ISTQB Learning

Test your knowledge

0%
35
Created on By Admin

Exam 5

1 / 40

1. Which of the following is MOST likely to be a risk of test automation?

Select ONE options.

2 / 40

2. You are working on a project to develop a system to analyze driving test results. You have been asked to design test cases based on the following decision table.

What test data will show that there are contradictory rules in the decision table?

Select ONE option.

3 / 40

3. Which of the following is NOT a purpose of a test plan?

Select ONE option.

4 / 40

4. Which collaborative user story writing practice enables the team to achieve a collective understanding of what needs to be delivered?

Select ONE option.

5 / 40

5. You are working as a tester in the team that follows the V-model. The choice of software development lifecycle (SDLC) model impacts the timing of testing, which of the following statement is NOT true?

Select ONE option.

6 / 40

6. You need to update one of the automated test scripts to be in line with a new requirement. Which process indicates that you create a new version of the test script in the test repository?

Select ONE option.

7 / 40

7. During risk analysis the team considered the following risk: “The system allows too high a discount for a customer”. The team estimated the risk impact to be very high.

What can one say about the risk likelihood?

Select ONE option.

8 / 40

8. The ‘absence-of-defects fallacy’ is one of the principles of testing. Which of the following is an example of addressing this principle in practice?

Select ONE option.

9 / 40

9. Which of the following options shows an example of test activities that contribute to success?

Select ONE option.

10 / 40

10. Which of the following CANNOT be examined by static testing?

Select ONE option.

11 / 40

11. Which TWO of the following options are the exit criteria for testing a system?

Select TWO options.

12 / 40

12. Given the following test tool categories:

i. Collaboration tools
ii. DevOps tools
iii. Management tools
iv. Non-functional testing tools
v. Test design and implementation tools

Tools from which of the categories are MOST likely to facilitate test execution?

Select ONE options.

13 / 40

13. Given the following testware:

1. Coverage items
2. Change requests
3. Test execution schedule
4. Prioritized test conditions

And the following test activities

A. Test analysis
B. Test design
C. Test implementation
D. Test completion

Which of the following BEST shows the testware produced by the activities?

Select ONE option.

14 / 40

14. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

15 / 40

15. The user reported a software failure. An engineer from the support team asked the user for the software version number where the failure was observed. Based on the version number, the team reassembled all the files that made up the release. This later allowed a developer to perform analysis, find the defect, and fix it.

Which of the following enabled the above activity to be performed by the team?

Select ONE options.

16 / 40

16. Your organization’s test strategy suggests that once a system is going to be retired, data migration shall be tested. As part of what test type is this testing MOST likely to be performed?

Select ONE option.

17 / 40

17. Which of the following statements about the value of static testing is CORRECT?

Select ONE option.

18 / 40

18. Which test activity involves working with test data requirements, test conditions, test environment requirements and test cases?

Select ONE option.

19 / 40

19. Given the following benefits and drawbacks of the independence of testing:

i. The testers work in a different location from the developers
ii. Testers question the assumptions programmers make while writing code
iii. A confrontational dynamic has been established between testers and developers
iv. Developers have convinced themselves that testers are mostly accountable for quality
v. Testers have different biases than those held by the developers

Which are MOST likely to be considered benefits?

Select ONE option.

20 / 40

20. You are testing a form that verifies the correctness of the length of the password given as input. The form accepts a password with the correct length and rejects a password that is too short or too long. The password length is correct if it has between 6 and 12 characters inclusive. Otherwise, it is considered incorrect.

At first, the form is empty (password length = 0). You apply boundary value analysis to the “password length” variable.

Your set of test cases achieves 100% 2-value boundary value coverage. The team decided that due to the high risk of this component, test cases should be added to ensure 100% 3-value boundary value coverage.

Which additional password lengths should be tested to achieve this?

Select ONE option.

21 / 40

21. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

22 / 40

22. You are a member of a test team located in North America, developing a product for a client located in Europe. The team is agile and follows the DevOps approach and uses a continuous integration/continuous delivery pipeline.

Which of the following is the LEAST effective way to communicate test progress to the customer?

Select ONE option.

23 / 40

23. Given the following roles in reviews:

1. Scribe
2. Review leader
3. Facilitator
4. Manager

And the following responsibilities in reviews:

A. Ensures the effective running of review meetings and the setting up a safe review environment
B. Records review information, such as decisions and new anomalies found during the review meeting
C. Decides what is to be reviewed and provides resources, such as staff and time for the review
D. Takes overall responsibility for the review such as organizing when and where the review will take place

Which of the following BEST matches the roles and responsibilities?

Select ONE option.

24 / 40

24. Your team follows the process that uses the DevOps delivery pipeline. The first three steps of this process are:

(1) Code development
(2) Submit code into a version control system and merge it into the “test” branch
(3) Perform component testing for the submitted code

Which of the following is BEST suited to be the entry criterion for step (2) of this pipeline?

Select ONE option.

25 / 40

25. You were given a task to analyze and fix causes of failures in a new system to be released.

Which activity are you performing?

Select ONE option.

26 / 40

26. Which of the following is an advantage of the whole team approach?

Select ONE option.

27 / 40

27. Decide which of the following statements (i-v) are true for static testing.

i. Abnormal external behaviors are easier to identify with this testing
ii. Discrepancies from a coding standard are easier to find with this testing
iii. It identifies failures caused by defects when the software is run
iv. Its test objective is to identify defects as early as possible
v. Missing coverage for critical security requirements is easier to find and fix

Select ONE option.

28 / 40

28. Why does white-box testing facilitate defect detection even when the software specification is vague, outdated or incomplete?

Select ONE option.

29 / 40

29. Which of the following is an example of how product risk analysis may influence the thoroughness and scope of testing?

Select ONE option.

30 / 40

30. The following list contains risks that have been identified for a new software product to be developed:

i. Management moves two experienced testers to another project
ii. The system does not comply with functional safety standards
iii. System response time exceeds user requirements
iv. Stakeholders have inaccurate expectations
v. Disabled people have problems when using the system

Which of them are project risks?

Select ONE option.

31 / 40

31. Your test suite S for a program P achieves 100% statement coverage. It consists of three test cases, each of which achieves 50% statement coverage.

Which of the following statements is CORRECT?

Select ONE option.

32 / 40

32. Which of the following is a benefit of early and frequent stakeholder feedback?

Select ONE option.

33 / 40

33. Consider the following part of a test plan.

Testing will be performed using component testing and component integration testing. The regulations require to demonstrate that 100% branch coverage is achieved for each component classified as critical.

Which part of the test plan does this part belong to?

Select ONE option.

34 / 40

34. Which of the following is true about exploratory testing?

Select ONE option.

35 / 40

35. The navigation system software has been updated due to it suggesting routes that break traffic laws, such as driving the wrong way down one-way streets. Which of the following BEST describes the testing that will be performed?

Select ONE option.

36 / 40

36. Which of the following provides the BEST description of the shift-left approach?

Select ONE option.

37 / 40

37. Your test suite achieved 100% statement coverage. What is the consequence of this fact?

Select ONE option.

38 / 40

38. Which of the following statements BEST describes the difference between decision table testing and branch testing?

Select ONE option.

39 / 40

39. In your project there has been a delay in the release of a brand-new application and test execution started late, but you have very detailed domain knowledge and good analytical skills. The full list of requirements has not yet been shared with the team, but management is asking for some test results to be presented.

Which test technique fits BEST in this situation?

Select ONE option.

40 / 40

40. Which of the following statements about quality assurance (QA) and/or quality control (QC) is correct?

Select ONE option.

0%

Scroll to top