ISTQB Learning

Test your knowledge

0%
13
Created on By Admin

Exam 5 - 75 minutes

1 / 40

1. Which of the following is a product quality metric?

Select ONE option.

2 / 40

2. Which of the following options shows an example of test activities that contribute to success?

Select ONE option.

3 / 40

3. You want to estimate the test effort for the new project using estimation based on ratios. You calculate the test-to-development effort ratio using averaged data for both development effort and test effort from four historical projects similar to the new one. The table shows this historical data.

The estimated development effort for the new project is $800,000. What is your estimate of the test effort in this project?

Select ONE option.

4 / 40

4. Which of the following is an example of a test-first approach to development?

Select ONE option.

5 / 40

5. Which of the following statements about quality assurance (QA) and/or quality control (QC) is correct?

Select ONE option.

6 / 40

6. You are preparing a test execution schedule for executing seven test cases TC 1 to TC 7.

The following figure includes the priorities of these test cases (1=highest priority, 3 = lowest priority).

The figure also shows the dependencies between test cases using arrows. For instance, the arrow from TC 4 to TC 5 means that TC 5 can only be executed if TC 4 was previously executed.

Which test case should be executed sixth?

Select ONE option.

7 / 40

7. What task may management take on during a formal review?

Select ONE option.

8 / 40

8. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

9 / 40

9. Which of the following tests is MOST likely to be performed as part of functional testing?

Select ONE option.

10 / 40

10. How do testers add value to iteration and release planning?

Select ONE option.

11 / 40

11. Your test suite achieved 100% statement coverage. What is the consequence of this fact?

Select ONE option.

12 / 40

12. How can white-box testing be useful in support of black-box testing?

Select ONE option.

13 / 40

13. Your team uses the three-point estimation technique to estimate the test effort for a new high-risk feature. The following estimates were made:

• Most optimistic estimation: 2 person-hours
• Most likely estimation: 11 person-hours
• Most pessimistic estimation: 14 person-hours

What is the final estimate?

Select ONE option.

14 / 40

14. Which of the following are product risks?

Select TWO options.

15 / 40

15. Which collaborative user story writing practice enables the team to achieve a collective understanding of what needs to be delivered?

Select ONE option.

16 / 40

16. Which of the following is a factor that contributes to a successful review?

Select ONE option.

17 / 40

17. Which of the following is an example of why testing is necessary?

Select ONE option.

18 / 40

18. Which of the following is the BEST example of how traceability supports testing?

Select ONE option.

19 / 40

19. Let the branch coverage metric be defined as BCov = (X / Y) * 100%.

What do X and Y represent in this formula?

Select ONE option.

20 / 40

20. Which of the following is an example of a test-first approach to development?

Select ONE option.

21 / 40

21. Which of the following is NOT a benefit of static testing?

Select ONE option.

22 / 40

22. Which of these statements is NOT a factor that contributes to successful reviews?

Select ONE option.

23 / 40

23. Which of the following is a typical test objective?

Select ONE option.

24 / 40

24. Which of the following statements about DevOps is CORRECT?

Select ONE option.

25 / 40

25. Which of the following is an example of a defect that can be found by static testing but NOT by dynamic testing?

Select ONE option.

26 / 40

26. What does the test pyramid model show?

Select ONE option.

27 / 40

27. You have been assigned as a tester to a team producing a new system incrementally. You have noticed that no changes have been made to the existing regression test cases for several iterations and no new regression defects were identified. Your manager is happy, but you are not. Which testing principle explains your skepticism?

Select ONE option.

28 / 40

28. Which TWO of the following statements provide the BEST rationale for using exploratory testing?

Select TWO options.

29 / 40

29. Which of the following is true about exploratory testing?

Select ONE option.

30 / 40

30. Which of the following is an advantage of the whole-team approach?

Select ONE option.

31 / 40

31. Which of the following is an example of how product risk analysis may influence the thoroughness and scope of testing?

Select ONE option.

32 / 40

32. Customers of the TestWash car wash chain have cards with a record of the number of washes they have bought so far. The initial value is 0. After entering the car wash, the system increases the number on the card by one. This value represents the number of the current wash. Based on this number the system decides what discount the customer is entitled to.

For every tenth wash the system gives a 10% discount, and for every twentieth wash, the system gives a further 40% discount (i.e., a 50% discount in total).

Which of the following sets of input data (understood as the numbers of the current wash) achieves the highest equivalence partition coverage?

Select ONE option.

33 / 40

33. Which of the following BEST fits as an element of the checklist used in checklist-based testing?

Select ONE option.

34 / 40

34. Which of the following is NOT anticipated by the tester while applying error guessing?

Select ONE option.

35 / 40

35. Which of the following is a benefit of early and frequent stakeholder feedback?

Select ONE option.

36 / 40

36. Which work product can be used by an agile team to show the amount of work that has been completed and the amount of total work remaining for a given iteration?

Select ONE option.

37 / 40

37. You are testing a system that calculates the final course grade for a given student.

The final grade is assigned based on the final result, according to the following rules:

• 0 – 50 points: failed
• 51 – 60 points: fair
• 61 – 70 points: satisfactory
• 71 – 80 points: good
• 81 – 90 points: very good
• 91 – 100 points: excellent

You have prepared the following set of test cases:

What is the 2-value Boundary Value Analysis (BVA) coverage for the final result that is achieved with the existing test cases?

Select ONE option.

38 / 40

38. Which of the following is an advantage of the whole-team approach?

Select ONE option.

39 / 40

39. Which of the following statements about the chosen software development lifecycle is CORRECT?

Select ONE option.

40 / 40

40. Which of the following are advantages of DevOps?

i. Faster product release and faster time to market
ii. Increases the need for repetitive manual testing
iii. Constant availability of executable software
iv. Reduction in the number of regression tests associated with code refactoring
v. Setting up the test automation framework is inexpensive since everything is automated

Select ONE option.

0%

Scroll to top