ISTQB Learning

Test your knowledge

0%
13
Created on By Admin

Exam 5 - 75 minutes

1 / 40

1. Consider the following part of a test plan.

Testing will be performed using component testing and component integration testing. The regulations require to demonstrate that 100% branch coverage is achieved for each component classified as critical.

Which part of the test plan does this part belong to?

Select ONE option.

2 / 40

2. Which of the following statements about the value of static testing is CORRECT?

Select ONE option.

3 / 40

3. Which of the following is an example of a defect that can be found by static testing but NOT by dynamic testing?

Select ONE option.

4 / 40

4. Which test activity does a data preparation tool support?

Select ONE option.

5 / 40

5. Your team uses planning poker to estimate the test effort for a newly required feature. There is a rule in your team that if there is no time to reach full agreement and the variation in the results is small, applying rules like “accept the number with the most votes” can be applied.
After two rounds, the consensus was not reached, so the third round was initiated. You can see the test estimation results in the table below.

Which of the following is the BEST example of the next step?

Select ONE option.

6 / 40

6. Given the following test tasks:

1. Derive test cases from test conditions
2. Identify reusable testware
3. Organize test cases into test procedures
4. Evaluate test basis and test object

And the following test activities:

A. Test analysis
B. Test design
C. Test implementation
D. Test completion

Which of the following BEST matches the tasks with the activities?

Select ONE option.

7 / 40

7. Which of the following statements is a CORRECT example of the value of traceability?

Select ONE option.

8 / 40

8. At the beginning of each iteration, the team estimates the amount of work (in person-days) they will need to complete during the iteration. Let E(n) be the estimated amount of work for iteration n, and let A(n) be the actual amount of work done in iteration n. From the third iteration, the team uses the following estimation model based on extrapolation:

 

 

The graph shows the estimated and actual amount of work for the first four iterations.

What is the estimated amount of work for iteration #5?

Select ONE option.

9 / 40

9. Which of the following is a typical test objective?

Select ONE option.

10 / 40

10. Which of the following is an example of why testing is necessary?

Select ONE option.

11 / 40

11. Which of the following is NOT an example of how configuration management supports testing?

Select ONE option.

12 / 40

12. Which of the following BEST explains a benefit of independence of testing?

Select ONE option.

13 / 40

13. High-level test conditions are being used by testers to generate test cases and execute tests. Even though the test conditions remain the same, the test cases are varied each time. Which of the following ‘principles of testing’ is being addressed through the variation of test cases?

Select ONE option.

14 / 40

14. You run two test cases, T1 and T2, on the same code. Test T1 achieved 40% statement coverage and test T2 achieved 65% statement coverage.

Which of the following sentences must be necessarily true?

Select ONE option.

15 / 40

15. Which TWO of the following options are common metrics used for reporting on the quality level of the test object?

Select TWO options.

16 / 40

16. Let the branch coverage metric be defined as BCov = (X / Y) * 100%.

What do X and Y represent in this formula?

Select ONE option.

17 / 40

17. Which of the following is an example of a test-first approach to development?

Select ONE option.

18 / 40

18. Given the following descriptions:

1. Support workflow tracking
2. Facilitate communication
3. Virtual machines
4. Support reviews

And the following test tool categories:

A. Static testing tools
B. Tools supporting scalability and deployment standardization
C. DevOps tools
D. Collaboration tools

Which of the following BEST matches the descriptions and categories?

Explanation / Rationale

19 / 40

19. Given the following risks:

1. Ineffective loop implementation causes long system responses
2. Consumers change their preferences
3. Flooding of the server room
4. Patients above a certain age receive inaccurate reports

And the following mitigation activities:

A. Risk acceptance
B. Performance testing
C. Using boundary value analysis as the test technique
D. Risk transfer

Which of the following BEST matches the risks with the mitigation activities?

Select ONE option.

20 / 40

20. Tools from which of the following categories help with the organization of test cases, detected defects and configuration management?

 

Select ONE option.

21 / 40

21. Which of the following BEST describes retrospectives?

Select ONE option.

22 / 40

22. You are testing a form that verifies the correctness of the length of the password given as input. The form accepts a password with the correct length and rejects a password that is too short or too long. The password length is correct if it has between 6 and 12 characters inclusive. Otherwise, it is considered incorrect.

At first, the form is empty (password length = 0). You apply boundary value analysis to the “password length” variable.

Your set of test cases achieves 100% 2-value boundary value coverage. The team decided that due to the high risk of this component, test cases should be added to ensure 100% 3-value boundary value coverage.

Which additional password lengths should be tested to achieve this?

Select ONE option.

23 / 40

23. The following decision table contains the rules for determining the risk of atherosclerosis.

You designed the test cases with the following test input data:

TC1: Cholesterol = 125 mg/dl Blood pressure = 141 mm Hg
TC2: Cholesterol = 200 mg/dl Blood pressure = 201 mm Hg
TC3: Cholesterol = 124 mg/dl Blood pressure = 201 mm Hg
TC4: Cholesterol = 109 mg/dl Blood pressure = 200 mm Hg
TC5: Cholesterol = 201 mg/dl Blood pressure = 140 mm Hg

What is the decision table coverage achieved by these test cases?

Select ONE option.

24 / 40

24. In many software organizations the test department is called the Quality Assurance (QA) department. Is this sentence correct or not and why?

Select ONE option.

25 / 40

25. You work as a tester in a project on a mobile application for food ordering for one of your clients. The client sent you a list of requirements. One of them, with high priority, says

“The order must be processed in less than 10 seconds in 95% of the cases”.

You created a set of test cases in which a number of random orders were made, the processing time measured, and the test results were checked against the requirements.

What test type did you perform?

Select ONE option.

26 / 40

26. You work in a team that develops a mobile application for food ordering. In the current iteration the team decided to implement the payment functionality.

Which of the following activities is a part of test analysis?

Select ONE option.

27 / 40

27. Which of the following is a benefit of early and frequent feedback?

Select ONE option.

28 / 40

28. You have been assigned as a tester to a team producing a new system incrementally. You have noticed that no changes have been made to the existing regression test cases for several iterations and no new regression defects were identified. Your manager is happy, but you are not. Which testing principle explains your skepticism?

Select ONE option.

29 / 40

29. You are testing a temperature control system for a horticultural cold storage facility. The system receives the temperature (in full degrees Celsius) as the input. If the temperature is between 0 and 2 degrees inclusive, the system displays the message “temperature OK”. For lower temperatures, the system displays the message "temperature too low" and for higher temperatures it displays the message “temperature too high”.

Using two-value boundary value analysis, which of the following sets of test inputs provides the highest level of boundary value coverage?

Select ONE option.

30 / 40

30. You are testing a user story with three acceptance criteria: AC1, AC2 and AC3. AC1 is covered by test case TC1, AC2 by TC2, and AC3 by TC3. The test execution history had three test runs on three consecutive versions of the software as follows:

Tests are repeated once you are informed that all defects found in the test run are corrected and a new version of the software is available.
Which of the above tests are executed as regression tests?

Select ONE option.

31 / 40

31. According to the testing quadrants model, which of the following falls into quadrant Q1 (“technology facing” and “support the team”)?

Select ONE option.

32 / 40

32. Given the following task descriptions:

1. The quality characteristics to be evaluated and the exit criteria are selected
2. Everyone has access to the work product
3. Anomalies are identified in the work product
4. Anomalies are discussed

And the following review activities

A. Individual review
B. Review initiation
C. Planning
D. Communication and analysis

Which of the following BEST matches the task descriptions and activities?

Select ONE option.

33 / 40

33. Which of the following skills (i-v) are the MOST important skills of a tester?

i. Having domain knowledge
ii. Creating a product vision
iii. Being a good team player
iv. Planning and organizing the work of the team
v. Critical thinking

Select ONE option.

34 / 40

34. Which of the following is a product quality metric?

Select ONE option.

35 / 40

35. Given the following benefits and drawbacks of the independence of testing:

i. The testers work in a different location from the developers
ii. Testers question the assumptions programmers make while writing code
iii. A confrontational dynamic has been established between testers and developers
iv. Developers have convinced themselves that testers are mostly accountable for quality
v. Testers have different biases than those held by the developers

Which are MOST likely to be considered benefits?

Select ONE option.

36 / 40

36. Which item correctly identifies a potential risk of performing test automation?

Select ONE option.

37 / 40

37. Your favorite bicycle daily rental store has just introduced a new Customer Relationship Management system and asked you, one of their most loyal members, to test it.
The implemented features are as follows:

• Anyone can rent a bicycle, but members receive a 20% discount
• However, if the return deadline is missed, the discount is no longer available
• After 15 rentals, members get a gift: a T-Shirt

Decision table describing the implemented features looks as follows:

Based ONLY on the feature description of the Customer Relationship Management system, which of the above rules describes an impossible situation?

 

Select ONE option.

38 / 40

38. Which of the following statements BEST describes the difference between testing and debugging?

Select ONE option.

39 / 40

39. Which of the following is MOST likely to be a risk of test automation?

Select ONE options.

40 / 40

40. Your test suite S for a program P achieves 100% statement coverage. It consists of three test cases, each of which achieves 50% statement coverage.

Which of the following statements is CORRECT?

Select ONE option.

0%

Scroll to top