ISTQB Learning

Test your knowledge

0%
13
Created on By Admin

Exam 5 - 75 minutes

1 / 40

1. Which of the following is NOT an example of the shift left approach?

Select ONE option.

2 / 40

2. Which of the following is NOT an example of how configuration management supports testing?

Select ONE option.

3 / 40

3. Which of the following is MOST likely to be a benefit of test automation?

 

Select ONE option.

4 / 40

4. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

5 / 40

5. High-level test conditions are being used by testers to generate test cases and execute tests. Even though the test conditions remain the same, the test cases are varied each time. Which of the following ‘principles of testing’ is being addressed through the variation of test cases?

Select ONE option.

6 / 40

6. How can the testing quadrants be beneficial for testing?

Select ONE options.

7 / 40

7. Which of the following is an example of a test-first approach to development?

Select ONE option.

8 / 40

8. Which TWO of the following statements provide the BEST rationale for using exploratory testing?

Select TWO options.

9 / 40

9. You are testing a temperature control system for a horticultural cold storage facility. The system receives the temperature (in full degrees Celsius) as the input. If the temperature is between 0 and 2 degrees inclusive, the system displays the message “temperature OK”. For lower temperatures, the system displays the message "temperature too low" and for higher temperatures it displays the message “temperature too high”.

Using two-value boundary value analysis, which of the following sets of test inputs provides the highest level of boundary value coverage?

Select ONE option.

10 / 40

10. You work in a team that develops a mobile application for food ordering. In the current iteration the team decided to implement the payment functionality.

Which of the following activities is a part of test analysis?

Select ONE option.

11 / 40

11. The following is a list of the work products produced in the SDLC.

i. Business requirements
ii. Schedule
iii. Test budget
iv. Third-party executable code
v. User stories and their acceptance criteria

Which of them can be reviewed?

Select ONE option.

12 / 40

12. Your team uses the three-point estimation technique to estimate the test effort for a new high-risk feature. The following estimates were made:

• Most optimistic estimation: 2 person-hours
• Most likely estimation: 11 person-hours
• Most pessimistic estimation: 14 person-hours

What is the final estimate?

Select ONE option.

13 / 40

13. You are preparing a test execution schedule for executing seven test cases TC 1 to TC 7.

The following figure includes the priorities of these test cases (1=highest priority, 3 = lowest priority).

The figure also shows the dependencies between test cases using arrows. For instance, the arrow from TC 4 to TC 5 means that TC 5 can only be executed if TC 4 was previously executed.

Which test case should be executed sixth?

Select ONE option.

14 / 40

14. Given the following test tasks:

1. Derive test cases from test conditions
2. Identify reusable testware
3. Organize test cases into test procedures
4. Evaluate test basis and test object

And the following test activities:

A. Test analysis
B. Test design
C. Test implementation
D. Test completion

Which of the following BEST matches the tasks with the activities?

Select ONE option.

15 / 40

15. Which of the following is a benefit of early and frequent stakeholder feedback?

Select ONE option.

16 / 40

16. Which of the following is a characteristic of experience-based test techniques?

Select ONE option.

17 / 40

17. Which of the following is MOST likely to impact how testing is performed for a given test object?

Select ONE option.

18 / 40

18. Which of the following statements about quality assurance (QA) and/or quality control (QC) is correct?

Select ONE option.

19 / 40

19. Given the following testware:

1. Coverage items
2. Change requests
3. Test execution schedule
4. Prioritized test conditions

And the following test activities

A. Test analysis
B. Test design
C. Test implementation
D. Test completion

Which of the following BEST shows the testware produced by the activities?

Select ONE option.

20 / 40

20. Which of the following is a benefit of early and frequent feedback?

Select ONE option.

21 / 40

21. Your organization’s test strategy suggests that once a system is going to be retired, data migration shall be tested. As part of what test type is this testing MOST likely to be performed?

Select ONE option.

22 / 40

22. Which of the following is NOT a purpose of a test plan?

Select ONE option.

23 / 40

23. Which of the following CANNOT be examined by static testing?

Select ONE option.

24 / 40

24. You are working as a tester in the team that follows the V-model. The choice of software development lifecycle (SDLC) model impacts the timing of testing, which of the following statement is NOT true?

Select ONE option.

25 / 40

25. In your project there has been a delay in the release of a brand-new application and test execution started late, but you have very detailed domain knowledge and good analytical skills. The full list of requirements has not yet been shared with the team, but management is asking for some test results to be presented.

Which test technique fits BEST in this situation?

Select ONE option.

26 / 40

26. The reviews being used in your organization have the following attributes:

• There is the role of a scribe
• The main purpose is to evaluate quality
• The meeting is led by the author of the work product
• There is individual preparation
• A review report is produced

Which of the following review types is MOST likely being used?

Select ONE option.

27 / 40

27. Which of the following provides the BEST description of the shift-left approach?

Select ONE option.

28 / 40

28. Which of the following are product risks?

Select TWO options.

29 / 40

29. Consider the following rule: “for every SDLC activity there is a corresponding test activity”. In which SDLC models does this rule hold?

Select ONE option.

30 / 40

30. Which of the following options shows an example of test activities that contribute to success?

Select ONE option.

31 / 40

31. Consider the following testware.

Which test activity produces this testware as an output?

Select ONE option.

32 / 40

32. Which of the following BEST fits as an element of the checklist used in checklist-based testing?

Select ONE option.

33 / 40

33. Your team uses planning poker to estimate the test effort for a newly required feature. There is a rule in your team that if there is no time to reach full agreement and the variation in the results is small, applying rules like “accept the number with the most votes” can be applied.
After two rounds, the consensus was not reached, so the third round was initiated. You can see the test estimation results in the table below.

Which of the following is the BEST example of the next step?

Select ONE option.

34 / 40

34. You are testing a user story with three acceptance criteria: AC1, AC2 and AC3. AC1 is covered by test case TC1, AC2 by TC2, and AC3 by TC3. The test execution history had three test runs on three consecutive versions of the software as follows:

Tests are repeated once you are informed that all defects found in the test run are corrected and a new version of the software is available.
Which of the above tests are executed as regression tests?

Select ONE option.

35 / 40

35. Which of the following statements about formal reviews is TRUE?

Select ONE option.

36 / 40

36. Consider the following test categories (1-4) and agile testing quadrants (A-D):

1. Usability testing
2. Component testing
3. Functional testing
4. Reliability testing

A. Agile testing quadrant Q1: technology facing, supporting the development team
B. Agile testing quadrant Q2: business facing, supporting the development team
C. Agile testing quadrant Q3: business facing, critique the product
D. Agile testing quadrant Q4: technology facing, critique the product

How do the following test categories map onto the agile testing quadrants?

Select ONE option.

37 / 40

37. Which of the following is NOT true regarding the test pyramid?

Select ONE option.

38 / 40

38. Which of the following is an advantage of the whole team approach?

Select ONE option.

39 / 40

39. Consider the following part of a test plan.

Testing will be performed using component testing and component integration testing. The regulations require to demonstrate that 100% branch coverage is achieved for each component classified as critical.

Which part of the test plan does this part belong to?

Select ONE option.

40 / 40

40. Given the following review types:

1. Technical review
2. Informal review
3. Inspection
4. Walkthrough

And the following descriptions:

A. Includes objectives such as gaining consensus, generating new ideas, and motivating authors to improve
B. Includes objectives such as educating reviewers, gaining consensus, generating new ideas and detecting potential defects
C. The main objective is detecting potential defects and it requires metrics collection to support process improvement
D. The main objective is detecting potential defects and it generates no formal documented output

Which of the following BEST matches the review types and the descriptions?

Select ONE option.

0%

Scroll to top