ISTQB Learning

Test your knowledge

0%
13
Created on By Admin

Exam 5 - 75 minutes

1 / 40

1. Which of the following is a benefit of early and frequent stakeholder feedback?

Select ONE option.

2 / 40

2. The following is a list of the work products produced in the SDLC.

i. Business requirements
ii. Schedule
iii. Test budget
iv. Third-party executable code
v. User stories and their acceptance criteria

Which of them can be reviewed?

Select ONE option.

3 / 40

3. Which of the following are product risks?

Select TWO options.

4 / 40

4. During risk analysis the team considered the following risk: “The system allows too high a discount for a customer”. The team estimated the risk impact to be very high.

What can one say about the risk likelihood?

Select ONE option.

5 / 40

5. You want to estimate the test effort for the new project using estimation based on ratios. You calculate the test-to-development effort ratio using averaged data for both development effort and test effort from four historical projects similar to the new one. The table shows this historical data.

The estimated development effort for the new project is $800,000. What is your estimate of the test effort in this project?

Select ONE option.

6 / 40

6. Which of the following statements about branch testing is CORRECT?

Select ONE option.

7 / 40

7. Which of the following is MOST likely to be a challenge encountered when implementing DevOps?

Select ONE option.

8 / 40

8. Which work product can be used by an agile team to show the amount of work that has been completed and the amount of total work remaining for a given iteration?

Select ONE option.

9 / 40

9. Which of the following activities in the test process makes the MOST use of test progress reports?

Select ONE option.

10 / 40

10. Which of the following is the BEST example of how traceability supports testing?

Select ONE option.

11 / 40

11. Which of the following statements BEST describes the difference between testing and debugging?

Select ONE option.

12 / 40

12. Which participant in the review process is responsible for ensuring that the review meetings run effectively and that everyone at the meetings can voice their opinions freely?

Select ONE option.

13 / 40

13. What is the relationship between the testing quadrants, test levels and test types?

Select ONE option.

14 / 40

14. A designer documents a design for a user interface that does not suitably address disabled users because the designer is tired. The programmer implements the user interface in line with the design but as they are working under severe time pressure, they do not include suitable exception handling in their program code for bonus calculations. When the operational system is used, complaints are made by some disabled users about the interface and the company is subsequently fined by the relevant regulatory authority. No one notices that bonus calculations are sometimes incorrect.

Which of the following statements is CORRECT?

Select ONE option.

15 / 40

15. Given the following testware:

i. Test completion report
ii. Data held in a database used for test inputs and expected results
iii. The list of elements needed to build the test environment
iv. Documented sequences of test cases in execution order
v. Test cases

Which of the following BEST shows the testware produced as a result of performing test implementation?

Select ONE option.

16 / 40

16. Which of the following test activities are MOST likely to involve the application of boundary value analysis and equivalence partitioning?

Select TWO options.

17 / 40

17. Your organization’s test strategy suggests that once a system is going to be retired, data migration shall be tested. As part of what test type is this testing MOST likely to be performed?

Select ONE option.

18 / 40

18. You work in a team that develops a mobile application for food ordering. In the current iteration the team decided to implement the payment functionality.

Which of the following activities is a part of test analysis?

Select ONE option.

19 / 40

19. Which of the following options shows an example of test activities that contribute to success?

Select ONE option.

20 / 40

20. Why does white-box testing facilitate defect detection even when the software specification is vague, outdated or incomplete?

Select ONE option.

21 / 40

21. Which of the following is a product quality metric?

Select ONE option.

22 / 40

22. Which of the following is an advantage of the whole team approach?

Select ONE option.

23 / 40

23. Which of the following is NOT a benefit of static testing?

Select ONE option.

24 / 40

24. You are testing a PIN validator, which accepts valid PINs and rejects invalid PINs. A PIN is a sequence of digits. A PIN is valid if it consists of four digits, at least two of which are different. You have identified the following valid equivalence partitions:

Variable: PIN code length

• The partition “length correct” - four-digit PINs
• The partition “length incorrect” - PINs with length other than 4

Variable: Number of different digits

• The partition “number of different digits correct” - PINs with at least two different digits
• The partition “number of different digits incorrect” - PINs with all digits being the same

Which of the following is a MINIMUM set of input test data that covers all identified equivalence partitions?

Select ONE option.

25 / 40

25. Which of the following are advantages of DevOps?

i. Faster product release and faster time to market
ii. Increases the need for repetitive manual testing
iii. Constant availability of executable software
iv. Reduction in the number of regression tests associated with code refactoring
v. Setting up the test automation framework is inexpensive since everything is automated

Select ONE option.

26 / 40

26. Decide which of the following statements (i-v) are true for static testing.

i. Abnormal external behaviors are easier to identify with this testing
ii. Discrepancies from a coding standard are easier to find with this testing
iii. It identifies failures caused by defects when the software is run
iv. Its test objective is to identify defects as early as possible
v. Missing coverage for critical security requirements is easier to find and fix

Select ONE option.

27 / 40

27. Which of the following statements is CORRECT?

Select ONE option.

28 / 40

28. Your test suite S for a program P achieves 100% statement coverage. It consists of three test cases, each of which achieves 50% statement coverage.

Which of the following statements is CORRECT?

Select ONE option.

29 / 40

29. You test a system whose lifecycle is modeled by the state transition diagram shown below. The system starts in the INIT state and ends its operation in the OFF state.

What is the MINIMAL number of test cases to achieve valid transitions coverage?

Select ONE option.

30 / 40

30. Which test activity does a data preparation tool support?

Select ONE option.

31 / 40

31. Which of the following is an example of how product risk analysis influences thoroughness and scope of testing?

Select ONE option.

32 / 40

32. Which of the following is a benefit of early and frequent stakeholder feedback?

Select ONE option.

33 / 40

33. Which of the following BEST describes the concept behind error guessing?

Select ONE option.

34 / 40

34. Which of the following is NOT a purpose of a test plan?

Select ONE option.

35 / 40

35. One of the ‘principles of testing’ states that exhaustive testing is impossible. Which of the following is an example of addressing this principle in practice?

Select ONE option.

36 / 40

36. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

37 / 40

37. You are designing test cases based on the following state transition diagram:

What is the MINIMUM number of test cases required to achieve 100% valid transitions coverage?

Select ONE option.

38 / 40

38. Which of the following statements about DevOps is CORRECT?

Select ONE option.

39 / 40

39. Consider the following user story:

As an Editor
I want to review content before it is published
so that I can assure the grammar is correct

and its acceptance criteria:

• The user can log in to the content management system with "Editor" role
• The editor can view existing content pages
• The editor can edit the page content
• The editor can add markup comments
• The editor can save changes
• The editor can reassign to the "content owner" role to make updates

Which of the following is the BEST example of an ATDD test for this user story?

Select ONE option.

40 / 40

40. Given the following test tool categories:

i. Collaboration tools
ii. DevOps tools
iii. Management tools
iv. Non-functional testing tools
v. Test design and implementation tools

Tools from which of the categories are MOST likely to facilitate test execution?

Select ONE options.

0%

Scroll to top