ISTQB Learning

Test your knowledge

0%
13
Created on By Admin

Exam 5 - 75 minutes

1 / 40

1. What is the relationship between the testing quadrants, test levels and test types?

Select ONE option.

2 / 40

2. Given the following review types:

1. Technical review
2. Informal review
3. Inspection
4. Walkthrough

And the following descriptions:

A. Includes objectives such as gaining consensus, generating new ideas, and motivating authors to improve
B. Includes objectives such as educating reviewers, gaining consensus, generating new ideas and detecting potential defects
C. The main objective is detecting potential defects and it requires metrics collection to support process improvement
D. The main objective is detecting potential defects and it generates no formal documented output

Which of the following BEST matches the review types and the descriptions?

Select ONE option.

3 / 40

3. Which of the following is MOST likely to describe a task performed by someone in a test management role?

Select ONE option.

4 / 40

4. In many software organizations the test department is called the Quality Assurance (QA) department. Is this sentence correct or not and why?

Select ONE option.

5 / 40

5. Which of the following is a factor that contributes to a successful review?

Select ONE option.

6 / 40

6. Which of the following statements about quality assurance (QA) and/or quality control (QC) is correct?

Select ONE option.

7 / 40

7. Which of the following is an example of a test-first approach to development?

Select ONE option.

8 / 40

8. Which of the following statements about DevOps is CORRECT?

Select ONE option.

9 / 40

9. Which of the following tests is MOST likely to be performed as part of functional testing?

Select ONE option.

10 / 40

10. Your team uses the three-point estimation technique to estimate the test effort for a new high-risk feature. The following estimates were made:

• Most optimistic estimation: 2 person-hours
• Most likely estimation: 11 person-hours
• Most pessimistic estimation: 14 person-hours

What is the final estimate?

Select ONE option.

11 / 40

11. During risk analysis the team considered the following risk: “The system allows too high a discount for a customer”. The team estimated the risk impact to be very high.

What can one say about the risk likelihood?

Select ONE option.

12 / 40

12. You are testing a system that calculates the final course grade for a given student.

The final grade is assigned based on the final result, according to the following rules:

• 0 – 50 points: failed
• 51 – 60 points: fair
• 61 – 70 points: satisfactory
• 71 – 80 points: good
• 81 – 90 points: very good
• 91 – 100 points: excellent

You have prepared the following set of test cases:

What is the 2-value Boundary Value Analysis (BVA) coverage for the final result that is achieved with the existing test cases?

Select ONE option.

13 / 40

13. Which of the following is NOT an example of the shift left approach?

Select ONE option.

14 / 40

14. You want to estimate the test effort for the new project using estimation based on ratios. You calculate the test-to-development effort ratio using averaged data for both development effort and test effort from four historical projects similar to the new one. The table shows this historical data.

The estimated development effort for the new project is $800,000. What is your estimate of the test effort in this project?

Select ONE option.

15 / 40

15. Which of the following provides the BEST description of the shift-left approach?

Select ONE option.

16 / 40

16. Which test activity involves working with test data requirements, test conditions, test environment requirements and test cases?

Select ONE option.

17 / 40

17. Consider the following part of a test plan.

Testing will be performed using component testing and component integration testing. The regulations require to demonstrate that 100% branch coverage is achieved for each component classified as critical.

Which part of the test plan does this part belong to?

Select ONE option.

18 / 40

18. You were given a task to analyze and fix causes of failures in a new system to be released.

Which activity are you performing?

Select ONE option.

19 / 40

19. You are testing a mobile application that allows users to find a nearby restaurant based on the type of food they want to eat. Consider the following list of test cases, priorities (i.e., a smaller number means a higher priority), and dependencies:

Which of the following test cases should be executed as the third one?

Select ONE option.

20 / 40

20. Which of the following is NOT true regarding the test pyramid?

Select ONE option.

21 / 40

21. Which of the following is an advantage of the whole-team approach?

Select ONE option.

22 / 40

22. A designer documents a design for a user interface that does not suitably address disabled users because the designer is tired. The programmer implements the user interface in line with the design but as they are working under severe time pressure, they do not include suitable exception handling in their program code for bonus calculations. When the operational system is used, complaints are made by some disabled users about the interface and the company is subsequently fined by the relevant regulatory authority. No one notices that bonus calculations are sometimes incorrect.

Which of the following statements is CORRECT?

Select ONE option.

23 / 40

23. Which of the following is NOT a purpose of a test plan?

Select ONE option.

24 / 40

24. Which TWO of the following options are the exit criteria for testing a system?

Select TWO options.

25 / 40

25. Which of the following statements about the independence of testing is CORRECT?

Select ONE option.

26 / 40

26. You have been assigned as a tester to a team producing a new system incrementally. You have noticed that no changes have been made to the existing regression test cases for several iterations and no new regression defects were identified. Your manager is happy, but you are not. Which testing principle explains your skepticism?

Select ONE option.

27 / 40

27. Which of the following is MOST likely to be an example of a tester using a generic skill when testing?

Select ONE option.

28 / 40

28. The table shows the traceability matrix from test cases to requirements. “X” means that a given test case covers the corresponding requirement.

You want to prioritize the test cases following the additional coverage prioritization technique.

You execute all four test cases.

Which test case should be executed as the LAST one?

Select ONE options.

29 / 40

29. Which of the following is the BEST example of how traceability supports testing?

Select ONE option.

30 / 40

30. Customers of the TestWash car wash chain have cards with a record of the number of washes they have bought so far. The initial value is 0. After entering the car wash, the system increases the number on the card by one. This value represents the number of the current wash. Based on this number the system decides what discount the customer is entitled to.

For every tenth wash the system gives a 10% discount, and for every twentieth wash, the system gives a further 40% discount (i.e., a 50% discount in total).

Which of the following sets of input data (understood as the numbers of the current wash) achieves the highest equivalence partition coverage?

Select ONE option.

31 / 40

31. Which of the following is an example of a defect that can be found by static testing but NOT by dynamic testing?

Select ONE option.

32 / 40

32. Which of the following is LEAST likely to occur as a result of a retrospective?

Select ONE option.

33 / 40

33. Which of the following is NOT true for white-box testing?

Select ONE option.

34 / 40

34. Which of the following BEST fits as an element of the checklist used in checklist-based testing?

Select ONE option.

35 / 40

35. Which of the following statements about the value of static testing is CORRECT?

Select ONE option.

36 / 40

36. How can the testing quadrants be beneficial for testing?

Select ONE options.

37 / 40

37. Which of the following activities in the test process makes the MOST use of test progress reports?

Select ONE option.

38 / 40

38. Which of the following is MOST likely to be a benefit of test automation?

 

Select ONE option.

39 / 40

39. You are testing a user story with three acceptance criteria: AC1, AC2 and AC3. AC1 is covered by test case TC1, AC2 by TC2, and AC3 by TC3. The test execution history had three test runs on three consecutive versions of the software as follows:

Tests are repeated once you are informed that all defects found in the test run are corrected and a new version of the software is available.
Which of the above tests are executed as regression tests?

Select ONE option.

40 / 40

40. The navigation system software has been updated due to it suggesting routes that break traffic laws, such as driving the wrong way down one-way streets. Which of the following BEST describes the testing that will be performed?

Select ONE option.

0%

Scroll to top