ISTQB Learning

Test your knowledge

0%
35
Created on By Admin

Exam 5

1 / 40

1. A designer documents a design for a user interface that does not suitably address disabled users because the designer is tired. The programmer implements the user interface in line with the design but as they are working under severe time pressure, they do not include suitable exception handling in their program code for bonus calculations. When the operational system is used, complaints are made by some disabled users about the interface and the company is subsequently fined by the relevant regulatory authority. No one notices that bonus calculations are sometimes incorrect.

Which of the following statements is CORRECT?

Select ONE option.

2 / 40

2. You are testing a PIN validator, which accepts valid PINs and rejects invalid PINs. A PIN is a sequence of digits. A PIN is valid if it consists of four digits, at least two of which are different. You have identified the following valid equivalence partitions:

Variable: PIN code length

• The partition “length correct” - four-digit PINs
• The partition “length incorrect” - PINs with length other than 4

Variable: Number of different digits

• The partition “number of different digits correct” - PINs with at least two different digits
• The partition “number of different digits incorrect” - PINs with all digits being the same

Which of the following is a MINIMUM set of input test data that covers all identified equivalence partitions?

Select ONE option.

3 / 40

3. Which of the following is a benefit of early and frequent feedback?

Select ONE option.

4 / 40

4. W A developer was asked to implement the following business rule:

You design the test cases using 2-value boundary value analysis.

Which of the following sets of test inputs achieves the greatest coverage?

Select ONE option.

5 / 40

5. Tools from which of the following categories help with the organization of test cases, detected defects and configuration management?

 

Select ONE option.

6 / 40

6. Which TWO of the following tasks belong MAINLY to a testing role?

Select TWO options.

7 / 40

7. Which of the following BEST fits as an element of the checklist used in checklist-based testing?

Select ONE option.

8 / 40

8. For a given risk, its risk level is $1,000 and its risk likelihood is estimated as 50%.

What is the risk impact?

Select ONE options.

9 / 40

9. Given the following roles in reviews:

1. Scribe
2. Review leader
3. Facilitator
4. Manager

And the following responsibilities in reviews:

A. Ensures the effective running of review meetings and the setting up a safe review environment
B. Records review information, such as decisions and new anomalies found during the review meeting
C. Decides what is to be reviewed and provides resources, such as staff and time for the review
D. Takes overall responsibility for the review such as organizing when and where the review will take place

Which of the following BEST matches the roles and responsibilities?

Select ONE option.

10 / 40

10. Which of the following statements is CORRECT?

Select ONE option.

11 / 40

11. Which of the following statements about formal reviews is TRUE?

Select ONE option.

12 / 40

12. Consider the following testware.

Which test activity produces this testware as an output?

Select ONE option.

13 / 40

13. Which of the following BEST define EXIT criteria in a testing project?

Select TWO options.

14 / 40

14. You are testing a mobile application that allows users to find a nearby restaurant based on the type of food they want to eat. Consider the following list of test cases, priorities (i.e., a smaller number means a higher priority), and dependencies:

Which of the following test cases should be executed as the third one?

Select ONE option.

15 / 40

15. Which of the following are advantages of DevOps?

i. Faster product release and faster time to market
ii. Increases the need for repetitive manual testing
iii. Constant availability of executable software
iv. Reduction in the number of regression tests associated with code refactoring
v. Setting up the test automation framework is inexpensive since everything is automated

Select ONE option.

16 / 40

16. Which of the following statements about quality assurance (QA) and/or quality control (QC) is correct?

Select ONE option.

17 / 40

17. Consider the following test categories (1-4) and agile testing quadrants (A-D):

1. Usability testing
2. Component testing
3. Functional testing
4. Reliability testing

A. Agile testing quadrant Q1: technology facing, supporting the development team
B. Agile testing quadrant Q2: business facing, supporting the development team
C. Agile testing quadrant Q3: business facing, critique the product
D. Agile testing quadrant Q4: technology facing, critique the product

How do the following test categories map onto the agile testing quadrants?

Select ONE option.

18 / 40

18. Given the following testware:

1. Coverage items
2. Change requests
3. Test execution schedule
4. Prioritized test conditions

And the following test activities

A. Test analysis
B. Test design
C. Test implementation
D. Test completion

Which of the following BEST shows the testware produced by the activities?

Select ONE option.

19 / 40

19. Which of the following is MOST likely to be a trigger that leads to maintenance testing of a currency exchange system?

Select ONE option.

20 / 40

20. Your team uses planning poker to estimate the test effort for a newly required feature. There is a rule in your team that if there is no time to reach full agreement and the variation in the results is small, applying rules like “accept the number with the most votes” can be applied.
After two rounds, the consensus was not reached, so the third round was initiated. You can see the test estimation results in the table below.

Which of the following is the BEST example of the next step?

Select ONE option.

21 / 40

21. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

22 / 40

22. Which of the following is NOT anticipated by the tester while applying error guessing?

Select ONE option.

23 / 40

23. At the beginning of each iteration, the team estimates the amount of work (in person-days) they will need to complete during the iteration. Let E(n) be the estimated amount of work for iteration n, and let A(n) be the actual amount of work done in iteration n. From the third iteration, the team uses the following estimation model based on extrapolation:

 

 

The graph shows the estimated and actual amount of work for the first four iterations.

What is the estimated amount of work for iteration #5?

Select ONE option.

24 / 40

24. During a risk analysis the following risk was identified and assessed:

• Risk: Response time is too long to generate a report
• Risk likelihood: medium; risk impact: high
• Response to risk:

o An independent test team performs performance testing during system testing
o A selected sample of end users performs alpha and beta acceptance testing before the release

What measure is proposed to be taken in response to this analyzed risk?

Select ONE option.

25 / 40

25. Which of the following statements about the value of static testing is CORRECT?

Select ONE option.

26 / 40

26. You work in a team that develops a mobile application for food ordering. In the current iteration the team decided to implement the payment functionality.

Which of the following activities is a part of test analysis?

Select ONE option.

27 / 40

27. Which of the following statements BEST describes the difference between testing and debugging?

Select ONE option.

28 / 40

28. You need to update one of the automated test scripts to be in line with a new requirement. Which process indicates that you create a new version of the test script in the test repository?

Select ONE option.

29 / 40

29. Which of the arguments below would you use to convince your manager to organize retrospectives at the end of each release cycle?

Select ONE option.

30 / 40

30. Given the following testware:

i. Test completion report
ii. Data held in a database used for test inputs and expected results
iii. The list of elements needed to build the test environment
iv. Documented sequences of test cases in execution order
v. Test cases

Which of the following BEST shows the testware produced as a result of performing test implementation?

Select ONE option.

31 / 40

31. You are working on a project to develop a system to analyze driving test results. You have been asked to design test cases based on the following decision table.

What test data will show that there are contradictory rules in the decision table?

Select ONE option.

32 / 40

32. What is the relationship between the testing quadrants, test levels and test types?

Select ONE option.

33 / 40

33. Given the following task descriptions:

1. The quality characteristics to be evaluated and the exit criteria are selected
2. Everyone has access to the work product
3. Anomalies are identified in the work product
4. Anomalies are discussed

And the following review activities

A. Individual review
B. Review initiation
C. Planning
D. Communication and analysis

Which of the following BEST matches the task descriptions and activities?

Select ONE option.

34 / 40

34. Given the following review types:

1. Technical review
2. Informal review
3. Inspection
4. Walkthrough

And the following descriptions:

A. Includes objectives such as gaining consensus, generating new ideas, and motivating authors to improve
B. Includes objectives such as educating reviewers, gaining consensus, generating new ideas and detecting potential defects
C. The main objective is detecting potential defects and it requires metrics collection to support process improvement
D. The main objective is detecting potential defects and it generates no formal documented output

Which of the following BEST matches the review types and the descriptions?

Select ONE option.

35 / 40

35. You work as a tester in a project on a mobile application for food ordering for one of your clients. The client sent you a list of requirements. One of them, with high priority, says

“The order must be processed in less than 10 seconds in 95% of the cases”.

You created a set of test cases in which a number of random orders were made, the processing time measured, and the test results were checked against the requirements.

What test type did you perform?

Select ONE option.

36 / 40

36. Which of the following is MOST likely to impact how testing is performed for a given test object?

Select ONE option.

37 / 40

37. Which of the following is an example of a defect that can be found by static testing but NOT by dynamic testing?

Select ONE option.

38 / 40

38. Which of the following BEST describes an example of how configuration management (CM) supports testing?

Select ONE option.

39 / 40

39. Which of the following is a typical test objective?

Select ONE option.

40 / 40

40. During risk analysis the team considered the following risk: “The system allows too high a discount for a customer”. The team estimated the risk impact to be very high.

What can one say about the risk likelihood?

Select ONE option.

0%

Scroll to top