ISTQB Learning

Test your knowledge

0%
35
Created on By Admin

Exam 5

1 / 40

1. Your team uses the three-point estimation technique to estimate the test effort for a new high-risk feature. The following estimates were made:

• Most optimistic estimation: 2 person-hours
• Most likely estimation: 11 person-hours
• Most pessimistic estimation: 14 person-hours

What is the final estimate?

Select ONE option.

2 / 40

2. Which of the following activities in the test process makes the MOST use of test progress reports?

Select ONE option.

3 / 40

3. According to the testing quadrants model, which of the following falls into quadrant Q1 (“technology facing” and “support the team”)?

Select ONE option.

4 / 40

4. Which of the following is a benefit of early and frequent feedback?

Select ONE option.

5 / 40

5. You received the following defect report from the developers stating that the anomaly described in this test report is not reproducible.

Application hangs up
2022-May-03 – John Doe – Rejected
The application hangs up after entering “Test input: $ä” in the Name field on the new user creation screen. Tried to log off, log in with test_admin01 account, same issue. Tried with other test admin accounts, same issue. No error message received; log (see attached) contains fatal error notification. Based on the test case TC-1305, the application should accept the provided input and create the user. Please fix with high priority, this feature is related to REQ-0012, which is a critical new business requirement.

What critical information is MISSING from this test report that would have been useful for the developers?

Select ONE option.

6 / 40

6. Which of the following is a typical test objective?

Select ONE option.

7 / 40

7. You want to estimate the test effort for the new project using estimation based on ratios. You calculate the test-to-development effort ratio using averaged data for both development effort and test effort from four historical projects similar to the new one. The table shows this historical data.

The estimated development effort for the new project is $800,000. What is your estimate of the test effort in this project?

Select ONE option.

8 / 40

8. High-level test conditions are being used by testers to generate test cases and execute tests. Even though the test conditions remain the same, the test cases are varied each time. Which of the following ‘principles of testing’ is being addressed through the variation of test cases?

Select ONE option.

9 / 40

9. Which of the following are product risks?

Select TWO options.

10 / 40

10. Which of the following is an example of how product risk analysis influences thoroughness and scope of testing?

Select ONE option.

11 / 40

11. You are designing test cases based on the following state transition diagram:

What is the MINIMUM number of test cases required to achieve 100% valid transitions coverage?

Select ONE option.

12 / 40

12. Which of the following statements about the chosen software development lifecycle is CORRECT?

Select ONE option.

13 / 40

13. You are using acceptance test-driven development and designing test cases based on the following user story:

Which test case is the MOST reasonable one to test AC3?

Select ONE option.

14 / 40

14. How do testers add value to iteration and release planning?

Select ONE option.

15 / 40

15. Which of the following BEST explains a benefit of independence of testing?

Select ONE option.

16 / 40

16. Which of the following BEST describes retrospectives?

Select ONE option.

17 / 40

17. The ‘absence-of-defects fallacy’ is one of the principles of testing. Which of the following is an example of addressing this principle in practice?

Select ONE option.

18 / 40

18. The table shows the traceability matrix from test cases to requirements. “X” means that a given test case covers the corresponding requirement.

You want to prioritize the test cases following the additional coverage prioritization technique.

You execute all four test cases.

Which test case should be executed as the LAST one?

Select ONE options.

19 / 40

19. You work as a tester in a project on a mobile application for food ordering for one of your clients. The client sent you a list of requirements. One of them, with high priority, says

“The order must be processed in less than 10 seconds in 95% of the cases”.

You created a set of test cases in which a number of random orders were made, the processing time measured, and the test results were checked against the requirements.

What test type did you perform?

Select ONE option.

20 / 40

20. You are testing a system that calculates the final course grade for a given student.

The final grade is assigned based on the final result, according to the following rules:

• 0 – 50 points: failed
• 51 – 60 points: fair
• 61 – 70 points: satisfactory
• 71 – 80 points: good
• 81 – 90 points: very good
• 91 – 100 points: excellent

You have prepared the following set of test cases:

What is the 2-value Boundary Value Analysis (BVA) coverage for the final result that is achieved with the existing test cases?

Select ONE option.

21 / 40

21. What does the test pyramid model show?

Select ONE option.

22 / 40

22. The team wants to estimate the time needed for one tester to execute four test cases for a software component. The team has gathered the following measures of the effort used to execute a single test case:

• Best-case scenario: 1 hour
• Worst-case scenario: 8 hours
• Most likely scenario: 3 hours

Given that the three-point estimation technique is being used, what is the final estimate of the time needed to execute all four test cases?

Select ONE option.

23 / 40

23. Which of the following is MOST likely to be performed as part of system testing?

Select ONE option.

24 / 40

24. Your team analyzes the following user story in order to define the acceptance criteria:

As a registered customer, I want to be able to view my previous orders on the company's website, so that I can keep track of my purchases.

Which of the following test cases will NOT be relevant for this user story?

Select ONE option.

25 / 40

25. In many software organizations the test department is called the Quality Assurance (QA) department. Is this sentence correct or not and why?

Select ONE option.

26 / 40

26. Your test suite achieved 100% statement coverage. What is the consequence of this fact?

Select ONE option.

27 / 40

27. Consider the following testware.

Which test activity produces this testware as an output?

Select ONE option.

28 / 40

28. You run two test cases, T1 and T2, on the same code. Test T1 achieved 40% statement coverage and test T2 achieved 65% statement coverage.

Which of the following sentences must be necessarily true?

Select ONE option.

29 / 40

29. Given the following test tool categories:

i. Collaboration tools
ii. DevOps tools
iii. Management tools
iv. Non-functional testing tools
v. Test design and implementation tools

Tools from which of the categories are MOST likely to facilitate test execution?

Select ONE options.

30 / 40

30. Let the branch coverage metric be defined as BCov = (X / Y) * 100%.

What do X and Y represent in this formula?

Select ONE option.

31 / 40

31. Which of the following is an example of how product risk analysis may influence the thoroughness and scope of testing?

Select ONE option.

32 / 40

32. Which of the following statements about the independence of testing is CORRECT?

Select ONE option.

33 / 40

33. Which of the following is NOT a valid purpose for a test report?

Select ONE options.

34 / 40

34. Given the following benefits and drawbacks of the independence of testing:

i. The testers work in a different location from the developers
ii. Testers question the assumptions programmers make while writing code
iii. A confrontational dynamic has been established between testers and developers
iv. Developers have convinced themselves that testers are mostly accountable for quality
v. Testers have different biases than those held by the developers

Which are MOST likely to be considered benefits?

Select ONE option.

35 / 40

35. You are working as a tester in the team that follows the V-model. The choice of software development lifecycle (SDLC) model impacts the timing of testing, which of the following statement is NOT true?

Select ONE option.

36 / 40

36. Which types of failures (1-4) fit which test levels (A-D) BEST?

1. Failures in system behavior as it deviates from the user’s business needs
2. Failures in communication between components
3. Failures in logic in a module
4. Failures in not correctly implemented business rules

A. Component testing
B. Component integration testing
C. System testing
D. Acceptance testing

Select ONE option.

37 / 40

37. Which of the following is a benefit of early and frequent stakeholder feedback?

Select ONE option.

38 / 40

38. Given the following task descriptions:

1. The quality characteristics to be evaluated and the exit criteria are selected
2. Everyone has access to the work product
3. Anomalies are identified in the work product
4. Anomalies are discussed

And the following review activities

A. Individual review
B. Review initiation
C. Planning
D. Communication and analysis

Which of the following BEST matches the task descriptions and activities?

Select ONE option.

39 / 40

39. Given the following review types:

1. Technical review
2. Informal review
3. Inspection
4. Walkthrough

And the following descriptions:

A. Includes objectives such as gaining consensus, generating new ideas, and motivating authors to improve
B. Includes objectives such as educating reviewers, gaining consensus, generating new ideas and detecting potential defects
C. The main objective is detecting potential defects and it requires metrics collection to support process improvement
D. The main objective is detecting potential defects and it generates no formal documented output

Which of the following BEST matches the review types and the descriptions?

Select ONE option.

40 / 40

40. How can white-box testing be useful in support of black-box testing?

Select ONE option.

0%

Scroll to top