ISTQB Learning

Test your knowledge

0%
35
Created on By Admin

Exam 5

1 / 40

1. Which of the following statements about the different testing roles is MOST likely to be CORRECT?

Select ONE option.

2 / 40

2. Consider the following list:

• Correct input not accepted
• Incorrect input accepted
• Wrong output format
• Division by zero

What test technique is MOST PROBABLY used by the tester who uses this list when performing testing?

Select ONE option.

3 / 40

3. Which of the following CANNOT be examined by static testing?

Select ONE option.

4 / 40

4. At the beginning of each iteration, the team estimates the amount of work (in person-days) they will need to complete during the iteration. Let E(n) be the estimated amount of work for iteration n, and let A(n) be the actual amount of work done in iteration n. From the third iteration, the team uses the following estimation model based on extrapolation:

 

 

The graph shows the estimated and actual amount of work for the first four iterations.

What is the estimated amount of work for iteration #5?

Select ONE option.

5 / 40

5. Which of the following is a typical test objective?

Select ONE option.

6 / 40

6. Your team uses the three-point estimation technique to estimate the test effort for a new high-risk feature. The following estimates were made:

• Most optimistic estimation: 2 person-hours
• Most likely estimation: 11 person-hours
• Most pessimistic estimation: 14 person-hours

What is the final estimate?

Select ONE option.

7 / 40

7. Consider the following part of a test plan.

Testing will be performed using component testing and component integration testing. The regulations require to demonstrate that 100% branch coverage is achieved for each component classified as critical.

Which part of the test plan does this part belong to?

Select ONE option.

8 / 40

8. Given the following test tasks:

1. Derive test cases from test conditions
2. Identify reusable testware
3. Organize test cases into test procedures
4. Evaluate test basis and test object

And the following test activities:

A. Test analysis
B. Test design
C. Test implementation
D. Test completion

Which of the following BEST matches the tasks with the activities?

Select ONE option.

9 / 40

9. You test a system whose lifecycle is modeled by the state transition diagram shown below. The system starts in the INIT state and ends its operation in the OFF state.

What is the MINIMAL number of test cases to achieve valid transitions coverage?

Select ONE option.

10 / 40

10. Which of the following is MOST likely to be a benefit of test automation?

Select ONE option.

11 / 40

11. Which of the following is NOT a benefit of static testing?

Select ONE option.

12 / 40

12. Which of the following statements about branch testing is CORRECT?

Select ONE option.

13 / 40

13. You are testing a form that verifies the correctness of the length of the password given as input. The form accepts a password with the correct length and rejects a password that is too short or too long. The password length is correct if it has between 6 and 12 characters inclusive. Otherwise, it is considered incorrect.

At first, the form is empty (password length = 0). You apply boundary value analysis to the “password length” variable.

Your set of test cases achieves 100% 2-value boundary value coverage. The team decided that due to the high risk of this component, test cases should be added to ensure 100% 3-value boundary value coverage.

Which additional password lengths should be tested to achieve this?

Select ONE option.

14 / 40

14. Which of the following statements about quality assurance (QA) and/or quality control (QC) is correct?

Select ONE option.

15 / 40

15. Which of the following is an example of a defect that can be found by static testing but NOT by dynamic testing?

Select ONE option.

16 / 40

16. What is the relationship between the testing quadrants, test levels and test types?

Select ONE option.

17 / 40

17. A storage system can store up to three elements and is modeled by the following state transition diagram. The variable N represents the number of currently stored elements.

Which of the following test cases, represented as sequences of events, achieves the highest level of valid transitions coverage?

Select ONE option.

18 / 40

18. Which of the following BEST describes the way acceptance criteria can be documented?

Select ONE option.

19 / 40

19. For a given risk, its risk level is $1,000 and its risk likelihood is estimated as 50%.

What is the risk impact?

Select ONE options.

20 / 40

20. Which of the following tests is MOST likely to be performed as part of functional testing?

Select ONE option.

21 / 40

21. You are working on a project to develop a system to analyze driving test results. You have been asked to design test cases based on the following decision table.

What test data will show that there are contradictory rules in the decision table?

Select ONE option.

22 / 40

22. Consider the following test categories (1-4) and agile testing quadrants (A-D):

1. Usability testing
2. Component testing
3. Functional testing
4. Reliability testing

A. Agile testing quadrant Q1: technology facing, supporting the development team
B. Agile testing quadrant Q2: business facing, supporting the development team
C. Agile testing quadrant Q3: business facing, critique the product
D. Agile testing quadrant Q4: technology facing, critique the product

How do the following test categories map onto the agile testing quadrants?

Select ONE option.

23 / 40

23. Which of the following is an example of a test-first approach to development?

Select ONE option.

24 / 40

24. Which of the following is the BEST example of how traceability supports testing?

Select ONE option.

25 / 40

25. Which of the following is LEAST likely to occur as a result of a retrospective?

Select ONE option.

26 / 40

26. Your team follows the process that uses the DevOps delivery pipeline. The first three steps of this process are:

(1) Code development
(2) Submit code into a version control system and merge it into the “test” branch
(3) Perform component testing for the submitted code

Which of the following is BEST suited to be the entry criterion for step (2) of this pipeline?

Select ONE option.

27 / 40

27. Your team uses planning poker to estimate the test effort for a newly required feature. There is a rule in your team that if there is no time to reach full agreement and the variation in the results is small, applying rules like “accept the number with the most votes” can be applied.
After two rounds, the consensus was not reached, so the third round was initiated. You can see the test estimation results in the table below.

Which of the following is the BEST example of the next step?

Select ONE option.

28 / 40

28. Which TWO of the following statements provide the BEST rationale for using exploratory testing?

Select TWO options.

29 / 40

29. You were given a task to analyze and fix causes of failures in a new system to be released.

Which activity are you performing?

Select ONE option.

30 / 40

30. Which of the following statements about the independence of testing is CORRECT?

Select ONE option.

31 / 40

31. Given the following testware:

i. Test completion report
ii. Data held in a database used for test inputs and expected results
iii. The list of elements needed to build the test environment
iv. Documented sequences of test cases in execution order
v. Test cases

Which of the following BEST shows the testware produced as a result of performing test implementation?

Select ONE option.

32 / 40

32. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

33 / 40

33. Which of the following is an example of a test-first approach to development?

Select ONE option.

34 / 40

34. Given the following test tool categories:

i. Collaboration tools
ii. DevOps tools
iii. Management tools
iv. Non-functional testing tools
v. Test design and implementation tools

Tools from which of the categories are MOST likely to facilitate test execution?

Select ONE options.

35 / 40

35. You are preparing a test execution schedule for executing seven test cases TC 1 to TC 7.

The following figure includes the priorities of these test cases (1=highest priority, 3 = lowest priority).

The figure also shows the dependencies between test cases using arrows. For instance, the arrow from TC 4 to TC 5 means that TC 5 can only be executed if TC 4 was previously executed.

Which test case should be executed sixth?

Select ONE option.

36 / 40

36. Which of the following BEST define EXIT criteria in a testing project?

Select TWO options.

37 / 40

37. Which of the following is an example of a test-first approach to development?

Select ONE option.

38 / 40

38. Consider the following testware.

Which test activity produces this testware as an output?

Select ONE option.

39 / 40

39. You are working as a tester in the team that follows the V-model. The choice of software development lifecycle (SDLC) model impacts the timing of testing, which of the following statement is NOT true?

Select ONE option.

40 / 40

40. Given the following benefits and drawbacks of the independence of testing:

i. The testers work in a different location from the developers
ii. Testers question the assumptions programmers make while writing code
iii. A confrontational dynamic has been established between testers and developers
iv. Developers have convinced themselves that testers are mostly accountable for quality
v. Testers have different biases than those held by the developers

Which are MOST likely to be considered benefits?

Select ONE option.

0%

Scroll to top