ISTQB Learning

Test your knowledge

0%
13
Created on By Admin

Exam 5 - 75 minutes

1 / 40

1. You are working as a tester in the team that follows the V-model. The choice of software development lifecycle (SDLC) model impacts the timing of testing, which of the following statement is NOT true?

Select ONE option.

2 / 40

2. Consider the following defect report for a web-based shopping application:

What is the MOST important information that is missing from this report?

Select ONE option.

3 / 40

3. You are testing a user story with three acceptance criteria: AC1, AC2 and AC3. AC1 is covered by test case TC1, AC2 by TC2, and AC3 by TC3. The test execution history had three test runs on three consecutive versions of the software as follows:

Tests are repeated once you are informed that all defects found in the test run are corrected and a new version of the software is available.
Which of the above tests are executed as regression tests?

Select ONE option.

4 / 40

4. Decide which of the following statements (i-v) are true for static testing.

i. Abnormal external behaviors are easier to identify with this testing
ii. Discrepancies from a coding standard are easier to find with this testing
iii. It identifies failures caused by defects when the software is run
iv. Its test objective is to identify defects as early as possible
v. Missing coverage for critical security requirements is easier to find and fix

Select ONE option.

5 / 40

5. Which of the following pieces of information contained in a test progress report is the LEAST useful for business representatives?

Select ONE option.

6 / 40

6. Which of the following statements BEST describes the difference between decision table testing and branch testing?

Select ONE option.

7 / 40

7. You need to update one of the automated test scripts to be in line with a new requirement. Which process indicates that you create a new version of the test script in the test repository?

Select ONE option.

8 / 40

8. Which of the following is NOT an example of the shift left approach?

Select ONE option.

9 / 40

9. Consider the following rule: “for every SDLC activity there is a corresponding test activity”. In which SDLC models does this rule hold?

Select ONE option.

10 / 40

10. You are preparing a test execution schedule for executing seven test cases TC 1 to TC 7.

The following figure includes the priorities of these test cases (1=highest priority, 3 = lowest priority).

The figure also shows the dependencies between test cases using arrows. For instance, the arrow from TC 4 to TC 5 means that TC 5 can only be executed if TC 4 was previously executed.

Which test case should be executed sixth?

Select ONE option.

11 / 40

11. A phone ringing in a neighboring cubicle distracts a programmer causing him to improperly program the logic that checks the upper boundary of an input variable. Later, during system testing, a tester notices that this input field accepts invalid input values.

Which of the following correctly describes an incorrectly coded upper bound?

Select ONE option.

12 / 40

12. According to the testing quadrants model, which of the following falls into quadrant Q1 (“technology facing” and “support the team”)?

Select ONE option.

13 / 40

13. Your favorite bicycle daily rental store has just introduced a new Customer Relationship Management system and asked you, one of their most loyal members, to test it.
The implemented features are as follows:

• Anyone can rent a bicycle, but members receive a 20% discount
• However, if the return deadline is missed, the discount is no longer available
• After 15 rentals, members get a gift: a T-Shirt

Decision table describing the implemented features looks as follows:

Based ONLY on the feature description of the Customer Relationship Management system, which of the above rules describes an impossible situation?

 

Select ONE option.

14 / 40

14. You test a system whose lifecycle is modeled by the state transition diagram shown below. The system starts in the INIT state and ends its operation in the OFF state.

What is the MINIMAL number of test cases to achieve valid transitions coverage?

Select ONE option.

15 / 40

15. The following is a list of the work products produced in the SDLC.

i. Business requirements
ii. Schedule
iii. Test budget
iv. Third-party executable code
v. User stories and their acceptance criteria

Which of them can be reviewed?

Select ONE option.

16 / 40

16. Which of the following statements BEST describes the acceptance test-driven development (ATDD) approach?

Select ONE option.

17 / 40

17. Which of the following is MOST likely to describe a task performed by someone in a test management role?

Select ONE option.

18 / 40

18. Which of the following statements is a CORRECT example of the value of traceability?

Select ONE option.

19 / 40

19. A designer documents a design for a user interface that does not suitably address disabled users because the designer is tired. The programmer implements the user interface in line with the design but as they are working under severe time pressure, they do not include suitable exception handling in their program code for bonus calculations. When the operational system is used, complaints are made by some disabled users about the interface and the company is subsequently fined by the relevant regulatory authority. No one notices that bonus calculations are sometimes incorrect.

Which of the following statements is CORRECT?

Select ONE option.

20 / 40

20. You are using acceptance test-driven development and designing test cases based on the following user story:

Which test case is the MOST reasonable one to test AC3?

Select ONE option.

21 / 40

21. Which of the following is an example of a test-first approach to development?

Select ONE option.

22 / 40

22. Which TWO of the following statements provide the BEST rationale for using exploratory testing?

Select TWO options.

23 / 40

23. In many software organizations the test department is called the Quality Assurance (QA) department. Is this sentence correct or not and why?

Select ONE option.

24 / 40

24. Consider the following list:

• Correct input not accepted
• Incorrect input accepted
• Wrong output format
• Division by zero

What test technique is MOST PROBABLY used by the tester who uses this list when performing testing?

Select ONE option.

25 / 40

25. Which participant in the review process is responsible for ensuring that the review meetings run effectively and that everyone at the meetings can voice their opinions freely?

Select ONE option.

26 / 40

26. Which of the following activities in the test process makes the MOST use of test progress reports?

Select ONE option.

27 / 40

27. The user reported a software failure. An engineer from the support team asked the user for the software version number where the failure was observed. Based on the version number, the team reassembled all the files that made up the release. This later allowed a developer to perform analysis, find the defect, and fix it.

Which of the following enabled the above activity to be performed by the team?

Select ONE options.

28 / 40

28. Which of the following statements is CORRECT?

Select ONE option.

29 / 40

29. During a risk analysis the following risk was identified and assessed:

• Risk: Response time is too long to generate a report
• Risk likelihood: medium; risk impact: high
• Response to risk:

o An independent test team performs performance testing during system testing
o A selected sample of end users performs alpha and beta acceptance testing before the release

What measure is proposed to be taken in response to this analyzed risk?

Select ONE option.

30 / 40

30. Which of the following statements about quality assurance (QA) and/or quality control (QC) is correct?

Select ONE option.

31 / 40

31. Which of the following test activities are MOST likely to involve the application of boundary value analysis and equivalence partitioning?

Select TWO options.

32 / 40

32. Consider the following user story:

As an Editor
I want to review content before it is published
so that I can assure the grammar is correct

and its acceptance criteria:

• The user can log in to the content management system with "Editor" role
• The editor can view existing content pages
• The editor can edit the page content
• The editor can add markup comments
• The editor can save changes
• The editor can reassign to the "content owner" role to make updates

Which of the following is the BEST example of an ATDD test for this user story?

Select ONE option.

33 / 40

33. Consider the following part of a test plan.

Testing will be performed using component testing and component integration testing. The regulations require to demonstrate that 100% branch coverage is achieved for each component classified as critical.

Which part of the test plan does this part belong to?

Select ONE option.

34 / 40

34. You received the following defect report from the developers stating that the anomaly described in this test report is not reproducible.

Application hangs up
2022-May-03 – John Doe – Rejected
The application hangs up after entering “Test input: $ä” in the Name field on the new user creation screen. Tried to log off, log in with test_admin01 account, same issue. Tried with other test admin accounts, same issue. No error message received; log (see attached) contains fatal error notification. Based on the test case TC-1305, the application should accept the provided input and create the user. Please fix with high priority, this feature is related to REQ-0012, which is a critical new business requirement.

What critical information is MISSING from this test report that would have been useful for the developers?

Select ONE option.

35 / 40

35. Why does white-box testing facilitate defect detection even when the software specification is vague, outdated or incomplete?

Select ONE option.

36 / 40

36. You were given a task to analyze and fix causes of failures in a new system to be released.

Which activity are you performing?

Select ONE option.

37 / 40

37. During risk analysis the team considered the following risk: “The system allows too high a discount for a customer”. The team estimated the risk impact to be very high.

What can one say about the risk likelihood?

Select ONE option.

38 / 40

38. Which of the following statements describe a valid test objective?

Select ONE option.

39 / 40

39. In your project there has been a delay in the release of a brand-new application and test execution started late, but you have very detailed domain knowledge and good analytical skills. The full list of requirements has not yet been shared with the team, but management is asking for some test results to be presented.

Which test technique fits BEST in this situation?

Select ONE option.

40 / 40

40. Which of the following is a typical test objective?

Select ONE option.

0%

Scroll to top