ISTQB Learning

Test your knowledge

0%
35
Created on By Admin

Exam 5

1 / 40

1. Which of the following statements about the independence of testing is CORRECT?

Select ONE option.

2 / 40

2. Your test suite achieved 100% statement coverage. What is the consequence of this fact?

Select ONE option.

3 / 40

3. Which of the following statements BEST describes the acceptance test-driven development (ATDD) approach?

Select ONE option.

4 / 40

4. Given the following benefits and drawbacks of the independence of testing:

i. The testers work in a different location from the developers
ii. Testers question the assumptions programmers make while writing code
iii. A confrontational dynamic has been established between testers and developers
iv. Developers have convinced themselves that testers are mostly accountable for quality
v. Testers have different biases than those held by the developers

Which are MOST likely to be considered benefits?

Select ONE option.

5 / 40

5. Which of the following BEST fits as an element of the checklist used in checklist-based testing?

Select ONE option.

6 / 40

6. Which of the following is an example of a defect that can be found by static testing but NOT by dynamic testing?

Select ONE option.

7 / 40

7. Consider the following acceptance criteria for a user story written from the perspective of an online store owner.

Given that the user is logged in and on the homepage,
When the user clicks on the "Add Item" button,
Then the "Create Item" form should appear,
And the user should be able to input a name and price for the new item.

In what format is this acceptance criteria written?

Select ONE option.

8 / 40

8. Your favorite bicycle daily rental store has just introduced a new Customer Relationship Management system and asked you, one of their most loyal members, to test it.
The implemented features are as follows:

• Anyone can rent a bicycle, but members receive a 20% discount
• However, if the return deadline is missed, the discount is no longer available
• After 15 rentals, members get a gift: a T-Shirt

Decision table describing the implemented features looks as follows:

Based ONLY on the feature description of the Customer Relationship Management system, which of the above rules describes an impossible situation?

 

Select ONE option.

9 / 40

9. Which of the following is a factor that contributes to a successful review?

Select ONE option.

10 / 40

10. Which of the following is a typical test objective?

Select ONE option.

11 / 40

11. At the beginning of each iteration, the team estimates the amount of work (in person-days) they will need to complete during the iteration. Let E(n) be the estimated amount of work for iteration n, and let A(n) be the actual amount of work done in iteration n. From the third iteration, the team uses the following estimation model based on extrapolation:

 

 

The graph shows the estimated and actual amount of work for the first four iterations.

What is the estimated amount of work for iteration #5?

Select ONE option.

12 / 40

12. Given the following risks:

1. Ineffective loop implementation causes long system responses
2. Consumers change their preferences
3. Flooding of the server room
4. Patients above a certain age receive inaccurate reports

And the following mitigation activities:

A. Risk acceptance
B. Performance testing
C. Using boundary value analysis as the test technique
D. Risk transfer

Which of the following BEST matches the risks with the mitigation activities?

Select ONE option.

13 / 40

13. What is the MAIN difference between black-box test techniques and experience-based test techniques?

Select ONE option.

14 / 40

14. According to the testing quadrants model, which of the following falls into quadrant Q1 (“technology facing” and “support the team”)?

Select ONE option.

15 / 40

15. Which of the following statements about formal reviews is TRUE?

Select ONE option.

16 / 40

16. Which of the following is an example of a test-first approach to development?

Select ONE option.

17 / 40

17. You are testing a mobile application that allows users to find a nearby restaurant based on the type of food they want to eat. Consider the following list of test cases, priorities (i.e., a smaller number means a higher priority), and dependencies:

Which of the following test cases should be executed as the third one?

Select ONE option.

18 / 40

18. You are testing a mobile application that allows customers to access and manage their bank accounts. You are running a test suite that involves evaluating each screen, and each field on each screen, against a general list of user interface best practices derived from a popular book on the topic that maximizes attractiveness, ease-of-use, and accessibility for such applications. Which of the following options BEST categorizes the test technique you are using?

Select ONE option.

19 / 40

19. In many software organizations the test department is called the Quality Assurance (QA) department. Is this sentence correct or not and why?

Select ONE option.

20 / 40

20. Which of the following statements BEST describes the difference between testing and debugging?

Select ONE option.

21 / 40

21. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

22 / 40

22. Which of the following statements about the value of static testing is CORRECT?

Select ONE option.

23 / 40

23. For a given risk, its risk level is $1,000 and its risk likelihood is estimated as 50%.

What is the risk impact?

Select ONE options.

24 / 40

24. Which of the following is MOST likely to describe a task performed by someone in a test management role?

Select ONE option.

25 / 40

25. You want to estimate the test effort for the new project using estimation based on ratios. You calculate the test-to-development effort ratio using averaged data for both development effort and test effort from four historical projects similar to the new one. The table shows this historical data.

The estimated development effort for the new project is $800,000. What is your estimate of the test effort in this project?

Select ONE option.

26 / 40

26. Which of the following provides the BEST description of the shift-left approach?

Select ONE option.

27 / 40

27. A designer documents a design for a user interface that does not suitably address disabled users because the designer is tired. The programmer implements the user interface in line with the design but as they are working under severe time pressure, they do not include suitable exception handling in their program code for bonus calculations. When the operational system is used, complaints are made by some disabled users about the interface and the company is subsequently fined by the relevant regulatory authority. No one notices that bonus calculations are sometimes incorrect.

Which of the following statements is CORRECT?

Select ONE option.

28 / 40

28. Which of the following is an example of a test-first approach to development?

Select ONE option.

29 / 40

29. You are a member of a test team located in North America, developing a product for a client located in Europe. The team is agile and follows the DevOps approach and uses a continuous integration/continuous delivery pipeline.

Which of the following is the LEAST effective way to communicate test progress to the customer?

Select ONE option.

30 / 40

30. A wine storage system uses a control device that measures the wine cell temperature T (measured in °C, rounded to the nearest degree) and alarms the user if it deviates from the optimal value of 12, according to the following rules:

• if T = 12, the system says, “optimal temperature”

• if T < 12, the system says, “temperature is too low!”

• if T > 12, the system says, “temperature is too high!”

You want to use the 3-point boundary value analysis (BVA) to verify the behavior of the control device. A test input is a temperature in °C provided by the device.

What is the MINIMAL set of test inputs that achieves 100% of the desired coverage?

Select ONE option.

31 / 40

31. You are preparing a test execution schedule for executing seven test cases TC 1 to TC 7.

The following figure includes the priorities of these test cases (1=highest priority, 3 = lowest priority).

The figure also shows the dependencies between test cases using arrows. For instance, the arrow from TC 4 to TC 5 means that TC 5 can only be executed if TC 4 was previously executed.

Which test case should be executed sixth?

Select ONE option.

32 / 40

32. Which of the following are advantages of DevOps?

i. Faster product release and faster time to market
ii. Increases the need for repetitive manual testing
iii. Constant availability of executable software
iv. Reduction in the number of regression tests associated with code refactoring
v. Setting up the test automation framework is inexpensive since everything is automated

Select ONE option.

33 / 40

33. Given the following task descriptions:

1. The quality characteristics to be evaluated and the exit criteria are selected
2. Everyone has access to the work product
3. Anomalies are identified in the work product
4. Anomalies are discussed

And the following review activities

A. Individual review
B. Review initiation
C. Planning
D. Communication and analysis

Which of the following BEST matches the task descriptions and activities?

Select ONE option.

34 / 40

34. Which of the following BEST describes how using checklist-based testing can result in increased coverage?

Select ONE option.

35 / 40

35. Which of the following BEST describes the way acceptance criteria can be documented?

Select ONE option.

36 / 40

36. Consider the following part of a test plan.

Testing will be performed using component testing and component integration testing. The regulations require to demonstrate that 100% branch coverage is achieved for each component classified as critical.

Which part of the test plan does this part belong to?

Select ONE option.

37 / 40

37. Which of the following is an example of why testing is necessary?

Select ONE option.

38 / 40

38. Which work product can be used by an agile team to show the amount of work that has been completed and the amount of total work remaining for a given iteration?

Select ONE option.

39 / 40

39. How can white-box testing be useful in support of black-box testing?

Select ONE option.

40 / 40

40. You are designing test cases based on the following state transition diagram:

What is the MINIMUM number of test cases required to achieve 100% valid transitions coverage?

Select ONE option.

0%

Scroll to top