ISTQB Learning

Test your knowledge

0%
35
Created on By Admin

Exam 5

1 / 40

1. Which of the following is MOST likely to be a risk of test automation?

Select ONE options.

2 / 40

2. You are working on a project to develop a system to analyze driving test results. You have been asked to design test cases based on the following decision table.

What test data will show that there are contradictory rules in the decision table?

Select ONE option.

3 / 40

3. In your project there has been a delay in the release of a brand-new application and test execution started late, but you have very detailed domain knowledge and good analytical skills. The full list of requirements has not yet been shared with the team, but management is asking for some test results to be presented.

Which test technique fits BEST in this situation?

Select ONE option.

4 / 40

4. The following list contains risks that have been identified for a new software product to be developed:

i. Management moves two experienced testers to another project
ii. The system does not comply with functional safety standards
iii. System response time exceeds user requirements
iv. Stakeholders have inaccurate expectations
v. Disabled people have problems when using the system

Which of them are project risks?

Select ONE option.

5 / 40

5. You work as a tester in a project on a mobile application for food ordering for one of your clients. The client sent you a list of requirements. One of them, with high priority, says

“The order must be processed in less than 10 seconds in 95% of the cases”.

You created a set of test cases in which a number of random orders were made, the processing time measured, and the test results were checked against the requirements.

What test type did you perform?

Select ONE option.

6 / 40

6. Which item correctly identifies a potential risk of performing test automation?

Select ONE option.

7 / 40

7. W A developer was asked to implement the following business rule:

You design the test cases using 2-value boundary value analysis.

Which of the following sets of test inputs achieves the greatest coverage?

Select ONE option.

8 / 40

8. Which of the following is MOST likely to be performed as part of system testing?

Select ONE option.

9 / 40

9. Which of the following BEST describes an example of how configuration management (CM) supports testing?

Select ONE option.

10 / 40

10. The user reported a software failure. An engineer from the support team asked the user for the software version number where the failure was observed. Based on the version number, the team reassembled all the files that made up the release. This later allowed a developer to perform analysis, find the defect, and fix it.

Which of the following enabled the above activity to be performed by the team?

Select ONE options.

11 / 40

11. Your organization’s test strategy suggests that once a system is going to be retired, data migration shall be tested. As part of what test type is this testing MOST likely to be performed?

Select ONE option.

12 / 40

12. Which of the following statements about the chosen software development lifecycle is CORRECT?

Select ONE option.

13 / 40

13. Tools from which of the following categories help with the organization of test cases, detected defects and configuration management?

 

Select ONE option.

14 / 40

14. The ‘absence-of-defects fallacy’ is one of the principles of testing. Which of the following is an example of addressing this principle in practice?

Select ONE option.

15 / 40

15. How is the whole team approach present in the interactions between testers and business representatives?

Select ONE option.

16 / 40

16. Your favorite bicycle daily rental store has just introduced a new Customer Relationship Management system and asked you, one of their most loyal members, to test it.
The implemented features are as follows:

• Anyone can rent a bicycle, but members receive a 20% discount
• However, if the return deadline is missed, the discount is no longer available
• After 15 rentals, members get a gift: a T-Shirt

Decision table describing the implemented features looks as follows:

Based ONLY on the feature description of the Customer Relationship Management system, which of the above rules describes an impossible situation?

 

Select ONE option.

17 / 40

17. What is the relationship between the testing quadrants, test levels and test types?

Select ONE option.

18 / 40

18. Your test suite S for a program P achieves 100% statement coverage. It consists of three test cases, each of which achieves 50% statement coverage.

Which of the following statements is CORRECT?

Select ONE option.

19 / 40

19. You are designing test cases based on the following state transition diagram:

What is the MINIMUM number of test cases required to achieve 100% valid transitions coverage?

Select ONE option.

20 / 40

20. Which of the following is a factor that contributes to a successful review?

Select ONE option.

21 / 40

21. You want to estimate the test effort for the new project using estimation based on ratios. You calculate the test-to-development effort ratio using averaged data for both development effort and test effort from four historical projects similar to the new one. The table shows this historical data.

The estimated development effort for the new project is $800,000. What is your estimate of the test effort in this project?

Select ONE option.

22 / 40

22. What is the MAIN difference between black-box test techniques and experience-based test techniques?

Select ONE option.

23 / 40

23. Which of the following statements is CORRECT?

Select ONE option.

24 / 40

24. Given the following benefits and drawbacks of the independence of testing:

i. The testers work in a different location from the developers
ii. Testers question the assumptions programmers make while writing code
iii. A confrontational dynamic has been established between testers and developers
iv. Developers have convinced themselves that testers are mostly accountable for quality
v. Testers have different biases than those held by the developers

Which are MOST likely to be considered benefits?

Select ONE option.

25 / 40

25. Which of the following is NOT an example of the shift left approach?

Select ONE option.

26 / 40

26. You are testing a PIN validator, which accepts valid PINs and rejects invalid PINs. A PIN is a sequence of digits. A PIN is valid if it consists of four digits, at least two of which are different. You have identified the following valid equivalence partitions:

Variable: PIN code length

• The partition “length correct” - four-digit PINs
• The partition “length incorrect” - PINs with length other than 4

Variable: Number of different digits

• The partition “number of different digits correct” - PINs with at least two different digits
• The partition “number of different digits incorrect” - PINs with all digits being the same

Which of the following is a MINIMUM set of input test data that covers all identified equivalence partitions?

Select ONE option.

27 / 40

27. Which of the following is a benefit of early and frequent stakeholder feedback?

Select ONE option.

28 / 40

28. Which of the following is an advantage of the whole-team approach?

Select ONE option.

29 / 40

29. Given the following descriptions of review activities:

1. Detected anomalies are deliberated upon, and determinations are reached regarding their status, ownership, and any further steps needed
2. Issues are recorded, and any needed updates are addressed prior to the acceptance of the work product
3. Reviewers employ techniques to come up with suggestions and questions about the work product and to spot anomalies
4. The objective of the review and its schedule are established to ensure a focused and efficient review
5. Participants are provided with access to the item being reviewed

Which of the following is the CORRECT sequence in the review process of the activities that correspond to the descriptions?

Select ONE option.

30 / 40

30. Which of the following is NOT a valid purpose for a test report?

Select ONE options.

31 / 40

31. Decide which of the following statements (i-v) are true for static testing.

i. Abnormal external behaviors are easier to identify with this testing
ii. Discrepancies from a coding standard are easier to find with this testing
iii. It identifies failures caused by defects when the software is run
iv. Its test objective is to identify defects as early as possible
v. Missing coverage for critical security requirements is easier to find and fix

Select ONE option.

32 / 40

32. Given the following risks:

1. Ineffective loop implementation causes long system responses
2. Consumers change their preferences
3. Flooding of the server room
4. Patients above a certain age receive inaccurate reports

And the following mitigation activities:

A. Risk acceptance
B. Performance testing
C. Using boundary value analysis as the test technique
D. Risk transfer

Which of the following BEST matches the risks with the mitigation activities?

Select ONE option.

33 / 40

33. Which of the following is LEAST likely to occur as a result of a retrospective?

Select ONE option.

34 / 40

34. Which of the following is an advantage of the whole team approach?

Select ONE option.

35 / 40

35. Which of the following is an example of a test-first approach to development?

Select ONE option.

36 / 40

36. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

37 / 40

37. You are testing a mobile application that allows users to find a nearby restaurant based on the type of food they want to eat. Consider the following list of test cases, priorities (i.e., a smaller number means a higher priority), and dependencies:

Which of the following test cases should be executed as the third one?

Select ONE option.

38 / 40

38. You are testing a web application that allows users to SEARCH for products, VIEW product details, ADD products to a shopping cart, and place an ORDER.
You have prepared the following five test cases, which you want to execute according to their priorities:

TC1: SEARCH product A Priority: medium

TC2: VIEW product A details Priority: low

TC3: ADD product B to a shopping cart Priority: medium

TC4: ADD product C to a shopping cart Priority: high

TC5: place an ORDER Priority: high

You also identified the following logical dependencies between test cases:

• SEARCH functionality must be tested before VIEW functionality can be tested, as product details rely on search functionality.
• VIEW functionality must be tested before ADD functionality, as adding products relies on the availability of accurate product details.
• ADD functionality must be tested before ORDER functionality, as placing an order relies on the availability of accurate shopping cart information.

Which test case should be executed as the fourth one?

Select ONE option.

39 / 40

39. Which of the following is NOT anticipated by the tester while applying error guessing?

Select ONE option.

40 / 40

40. Why does white-box testing facilitate defect detection even when the software specification is vague, outdated or incomplete?

Select ONE option.

0%

Scroll to top