A set of preconditions, inputs, actions, expected results and post conditions, developed based on test conditions c) Work products produced during the test process for use in planning, designing, executing, evaluating, and reporting on testing d) A source to determine an expected result to compare with the actual result of the system under test Select ONE option. Explanation / Rationale a) Is not correct. Based on definition of equivalence partition b) Is correct. Based on definition from Glossary c) Is not correct. Based on Glossary definition of testware d) Is not correct. Based on definition of test oracle 21 / 40 21. Which of the following statements comparing component testing and system testing is TRUE? a) Component testing verifies the functionality of software modules, program objects, and classes that are separately testable, whereas system testing verifies interfaces between components and interactions between different parts of the system b) Test cases for component testing are usually derived from component specifications, design specifications, or data models, whereas test cases for system testing are usually derived from requirement specifications or use cases c) Component testing only focuses on functional characteristics, whereas system testing focuses on functional and non-functional characteristics d) Component testing is the responsibility of the testers, whereas system testing typically is the responsibility of the users of the system Select ONE option. Explanation / Rationale a) Is not correct. System testing does not test interfaces between components and interactions between different parts of the system; this is a target of integration tests b) Is correct. Examples of work products that can be used as a test basis for component testing include detailed design, code, data model, component specifications. Examples of work products for system testing include system and software requirement specifications (functional and non-functional) use cases c) Is not correct. Component testing does not ONLY focus on functional characteristics d) Is not correct. Component tests are also executed by developers, whereas system testing typically is the responsibility of (independent) testers 22 / 40 22. You are engaged in planning a test effort for a new mobile banking application. As part of estimation, you first meet with the proposed testers and others on the project. The team is well-coordinated and has already worked on similar projects. To verify the resulting estimate, you then refer to some industry averages for testing effort and costs on similar projects, published by a reputable consultant. Which statement accurately describes your estimation approach? a) A simultaneous expert-based and metrics-based approach b) Primarily an expert-based approach, augmented with a metrics-based approach c) Primarily a metrics-based approach, augmented with an expert-based approach d) Primarily planning poker, checked by velocity from burndown charts Select ONE option. Explanation / Rationale a) Is not correct. The two methods are used sequentially, not simultaneously b) Is correct. The primary sources of information come from the experienced testers, who are the experts. The consultant’s industry averages augment the original estimate from published metrics c) Is not correct. The expert-based approach is the primary approach, augmented by a metrics-based approach d) Is not correct. We do not know if this project is following Agile methods, and burndown charts do not come from external consultants 23 / 40 23. Which of the following is a true statement about exploratory testing? a) More experienced testers who have tested similar applications and technologies are likely to do better than less experienced testers at exploratory testing b) Exploratory testing does not identify any additional tests beyond those that would result from formal test techniques c) The time required to complete an exploratory testing session cannot be predicted in advance d) Exploratory testing can involve the use of black-box techniques but not white-box techniques Select ONE option. Explanation / Rationale a) Is correct. Exploratory testing is a form of experience-based testing, which benefits from the skills and experience of the tester b) b) Is not correct. Exploratory testing is useful to complement formal testing techniques c) Is not correct. In session-based test management, exploratory testing is conducted within a defined time-box, and the tester uses a test charter containing test objectives to guide the testing d) Is not correct. Exploratory testing can incorporate the use of other black-box, white-box, and experience-based techniques referenced in this syllabus 24 / 40 24. You are testing an e-commerce system that sells cooking supplies such as spices, flour, and other items in bulk. The units in which the items are sold are either grams (for spices and other expensive items) or kilograms (for flour and other inexpensive items). Regardless of the units, the smallest valid order amount is 0.5 units (e.g., half a gram of cardamom pods) and the largest valid order amount is 25.0 units (e.g., 25 kilograms of sugar). The precision of the units’ field is 0.1 units. Which of the following is a MINIMAL set of input values that cover the equivalence partitions for this field? a) 10.0, 28.0 b) 0.4, 0.5, 25.0, 25.1 c) 0.2, 0.9, 29.5 d) 12.3 Select ONE option. Explanation / Rationale There are three equivalence partitions, with the boundaries as shown: • Invalid too low (0.4 and below) • Valid (0.5 to 25.0) • Invalid too high (25.1 and above) Thus: a) Is not correct. Only two of the equivalence partitions are covered in this set of tests b) Is not correct. Each of those four boundary values are included in this set of tests, but the question asked for equivalence partition coverage with minimal tests, so either 0.5 or 25.0 should be dropped c) Is correct. Each of these three equivalence partitions are covered in this set of tests d) Is not correct. Only one of those equivalence partitions is covered by this test 25 / 40 25. Which of the following should NOT be a trigger for maintenance testing? a) Decision to test the maintainability of the software b) Decision to test the system after migration to a new operating platform c) Decision to test if archived data is possible to be retrieved d) Decision to test after “hot fixes” Select ONE option. Explanation / Rationale a) Is correct. This is maintainability testing, not maintenance testing b) Is not correct. This is a trigger for maintenance testing: Operational tests of the new environment as well as of the changed software c) Is not correct. This is the trigger for maintenance testing: testing restore/retrieve procedures after archiving for long retention periods d) Is not correct. This is the trigger for maintenance testing: Reactive modification of a delivered software product to correct emergency defects that have caused actual failures 26 / 40 26. Consider the following decision table for the portion of an online airline reservation system that allows frequent flyers to redeem points for reward travel: Suppose that there are two equivalence partitions for the condition where “Account/password okay” is not true, one where the account is invalid and another where the account is valid, but the password is invalid. Suppose that there is only one equivalence partition corresponding to the condition where “Account/password okay” is true, where both the account and password are valid. If you want to design tests to cover the equivalence partitions for “Account/password okay” and also for this portion of the decision table, what is the minimum number of tests required? a) 2 b) 3 c) 4 d) 9 Select ONE option. Explanation / Rationale There is at least one test for each column in the decision table. However, column one requires two tests, one where the account is invalid and another where the account is valid, but the password is invalid, so the minimum number of tests is four. Thus: a) Is not correct b) Is not correct c) Is correct d) Is not correct 27 / 40 27. Which one of the following is the BEST definition of an incremental development model? a) Defining requirements, designing software and testing are done in phases where in each phase a piece of the system is added b) A phase in the development process should begin when the previous phase is complete c) Testing is viewed as a separate phase which takes place after development has been completed d) Testing is added to development as an increment Select ONE option. Explanation / Rationale a) Is correct. Incremental development involves establishing requirements, designing, building, and testing a system in pieces b) Is not correct. This is a sequential model c) Is not correct. This describes the waterfall model d) Is not correct. Testing alone is not an increment/additional step in the development 28 / 40 28. A daily radiation recorder for plants produces a sunshine score based on a combination of the number of hours a plant is exposed to the sun (below 3 hours, 3 to 6 hours or above 6 hours) and the average intensity of the sunshine (very low, low, medium, high). Given the following test cases: What is the minimum number of additional test cases that are needed to ensure full coverage of ALL VALID INPUT equivalence partitions? a) 1 b) 2 c) 3 d) 4 Select ONE option. Explanation / Rationale The following valid input equivalence partitions can be identified: • Hours 1. Below 3 hours 2. 3 to 6 hours 3. Above 6 hours • Intensity 4. Very low 5. Low 6. Medium 7. High The given test cases cover the following valid input equivalence partitions: Thus, the missing valid input equivalence partitions are: (2), (5) and (7). These can be covered by two test cases, as (2) can be combined with either (5) or (7). Thus: a) Is not correct b) Is correct c) Is not correct d) Is not correct 29 / 40 29. Which of the following is a defect rather than a root cause in a fitness tracker? a) Because the author of the requirements was unfamiliar with the domain of fitness training, he therefore wrongly assumed that users wanted heartbeat in beats per hour b) The tester of the smartphone interface had not been trained in state transition testing, so missed a major defect c) An incorrect configuration variable implemented for the GPS function could cause location problems during daylight saving times d) Because the designer had never worked on wearable devices before, she as designer of the user interface therefore misunderstood the effects of reflected sunlight Select ONE option. Explanation / Rationale a) Is not correct. The lack of familiarity of the requirements author with the fitness domain is a root cause b) Is not correct. The lack of training of the tester in state transition testing was one of the root causes of the defect (the developer presumably created the defect, as well) c) Is correct. The incorrect configuration data represents faulty software in the fitness tracker (a defect), that may cause failures d) Is not correct. The lack of experience in designing user interfaces for wearable devices is a typical example of a root cause of a defect 30 / 40 30. You are working on a video game development project, using Agile methods. It is based on Greek mythology and history, and players can play key roles in scenarios such as the battles between the Greeks and Trojans. Consider the following user story and its associated acceptance criteria: As a player, I want to be able to acquire the Rod of Midas (a new magic object), so that I can turn objects and other players into gold AC1: The Rod must work on any object or player, no matter what size, which can be touched anywhere by the player holding the Rod AC2: Holding the Rod does not change the player holding it into gold AC3: Any object or player touched by the Rod transforms completely into gold within one millisecond AC4: The Rod appears as shown in Prototype O.W.RoM AC5: The transformation starts at the point of contact with the Rod and moves at a rate of one meter per millisecond You are participating in a checklist-based review session of this user story. This user story and its associated acceptance criteria contain which of the following typical defects identified by static testing in this type of work product? a) Deviation from standards b) Contradiction c) Security vulnerability d) Coverage gaps Select ONE option. Explanation / Rationale a) Is not correct. While deviation from standards is a typical, we are not given any standard with which the user stories should comply b) Is correct. Contradiction is a typical requirements defect. AC3 and AC5 conflict if the Rod is touched to an object that extends more than 1 meter in any direction from the point at which touched, since AC1 does not limit the size of the objects to be touched c) Is not correct. While security vulnerabilities are typical defects, there is nothing here related to security d) Is not correct. While test coverage gaps are typical defects, including missing tests for acceptance criteria, we are not provided with any information about which tests do and do not exist 31 / 40 31. Which of the following qualities is MORE likely to be found in a tester’s mindset rather than in a developer’s? a) A tester´s mindset tends to grow and mature as the tester gains experience b) Ability to see what might go wrong c) Good communication with team members d) Focus on getting all things done Select ONE option. Explanation / Rationale a) Is not correct. Both developers and testers gain from experience b) Is correct. Developers are often more interested in designing and building solutions than in contemplating what might be wrong with those solutions c) Is not correct. Both developers and testers should be able to communicate well d) Is not correct. Testers shall focus on the quality, not on the quantity 32 / 40 32. You will be invited to a review. The work product to be reviewed is a description of the in-house document creation process. The aim of the description is to present the work distribution between the different roles involved in the process in a way that can be clearly understood by everyone. You will be invited to a checklist-based review. The checklist will also be sent to you. It includes the following points: i. Is the person who performs the activity clearly identified for each activity? ii. Are the entry criteria clearly defined for each activity? iii. Are the exit criteria clearly defined for each activity? iv. Are the supporting roles and their scope of work clearly defined for each activity? In the following we show an excerpt of the work result to be reviewed, for which you should use the checklist above: "After checking the customer documentation for completeness and correctness, the software architect creates the system specification. Once the software architect has completed the system specification, he invites testers and verifiers to the review. A checklist describes the scope of the review. Each invited reviewer creates review comments - if necessary - and concludes the review with an official review done-comment." Which of the following statements about your review is correct? a) Point ii) of the checklist has been violated because it is not clear which condition must be fulfilled to invite to the review b) You notice that in addition to the tester and the verifier, the validator must also be invited. Since this item is not part of your checklist, you do not create a corresponding comment c) Point iii) of the checklist has been violated as it is not clear what marks the review as completed d) Point i) of the checklist has been violated because it is not clear who is providing the checklist for the invitation to the review Select ONE option. Explanation / Rationale a) Is not correct. It is described that the software architect must have completed the system specification b) Is not correct. ‘Checklist-based’, last sentence it is documented that you should also look for defects outside the checklist c) Is not correct. It is described: every reviewer did his review done comment d) Is correct. It is described that a checklist is available, but who provides the checklist? 33 / 40 33. Consider the following state transition diagram for a credit-card only, unattended gasoline pump: Assume that you want to develop the minimum number of tests to cover each transition in the state transition diagram. Assume further that each test must start at the beginning state, waiting for customer, and each test ends when a transition arrives at the beginning state. How many tests do you need? a) 4 b) 7 c) 1 d) Infinite Select ONE option. Explanation / Rationale Each transition must be traversed at least once. To do so, the first test can cover the happy path, a successful purchase, the next test cancels, or timeout from waiting for pumping, the next test cancels, or timeout from waiting for fuel type, and the last test the insertion of an invalid credit card. While the order is immaterial, fewer than four tests fail to cover one of the transitions inbound to waiting for customer or violates the rules about where a test starts or ends. More than four tests include tests that re-traverse already-covered transitions. Thus: a) Is correct b) Is not correct c) Is not correct d) Is not correct 34 / 40 34. In what way can testing be part of Quality Assurance? a) It ensures that requirements are detailed enough b) Testing reduces the risk of poor software quality c) It ensures that standards in the organization are followed d) It measures the quality of software in terms of number of executed test cases Select ONE option. Explanation / Rationale a) Is not correct. Static testing (reviews) contributes, but could not ensure, that requirements are detailed enough b) Is correct. Testing contributes to the achievement of quality in a variety of ways, e.g., such as reducing the risk of inadequate software quality c) Is not correct. This is quality assurance but not testing d) Is not correct. The quality cannot be measured by counting the number of executed test cases without knowing the outcome 35 / 40 35. You are working as a project manager on an in-house banking software project. To prevent rework and excessive find/fix/retest cycles, the following process has been put in place for resolving a defect once it is found in the test lab: 1. The assigned developer finds and fixes the defect, then creates an experimental build 2. A peer developer reviews, unit tests, and confirmation tests the defect fix on his/her desktop 3. A tester – usually the one who found the defect – confirmation tests the defect fix in the development environment 4. Once a day, a new release with all confirmed defect fixes included, is installed in the test environment 5. The same tester from step 3 confirmation tests the defect fix in the test environment Nevertheless, a large number of defects which the testers confirmed as fixed in the development environment (in step 3) are somehow failing confirmation testing in the test environment, with the resulting rework and cycle time outcomes. You have the highest confidence in your testers and have ruled out mistakes or omissions in step 3. Which of the following is the MOST likely part of the process to check next? a) The activity of developers, who may not be adequately testing in step 2 b) The activity of testers, who may be confused about what to test in step 5 c) Configuration management, which may not be maintaining the integrity of the product in step 4 d) The activity of developers, who may not be fixing defects properly in step 1 Select ONE option. Explanation / Rationale a) Is not correct. If inadequate developer testing were the problem, the confirmation test would not pass in step 3 b) Is not correct. The same tester who successfully performed the confirmation test in step 3 is repeating it in step 5 c) Is correct. Configuration management maintains the integrity of the software. If a test that passes in step 3 fails in step 5, then something is different between those two steps. One possible difference is the test object, the option listed here. Another possible difference is the between the development environment and the test environment, but that is not an option listed here d) Is not correct. If the developers were not fixing the defect, the confirmation test would not pass in step 3 36 / 40 36. Decision table testing is being performed on a speeding fine system. Two test cases have already been generated for rules R1 and R4, which are shown below: Given the following additional test cases: Which two of the additional test cases would achieve full coverage of the complete decision table (when combined with the test cases that have already been generated for rules R1 and R4)? a) DT1, DT2 b) DT2, DT3 c) DT2, DT4 d) DT3, DT4 Select ONE option. Explanation / Rationale The complete decision table is shown below: To achieve full coverage, test cases covering rules 2 and 3 are needed. DT4 satisfies the constraints of rule 2, while DT2 satisfies the constraints of rule 3. Thus: a) Is not correct b) Is not correct c) Is correct d) Is not correct 37 / 40 37. Which one of the following answers describes a test condition? a) A distinguishing characteristic of a component or system b) A testable aspect of a component or system identified as a basis for testing c) The degree to which a software product provides functions which meet stated and implied needs when the software is used under specified conditions d) Test cases designed to execute combinations of conditions and actions resulting from them Select ONE option. Explanation / Rationale a) Is not correct. Definition of feature according to glossary b) Is correct. From glossary c) Is not correct. Definition of functionality suitability according to glossary d) Is not correct. Like Definition of Decision table testing according to glossary 38 / 40 38. Which of the following statements on the use of checklists in a formal review is CORRECT? a) As part of the review planning, the reviewers create the checklists needed for the review b) As part of the issue communication, the reviewers fill in the checklists provided for the review c) As part of the review meeting, the reviewers create defect reports based on the checklists provided for the review d) As part of the review initiation, the reviewers receive the checklists needed for the review Select ONE option. Explanation / Rationale a) Is not correct. During planning it is decided whether checklists are used. The preparation of the checklists is not part of the planning. In addition, the reviewers are neither involved in the planning, nor responsible for the creation of the checklists b) Is not correct. During issue communication, any potential defects that have been identified in the individual review are communicated. The completion of checklists by the reviewers already takes place, if at all, during individual review c) Is not correct. During review session, the reviewers communicate any potential defects of the work product that they did identify during the individual review. Defect reports are only created during the fixing and reporting activity d) Is correct. Initiating the review (“Kick-off”) involves distributing the work product and other materials, like checklists 39 / 40 39. You are reading a user story in the product backlog to prepare for a meeting with the product owner and a developer, noting potential defects as you go. Which of the following statements is true about this activity? a) It is not a static test, because static testing involves execution of the test object b) It is not a static test, because static testing is always performed using a tool c) It is a static test, because any defects you find could be found cheaper during dynamic testing d) It is a static test because static testing does not involve execution of the test object Select ONE option. Explanation / Rationale a) Is not correct. Static testing does not involve execution of the test object b) Is not correct. Some static tests involve the use of a tool, especially static analysis, but reviews (such as the activity described here) do not necessarily involve the use of a tool c) Is not correct. The review activity described here is part of a static test, but defects found in static tests are usually cheaper than those found in dynamic testing d) Is correct. Static testing does not involve execution of the test object 40 / 40 40. Which of the following provides the BEST description of exploratory testing? a) A testing practice in which an in-depth investigation of the background of the test object is used to identify potential weaknesses that are examined by test cases b) An approach to testing whereby the testers dynamically design and execute tests based on their knowledge, exploration of the test item and the results of previous tests c) An approach to test design in which test activities are planned as uninterrupted sessions of test analysis and design, often used in conjunction with checklist-based testing d) Testing based on the tester's experience, knowledge, and intuition Select ONE option. Explanation / Rationale a) Is not correct. Exploratory testing is often carried out when timescales are short, so making in-depth investigations of the background of the test object is unlikely b) Is correct. Glossary definition c) Is not correct. Based on the Glossary definition of session-based testing, but with test execution replaced by test analysis d) Is not correct. Glossary definition of experience-based testing 0% Restart quiz