ISTQB Learning

Test your knowledge

0%
13
Created on By Admin

Exam 5 - 75 minutes

1 / 40

1. Which test activity does a data preparation tool support?

Select ONE option.

2 / 40

2. You have been assigned as a tester to a team producing a new system incrementally. You have noticed that no changes have been made to the existing regression test cases for several iterations and no new regression defects were identified. Your manager is happy, but you are not. Which testing principle explains your skepticism?

Select ONE option.

3 / 40

3. Which of the following are product risks?

Select TWO options.

4 / 40

4. Which of the following is a typical test objective?

Select ONE option.

5 / 40

5. Which of the following factors (i-v) have SIGNIFICANT influence on the test process?

i. The SDLC
ii. The number of defects detected in previous projects
iii. The identified product risks
iv. New regulatory requirements forcing formal white-box testing
v. The test environment setup

Select ONE option.

6 / 40

6. Which of the following is MOST likely to impact how testing is performed for a given test object?

Select ONE option.

7 / 40

7. Which of the following statements about the independence of testing is CORRECT?

Select ONE option.

8 / 40

8. Which of the following is NOT a valid purpose for a test report?

Select ONE options.

9 / 40

9. During risk analysis the team considered the following risk: “The system allows too high a discount for a customer”. The team estimated the risk impact to be very high.

What can one say about the risk likelihood?

Select ONE option.

10 / 40

10. You have just started designing test cases for the following user story.

In all test cases the precondition is as follows: there are only two products available, products A and B. Product A costs $100 and product B costs $110.

Which of the following is the BEST example of a test case for this user story?

Select ONE option.

11 / 40

11. Which of the following is an example of a test-first approach to development?

Select ONE option.

12 / 40

12. Which of the following statements about branch testing is CORRECT?

Select ONE option.

13 / 40

13. Which of the following is MOST likely to be a benefit of test automation?

Select ONE option.

14 / 40

14. Given the following benefits and drawbacks of the independence of testing:

i. The testers work in a different location from the developers
ii. Testers question the assumptions programmers make while writing code
iii. A confrontational dynamic has been established between testers and developers
iv. Developers have convinced themselves that testers are mostly accountable for quality
v. Testers have different biases than those held by the developers

Which are MOST likely to be considered benefits?

Select ONE option.

15 / 40

15. Which of the following is a product quality metric?

Select ONE option.

16 / 40

16. You test a system whose lifecycle is modeled by the state transition diagram shown below. The system starts in the INIT state and ends its operation in the OFF state.

What is the MINIMAL number of test cases to achieve valid transitions coverage?

Select ONE option.

17 / 40

17. You received the following defect report from the developers stating that the anomaly described in this test report is not reproducible.

Application hangs up
2022-May-03 – John Doe – Rejected
The application hangs up after entering “Test input: $ä” in the Name field on the new user creation screen. Tried to log off, log in with test_admin01 account, same issue. Tried with other test admin accounts, same issue. No error message received; log (see attached) contains fatal error notification. Based on the test case TC-1305, the application should accept the provided input and create the user. Please fix with high priority, this feature is related to REQ-0012, which is a critical new business requirement.

What critical information is MISSING from this test report that would have been useful for the developers?

Select ONE option.

18 / 40

18. Your test suite achieved 100% statement coverage. What is the consequence of this fact?

Select ONE option.

19 / 40

19. Which of the following statements BEST describes the difference between testing and debugging?

Select ONE option.

20 / 40

20. Which of the following BEST fits as an element of the checklist used in checklist-based testing?

Select ONE option.

21 / 40

21. The reviews being used in your organization have the following attributes:

• There is the role of a scribe
• The main purpose is to evaluate quality
• The meeting is led by the author of the work product
• There is individual preparation
• A review report is produced

Which of the following review types is MOST likely being used?

Select ONE option.

22 / 40

22. Which of the following is an example of a defect that can be found by static testing but NOT by dynamic testing?

Select ONE option.

23 / 40

23. Which of the following is MOST likely to be a risk of test automation?

Select ONE options.

24 / 40

24. Which of the following is the BEST example of how traceability supports testing?

Select ONE option.

25 / 40

25. Which of the following BEST describes the concept behind error guessing?

Select ONE option.

26 / 40

26. Which of the following is MOST likely to be a trigger that leads to maintenance testing of a currency exchange system?

Select ONE option.

27 / 40

27. Your team follows the process that uses the DevOps delivery pipeline. The first three steps of this process are:

(1) Code development
(2) Submit code into a version control system and merge it into the “test” branch
(3) Perform component testing for the submitted code

Which of the following is BEST suited to be the entry criterion for step (2) of this pipeline?

Select ONE option.

28 / 40

28. The team wants to estimate the time needed for one tester to execute four test cases for a software component. The team has gathered the following measures of the effort used to execute a single test case:

• Best-case scenario: 1 hour
• Worst-case scenario: 8 hours
• Most likely scenario: 3 hours

Given that the three-point estimation technique is being used, what is the final estimate of the time needed to execute all four test cases?

Select ONE option.

29 / 40

29. At the beginning of each iteration, the team estimates the amount of work (in person-days) they will need to complete during the iteration. Let E(n) be the estimated amount of work for iteration n, and let A(n) be the actual amount of work done in iteration n. From the third iteration, the team uses the following estimation model based on extrapolation:

 

 

The graph shows the estimated and actual amount of work for the first four iterations.

What is the estimated amount of work for iteration #5?

Select ONE option.

30 / 40

30. You are working as a tester in the team that follows the V-model. The choice of software development lifecycle (SDLC) model impacts the timing of testing, which of the following statement is NOT true?

Select ONE option.

31 / 40

31. Which of the following test activities are MOST likely to involve the application of boundary value analysis and equivalence partitioning?

Select TWO options.

32 / 40

32. Which TWO of the following options are common metrics used for reporting on the quality level of the test object?

Select TWO options.

33 / 40

33. In your project there has been a delay in the release of a brand-new application and test execution started late, but you have very detailed domain knowledge and good analytical skills. The full list of requirements has not yet been shared with the team, but management is asking for some test results to be presented.

Which test technique fits BEST in this situation?

Select ONE option.

34 / 40

34. Given the following roles in reviews:

1. Scribe
2. Review leader
3. Facilitator
4. Manager

And the following responsibilities in reviews:

A. Ensures the effective running of review meetings and the setting up a safe review environment
B. Records review information, such as decisions and new anomalies found during the review meeting
C. Decides what is to be reviewed and provides resources, such as staff and time for the review
D. Takes overall responsibility for the review such as organizing when and where the review will take place

Which of the following BEST matches the roles and responsibilities?

Select ONE option.

35 / 40

35. Which of the following statements is a CORRECT example of the value of traceability?

Select ONE option.

36 / 40

36. Which TWO of the following statements provide the BEST rationale for using exploratory testing?

Select TWO options.

37 / 40

37. Which work product can be used by an agile team to show the amount of work that has been completed and the amount of total work remaining for a given iteration?

Select ONE option.

38 / 40

38. Given the following testware:

i. Test completion report
ii. Data held in a database used for test inputs and expected results
iii. The list of elements needed to build the test environment
iv. Documented sequences of test cases in execution order
v. Test cases

Which of the following BEST shows the testware produced as a result of performing test implementation?

Select ONE option.

39 / 40

39. Which of the following is an advantage of the whole-team approach?

Select ONE option.

40 / 40

40. Which of the following is LEAST likely to occur as a result of a retrospective?

Select ONE option.

0%

Scroll to top