ISTQB Learning

Test your knowledge

0%
13
Created on By Admin

Exam 5 - 75 minutes

1 / 40

1. Which of the following are product risks?

Select TWO options.

2 / 40

2. Consider the following testware.

Which test activity produces this testware as an output?

Select ONE option.

3 / 40

3. Given the following test tool categories:

i. Collaboration tools
ii. DevOps tools
iii. Management tools
iv. Non-functional testing tools
v. Test design and implementation tools

Tools from which of the categories are MOST likely to facilitate test execution?

Select ONE options.

4 / 40

4. The ‘absence-of-defects fallacy’ is one of the principles of testing. Which of the following is an example of addressing this principle in practice?

Select ONE option.

5 / 40

5. Given the following benefits and drawbacks of the independence of testing:

i. The testers work in a different location from the developers
ii. Testers question the assumptions programmers make while writing code
iii. A confrontational dynamic has been established between testers and developers
iv. Developers have convinced themselves that testers are mostly accountable for quality
v. Testers have different biases than those held by the developers

Which are MOST likely to be considered benefits?

Select ONE option.

6 / 40

6. You test a system whose lifecycle is modeled by the state transition diagram shown below. The system starts in the INIT state and ends its operation in the OFF state.

What is the MINIMAL number of test cases to achieve valid transitions coverage?

Select ONE option.

7 / 40

7. Which of the following CANNOT be examined by static testing?

Select ONE option.

8 / 40

8. Your organization’s test strategy suggests that once a system is going to be retired, data migration shall be tested. As part of what test type is this testing MOST likely to be performed?

Select ONE option.

9 / 40

9. You are testing a mobile application that allows customers to access and manage their bank accounts. You are running a test suite that involves evaluating each screen, and each field on each screen, against a general list of user interface best practices derived from a popular book on the topic that maximizes attractiveness, ease-of-use, and accessibility for such applications. Which of the following options BEST categorizes the test technique you are using?

Select ONE option.

10 / 40

10. At the beginning of each iteration, the team estimates the amount of work (in person-days) they will need to complete during the iteration. Let E(n) be the estimated amount of work for iteration n, and let A(n) be the actual amount of work done in iteration n. From the third iteration, the team uses the following estimation model based on extrapolation:

 

 

The graph shows the estimated and actual amount of work for the first four iterations.

What is the estimated amount of work for iteration #5?

Select ONE option.

11 / 40

11. Which of the following statements about the value of static testing is CORRECT?

Select ONE option.

12 / 40

12. Which of the following is NOT a purpose of a test plan?

Select ONE option.

13 / 40

13. Which of the following BEST describes an example of how configuration management (CM) supports testing?

Select ONE option.

14 / 40

14. Which of the following is MOST likely to be a benefit of test automation?

 

Select ONE option.

15 / 40

15. Which of the following is NOT a benefit of static testing?

Select ONE option.

16 / 40

16. Which of the following BEST define EXIT criteria in a testing project?

Select TWO options.

17 / 40

17. Which of the following statements about quality assurance (QA) and/or quality control (QC) is correct?

Select ONE option.

18 / 40

18. Given the following test tasks:

1. Derive test cases from test conditions
2. Identify reusable testware
3. Organize test cases into test procedures
4. Evaluate test basis and test object

And the following test activities:

A. Test analysis
B. Test design
C. Test implementation
D. Test completion

Which of the following BEST matches the tasks with the activities?

Select ONE option.

19 / 40

19. Which item correctly identifies a potential risk of performing test automation?

Select ONE option.

20 / 40

20. Which test activity involves working with test data requirements, test conditions, test environment requirements and test cases?

Select ONE option.

21 / 40

21. You are testing a user story with three acceptance criteria: AC1, AC2 and AC3. AC1 is covered by test case TC1, AC2 by TC2, and AC3 by TC3. The test execution history had three test runs on three consecutive versions of the software as follows:

Tests are repeated once you are informed that all defects found in the test run are corrected and a new version of the software is available.
Which of the above tests are executed as regression tests?

Select ONE option.

22 / 40

22. Which of the following provides the BEST description of the shift-left approach?

Select ONE option.

23 / 40

23. A designer documents a design for a user interface that does not suitably address disabled users because the designer is tired. The programmer implements the user interface in line with the design but as they are working under severe time pressure, they do not include suitable exception handling in their program code for bonus calculations. When the operational system is used, complaints are made by some disabled users about the interface and the company is subsequently fined by the relevant regulatory authority. No one notices that bonus calculations are sometimes incorrect.

Which of the following statements is CORRECT?

Select ONE option.

24 / 40

24. You run two test cases, T1 and T2, on the same code. Test T1 achieved 40% statement coverage and test T2 achieved 65% statement coverage.

Which of the following sentences must be necessarily true?

Select ONE option.

25 / 40

25. Which of the following is a typical test objective?

Select ONE option.

26 / 40

26. Which of the following are advantages of DevOps?

i. Faster product release and faster time to market
ii. Increases the need for repetitive manual testing
iii. Constant availability of executable software
iv. Reduction in the number of regression tests associated with code refactoring
v. Setting up the test automation framework is inexpensive since everything is automated

Select ONE option.

27 / 40

27. Which of the following is MOST likely to be a challenge encountered when implementing DevOps?

Select ONE option.

28 / 40

28. The user reported a software failure. An engineer from the support team asked the user for the software version number where the failure was observed. Based on the version number, the team reassembled all the files that made up the release. This later allowed a developer to perform analysis, find the defect, and fix it.

Which of the following enabled the above activity to be performed by the team?

Select ONE options.

29 / 40

29. Consider the following defect report for a Book Lending System.

Which of the following is MOST likely to help the developer reproduce the failure quickly?

Select ONE options.

30 / 40

30. Which collaborative user story writing practice enables the team to achieve a collective understanding of what needs to be delivered?

Select ONE option.

31 / 40

31. Your team uses the three-point estimation technique to estimate the test effort for a new high-risk feature. The following estimates were made:

• Most optimistic estimation: 2 person-hours
• Most likely estimation: 11 person-hours
• Most pessimistic estimation: 14 person-hours

What is the final estimate?

Select ONE option.

32 / 40

32. What does the test pyramid model show?

Select ONE option.

33 / 40

33. Which of the following is MOST likely to impact how testing is performed for a given test object?

Select ONE option.

34 / 40

34. How do testers add value to iteration and release planning?

Select ONE option.

35 / 40

35. A storage system can store up to three elements and is modeled by the following state transition diagram. The variable N represents the number of currently stored elements.

Which of the following test cases, represented as sequences of events, achieves the highest level of valid transitions coverage?

Select ONE option.

36 / 40

36. Which of the following is an advantage of the whole-team approach?

Select ONE option.

37 / 40

37. Given the following risks:

1. Ineffective loop implementation causes long system responses
2. Consumers change their preferences
3. Flooding of the server room
4. Patients above a certain age receive inaccurate reports

And the following mitigation activities:

A. Risk acceptance
B. Performance testing
C. Using boundary value analysis as the test technique
D. Risk transfer

Which of the following BEST matches the risks with the mitigation activities?

Select ONE option.

38 / 40

38. During a risk analysis the following risk was identified and assessed:

• Risk: Response time is too long to generate a report
• Risk likelihood: medium; risk impact: high
• Response to risk:

o An independent test team performs performance testing during system testing
o A selected sample of end users performs alpha and beta acceptance testing before the release

What measure is proposed to be taken in response to this analyzed risk?

Select ONE option.

39 / 40

39. You are working as a tester in the team that follows the V-model. The choice of software development lifecycle (SDLC) model impacts the timing of testing, which of the following statement is NOT true?

Select ONE option.

40 / 40

40. Decide which of the following statements (i-v) are true for static testing.

i. Abnormal external behaviors are easier to identify with this testing
ii. Discrepancies from a coding standard are easier to find with this testing
iii. It identifies failures caused by defects when the software is run
iv. Its test objective is to identify defects as early as possible
v. Missing coverage for critical security requirements is easier to find and fix

Select ONE option.

0%

Scroll to top