ISTQB Learning

Test your knowledge

0%
13
Created on By Admin

Exam 5 - 75 minutes

1 / 40

1. Which TWO of the following options are common metrics used for reporting on the quality level of the test object?

Select TWO options.

2 / 40

2. The user reported a software failure. An engineer from the support team asked the user for the software version number where the failure was observed. Based on the version number, the team reassembled all the files that made up the release. This later allowed a developer to perform analysis, find the defect, and fix it.

Which of the following enabled the above activity to be performed by the team?

Select ONE options.

3 / 40

3. Which of the following is an advantage of the whole team approach?

Select ONE option.

4 / 40

4. The following list contains risks that have been identified for a new software product to be developed:

i. Management moves two experienced testers to another project
ii. The system does not comply with functional safety standards
iii. System response time exceeds user requirements
iv. Stakeholders have inaccurate expectations
v. Disabled people have problems when using the system

Which of them are project risks?

Select ONE option.

5 / 40

5. Which of the following statements about the different testing roles is MOST likely to be CORRECT?

Select ONE option.

6 / 40

6. Which of the following statements BEST describes the difference between decision table testing and branch testing?

Select ONE option.

7 / 40

7. You work as a tester in a project on a mobile application for food ordering for one of your clients. The client sent you a list of requirements. One of them, with high priority, says

“The order must be processed in less than 10 seconds in 95% of the cases”.

You created a set of test cases in which a number of random orders were made, the processing time measured, and the test results were checked against the requirements.

What test type did you perform?

Select ONE option.

8 / 40

8. You are testing a user story with three acceptance criteria: AC1, AC2 and AC3. AC1 is covered by test case TC1, AC2 by TC2, and AC3 by TC3. The test execution history had three test runs on three consecutive versions of the software as follows:

Tests are repeated once you are informed that all defects found in the test run are corrected and a new version of the software is available.
Which of the above tests are executed as regression tests?

Select ONE option.

9 / 40

9. Which of the following is a benefit of early and frequent stakeholder feedback?

Select ONE option.

10 / 40

10. Which of the following is true about exploratory testing?

Select ONE option.

11 / 40

11. Which of the arguments below would you use to convince your manager to organize retrospectives at the end of each release cycle?

Select ONE option.

12 / 40

12. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

13 / 40

13. Which of the following is an example of a defect that can be found by static testing but NOT by dynamic testing?

Select ONE option.

14 / 40

14. Which of the following is a characteristic of experience-based test techniques?

Select ONE option.

15 / 40

15. Which of the following is an example of a test-first approach to development?

Select ONE option.

16 / 40

16. Which of the following is an example of how product risk analysis influences thoroughness and scope of testing?

Select ONE option.

17 / 40

17. The reviews being used in your organization have the following attributes:

• There is the role of a scribe
• The main purpose is to evaluate quality
• The meeting is led by the author of the work product
• There is individual preparation
• A review report is produced

Which of the following review types is MOST likely being used?

Select ONE option.

18 / 40

18. Which of the following is NOT a benefit of static testing?

Select ONE option.

19 / 40

19. Which of the following BEST describe the collaborative approach to user story writing?

Select ONE option.

20 / 40

20. You are testing a sort function that gets a set of numbers as input and returns the same set of numbers sorted in ascending order. The log from the test execution looks as follows.

Which of the following provides the BEST description of the failure that can be used in a defect report?

Select ONE option.

21 / 40

21. How can white-box testing be useful in support of black-box testing?

Select ONE option.

22 / 40

22. Consider the following defect report for a Book Lending System.

Which of the following is MOST likely to help the developer reproduce the failure quickly?

Select ONE options.

23 / 40

23. Which of the following statements about the value of static testing is CORRECT?

Select ONE option.

24 / 40

24. Which of the following BEST define EXIT criteria in a testing project?

Select TWO options.

25 / 40

25. Consider the following defect report for a web-based shopping application:

What is the MOST important information that is missing from this report?

Select ONE option.

26 / 40

26. Which of the following statements is CORRECT?

Select ONE option.

27 / 40

27. Given the following roles in reviews:

1. Scribe
2. Review leader
3. Facilitator
4. Manager

And the following responsibilities in reviews:

A. Ensures the effective running of review meetings and the setting up a safe review environment
B. Records review information, such as decisions and new anomalies found during the review meeting
C. Decides what is to be reviewed and provides resources, such as staff and time for the review
D. Takes overall responsibility for the review such as organizing when and where the review will take place

Which of the following BEST matches the roles and responsibilities?

Select ONE option.

28 / 40

28. Given the following example defects:

i. Two different parts of the design specification disagree due to the complexity of the design
ii. A response time is too long and so makes users lose patience
iii. A path in the code cannot be reached during execution
iv. A variable is declared but never subsequently used in the program
v. The amount of memory needed by the program to generate a report is too high

Which of the following BEST identifies example defects that could be found by static testing (rather than dynamic testing)?

Select ONE option.

29 / 40

29. Which of these statements is NOT a factor that contributes to successful reviews?

Select ONE option.

30 / 40

30. Which of the following is MOST likely to be an example of a tester using a generic skill when testing?

Select ONE option.

31 / 40

31. How do testers add value to iteration and release planning?

Select ONE option.

32 / 40

32. Consider the following rule: “for every SDLC activity there is a corresponding test activity”. In which SDLC models does this rule hold?

Select ONE option.

33 / 40

33. Which of the following is NOT an example of the shift left approach?

Select ONE option.

34 / 40

34. Consider the following part of a test plan.

Testing will be performed using component testing and component integration testing. The regulations require to demonstrate that 100% branch coverage is achieved for each component classified as critical.

Which part of the test plan does this part belong to?

Select ONE option.

35 / 40

35. A storage system can store up to three elements and is modeled by the following state transition diagram. The variable N represents the number of currently stored elements.

Which of the following test cases, represented as sequences of events, achieves the highest level of valid transitions coverage?

Select ONE option.

36 / 40

36. Which of the following is a benefit of early and frequent feedback?

Select ONE option.

37 / 40

37. Which of the following are product risks?

Select TWO options.

38 / 40

38. Your test suite achieved 100% statement coverage. What is the consequence of this fact?

Select ONE option.

39 / 40

39. Your team uses the three-point estimation technique to estimate the test effort for a new high-risk feature. The following estimates were made:

• Most optimistic estimation: 2 person-hours
• Most likely estimation: 11 person-hours
• Most pessimistic estimation: 14 person-hours

What is the final estimate?

Select ONE option.

40 / 40

40. Consider the following list:

• Correct input not accepted
• Incorrect input accepted
• Wrong output format
• Division by zero

What test technique is MOST PROBABLY used by the tester who uses this list when performing testing?

Select ONE option.

0%

Scroll to top