ISTQB Learning

Test your knowledge

0%
318
Created on By Admin

Exam 1

1 / 40

1. In your project there has been a delay in the release of a brand-new application and test execution started late, but you have very detailed domain knowledge and good analytical skills. The full list of requirements has not yet been shared with the team, but management is asking for some test results to be presented.

Which test technique fits BEST in this situation?

Select ONE option.

2 / 40

2. A wine storage system uses a control device that measures the wine cell temperature T (measured in °C, rounded to the nearest degree) and alarms the user if it deviates from the optimal value of 12, according to the following rules:

• if T = 12, the system says, “optimal temperature”

• if T < 12, the system says, “temperature is too low!”

• if T > 12, the system says, “temperature is too high!”

You want to use the 3-point boundary value analysis (BVA) to verify the behavior of the control device. A test input is a temperature in °C provided by the device.

What is the MINIMAL set of test inputs that achieves 100% of the desired coverage?

Select ONE option.

3 / 40

3. Which of the following statements about formal reviews is TRUE?

Select ONE option.

4 / 40

4. Which of the following is NOT true regarding the test pyramid?

Select ONE option.

5 / 40

5. Which work product can be used by an agile team to show the amount of work that has been completed and the amount of total work remaining for a given iteration?

Select ONE option.

6 / 40

6. You were given a task to analyze and fix causes of failures in a new system to be released.

Which activity are you performing?

Select ONE option.

7 / 40

7. During a risk analysis the following risk was identified and assessed:

• Risk: Response time is too long to generate a report
• Risk likelihood: medium; risk impact: high
• Response to risk:

o An independent test team performs performance testing during system testing
o A selected sample of end users performs alpha and beta acceptance testing before the release

What measure is proposed to be taken in response to this analyzed risk?

Select ONE option.

8 / 40

8. Your test suite achieved 100% statement coverage. What is the consequence of this fact?

Select ONE option.

9 / 40

9. You are testing a mobile application that allows users to find a nearby restaurant based on the type of food they want to eat. Consider the following list of test cases, priorities (i.e., a smaller number means a higher priority), and dependencies:

Which of the following test cases should be executed as the third one?

Select ONE option.

10 / 40

10. Which of the following statements about branch testing is CORRECT?

Select ONE option.

11 / 40

11. You need to update one of the automated test scripts to be in line with a new requirement. Which process indicates that you create a new version of the test script in the test repository?

Select ONE option.

12 / 40

12. Consider the following testware.

Which test activity produces this testware as an output?

Select ONE option.

13 / 40

13. Which TWO of the following options are the exit criteria for testing a system?

Select TWO options.

14 / 40

14. Which of the following is an example of how product risk analysis influences thoroughness and scope of testing?

Select ONE option.

15 / 40

15. Which of the following statements BEST describes the acceptance test-driven development (ATDD) approach?

Select ONE option.

16 / 40

16. You received the following defect report from the developers stating that the anomaly described in this test report is not reproducible.

Application hangs up
2022-May-03 – John Doe – Rejected
The application hangs up after entering “Test input: $ä” in the Name field on the new user creation screen. Tried to log off, log in with test_admin01 account, same issue. Tried with other test admin accounts, same issue. No error message received; log (see attached) contains fatal error notification. Based on the test case TC-1305, the application should accept the provided input and create the user. Please fix with high priority, this feature is related to REQ-0012, which is a critical new business requirement.

What critical information is MISSING from this test report that would have been useful for the developers?

Select ONE option.

17 / 40

17. Which types of failures (1-4) fit which test levels (A-D) BEST?

1. Failures in system behavior as it deviates from the user’s business needs
2. Failures in communication between components
3. Failures in logic in a module
4. Failures in not correctly implemented business rules

A. Component testing
B. Component integration testing
C. System testing
D. Acceptance testing

Select ONE option.

18 / 40

18. You are testing a mobile application that allows customers to access and manage their bank accounts. You are running a test suite that involves evaluating each screen, and each field on each screen, against a general list of user interface best practices derived from a popular book on the topic that maximizes attractiveness, ease-of-use, and accessibility for such applications. Which of the following options BEST categorizes the test technique you are using?

Select ONE option.

19 / 40

19. A phone ringing in a neighboring cubicle distracts a programmer causing him to improperly program the logic that checks the upper boundary of an input variable. Later, during system testing, a tester notices that this input field accepts invalid input values.

Which of the following correctly describes an incorrectly coded upper bound?

Select ONE option.

20 / 40

20. You work as a tester in a project on a mobile application for food ordering for one of your clients. The client sent you a list of requirements. One of them, with high priority, says

“The order must be processed in less than 10 seconds in 95% of the cases”.

You created a set of test cases in which a number of random orders were made, the processing time measured, and the test results were checked against the requirements.

What test type did you perform?

Select ONE option.

21 / 40

21. Which of the following BEST describes the concept behind error guessing?

Select ONE option.

22 / 40

22. Which of the following options shows an example of test activities that contribute to success?

Select ONE option.

23 / 40

23. Decide which of the following statements (i-v) are true for static testing.

i. Abnormal external behaviors are easier to identify with this testing
ii. Discrepancies from a coding standard are easier to find with this testing
iii. It identifies failures caused by defects when the software is run
iv. Its test objective is to identify defects as early as possible
v. Missing coverage for critical security requirements is easier to find and fix

Select ONE option.

24 / 40

24. Which of the following is NOT an example of the shift left approach?

Select ONE option.

25 / 40

25. You have been assigned as a tester to a team producing a new system incrementally. You have noticed that no changes have been made to the existing regression test cases for several iterations and no new regression defects were identified. Your manager is happy, but you are not. Which testing principle explains your skepticism?

Select ONE option.

26 / 40

26. Which of the following factors (i-v) have SIGNIFICANT influence on the test process?

i. The SDLC
ii. The number of defects detected in previous projects
iii. The identified product risks
iv. New regulatory requirements forcing formal white-box testing
v. The test environment setup

Select ONE option.

27 / 40

27. How do testers add value to iteration and release planning?

Select ONE option.

28 / 40

28. During risk analysis the team considered the following risk: “The system allows too high a discount for a customer”. The team estimated the risk impact to be very high.

What can one say about the risk likelihood?

Select ONE option.

29 / 40

29. Which TWO of the following tasks belong MAINLY to a testing role?

Select TWO options.

30 / 40

30. Which of the following pieces of information contained in a test progress report is the LEAST useful for business representatives?

Select ONE option.

31 / 40

31. Which of the following BEST describe the collaborative approach to user story writing?

Select ONE option.

32 / 40

32. Your favorite bicycle daily rental store has just introduced a new Customer Relationship Management system and asked you, one of their most loyal members, to test it.
The implemented features are as follows:

• Anyone can rent a bicycle, but members receive a 20% discount
• However, if the return deadline is missed, the discount is no longer available
• After 15 rentals, members get a gift: a T-Shirt

Decision table describing the implemented features looks as follows:

Based ONLY on the feature description of the Customer Relationship Management system, which of the above rules describes an impossible situation?

 

Select ONE option.

33 / 40

33. The following list contains risks that have been identified for a new software product to be developed:

i. Management moves two experienced testers to another project
ii. The system does not comply with functional safety standards
iii. System response time exceeds user requirements
iv. Stakeholders have inaccurate expectations
v. Disabled people have problems when using the system

Which of them are project risks?

Select ONE option.

34 / 40

34. Which of the following is a benefit of early and frequent feedback?

Select ONE option.

35 / 40

35. You are testing a user story with three acceptance criteria: AC1, AC2 and AC3. AC1 is covered by test case TC1, AC2 by TC2, and AC3 by TC3. The test execution history had three test runs on three consecutive versions of the software as follows:

Tests are repeated once you are informed that all defects found in the test run are corrected and a new version of the software is available.
Which of the above tests are executed as regression tests?

Select ONE option.

36 / 40

36. How is the whole team approach present in the interactions between testers and business representatives?

Select ONE option.

37 / 40

37. Which item correctly identifies a potential risk of performing test automation?

Select ONE option.

38 / 40

38. You are working as a tester in the team that follows the V-model. The choice of software development lifecycle (SDLC) model impacts the timing of testing, which of the following statement is NOT true?

Select ONE option.

39 / 40

39. Which TWO of the following options are common metrics used for reporting on the quality level of the test object?

Select TWO options.

40 / 40

40. Which of the following statements describe a valid test objective?

Select ONE option.

0%

Scroll to top