ISTQB Learning

Test your knowledge

0%
13
Created on By Admin

Exam 5 - 75 minutes

1 / 40

1. At the beginning of each iteration, the team estimates the amount of work (in person-days) they will need to complete during the iteration. Let E(n) be the estimated amount of work for iteration n, and let A(n) be the actual amount of work done in iteration n. From the third iteration, the team uses the following estimation model based on extrapolation:

 

 

The graph shows the estimated and actual amount of work for the first four iterations.

What is the estimated amount of work for iteration #5?

Select ONE option.

2 / 40

2. You are using acceptance test-driven development and designing test cases based on the following user story:

Which test case is the MOST reasonable one to test AC3?

Select ONE option.

3 / 40

3. Which of the following is NOT an example of the shift left approach?

Select ONE option.

4 / 40

4. A designer documents a design for a user interface that does not suitably address disabled users because the designer is tired. The programmer implements the user interface in line with the design but as they are working under severe time pressure, they do not include suitable exception handling in their program code for bonus calculations. When the operational system is used, complaints are made by some disabled users about the interface and the company is subsequently fined by the relevant regulatory authority. No one notices that bonus calculations are sometimes incorrect.

Which of the following statements is CORRECT?

Select ONE option.

5 / 40

5. Which of the following is a good testing practice that applies to all software development lifecycles?

Select ONE option.

6 / 40

6. Which of the following is MOST likely to be a benefit of test automation?

Select ONE option.

7 / 40

7. Which of the following statements about the value of static testing is CORRECT?

Select ONE option.

8 / 40

8. How can white-box testing be useful in support of black-box testing?

Select ONE option.

9 / 40

9. You have been assigned as a tester to a team producing a new system incrementally. You have noticed that no changes have been made to the existing regression test cases for several iterations and no new regression defects were identified. Your manager is happy, but you are not. Which testing principle explains your skepticism?

Select ONE option.

10 / 40

10. Which of the following is MOST likely to impact how testing is performed for a given test object?

Select ONE option.

11 / 40

11. You are working as a tester in the team that follows the V-model. The choice of software development lifecycle (SDLC) model impacts the timing of testing, which of the following statement is NOT true?

Select ONE option.

12 / 40

12. Consider the following test categories (1-4) and agile testing quadrants (A-D):

1. Usability testing
2. Component testing
3. Functional testing
4. Reliability testing

A. Agile testing quadrant Q1: technology facing, supporting the development team
B. Agile testing quadrant Q2: business facing, supporting the development team
C. Agile testing quadrant Q3: business facing, critique the product
D. Agile testing quadrant Q4: technology facing, critique the product

How do the following test categories map onto the agile testing quadrants?

Select ONE option.

13 / 40

13. Which of the following statements is a CORRECT example of the value of traceability?

Select ONE option.

14 / 40

14. Which of the following statements about the chosen software development lifecycle is CORRECT?

Select ONE option.

15 / 40

15. According to the testing quadrants model, which of the following falls into quadrant Q1 (“technology facing” and “support the team”)?

Select ONE option.

16 / 40

16. Which of the following skills (i-v) are the MOST important skills of a tester?

i. Having domain knowledge
ii. Creating a product vision
iii. Being a good team player
iv. Planning and organizing the work of the team
v. Critical thinking

Select ONE option.

17 / 40

17. Which of the following is NOT a benefit of static testing?

Select ONE option.

18 / 40

18. How do testers add value to iteration and release planning?

Select ONE option.

19 / 40

19. Consider the following defect report for a Book Lending System.

Which of the following is MOST likely to help the developer reproduce the failure quickly?

Select ONE options.

20 / 40

20. Given the following roles in reviews:

1. Scribe
2. Review leader
3. Facilitator
4. Manager

And the following responsibilities in reviews:

A. Ensures the effective running of review meetings and the setting up a safe review environment
B. Records review information, such as decisions and new anomalies found during the review meeting
C. Decides what is to be reviewed and provides resources, such as staff and time for the review
D. Takes overall responsibility for the review such as organizing when and where the review will take place

Which of the following BEST matches the roles and responsibilities?

Select ONE option.

21 / 40

21. You are designing test cases based on the following decision table.

So far you have designed the following test cases:

• TC1: 19-year-old, unregistered man with no experience; expected result: category A
• TC2: 65-year-old, unregistered woman with 5 years of experience; expected result: category B
• TC3: 66-year-old, registered man with no experience; expected result: category C
• TC4: 65-year-old, registered woman with 4 years of experience; expected result:
category D

Which of the following test cases, when added to the existing set of test cases, will increase the decision table coverage?

Select ONE option.

22 / 40

22. You received the following defect report from the developers stating that the anomaly described in this test report is not reproducible.

Application hangs up
2022-May-03 – John Doe – Rejected
The application hangs up after entering “Test input: $ä” in the Name field on the new user creation screen. Tried to log off, log in with test_admin01 account, same issue. Tried with other test admin accounts, same issue. No error message received; log (see attached) contains fatal error notification. Based on the test case TC-1305, the application should accept the provided input and create the user. Please fix with high priority, this feature is related to REQ-0012, which is a critical new business requirement.

What critical information is MISSING from this test report that would have been useful for the developers?

Select ONE option.

23 / 40

23. You are designing test cases based on the following state transition diagram:

What is the MINIMUM number of test cases required to achieve 100% valid transitions coverage?

Select ONE option.

24 / 40

24. Which of the following options shows an example of test activities that contribute to success?

Select ONE option.

25 / 40

25. Which participant in the review process is responsible for ensuring that the review meetings run effectively and that everyone at the meetings can voice their opinions freely?

Select ONE option.

26 / 40

26. Which of the following is an example of a test-first approach to development?

Select ONE option.

27 / 40

27. Which of the following BEST describes an example of how configuration management (CM) supports testing?

Select ONE option.

28 / 40

28. Given the following example defects:

i. Two different parts of the design specification disagree due to the complexity of the design
ii. A response time is too long and so makes users lose patience
iii. A path in the code cannot be reached during execution
iv. A variable is declared but never subsequently used in the program
v. The amount of memory needed by the program to generate a report is too high

Which of the following BEST identifies example defects that could be found by static testing (rather than dynamic testing)?

Select ONE option.

29 / 40

29. You are testing a web application that allows users to SEARCH for products, VIEW product details, ADD products to a shopping cart, and place an ORDER.
You have prepared the following five test cases, which you want to execute according to their priorities:

TC1: SEARCH product A Priority: medium

TC2: VIEW product A details Priority: low

TC3: ADD product B to a shopping cart Priority: medium

TC4: ADD product C to a shopping cart Priority: high

TC5: place an ORDER Priority: high

You also identified the following logical dependencies between test cases:

• SEARCH functionality must be tested before VIEW functionality can be tested, as product details rely on search functionality.
• VIEW functionality must be tested before ADD functionality, as adding products relies on the availability of accurate product details.
• ADD functionality must be tested before ORDER functionality, as placing an order relies on the availability of accurate shopping cart information.

Which test case should be executed as the fourth one?

Select ONE option.

30 / 40

30. One of the ‘principles of testing’ states that exhaustive testing is impossible. Which of the following is an example of addressing this principle in practice?

Select ONE option.

31 / 40

31. Which of the following is a benefit of early and frequent stakeholder feedback?

Select ONE option.

32 / 40

32. Which of the following is NOT true for white-box testing?

Select ONE option.

33 / 40

33. You are preparing a test execution schedule for executing seven test cases TC 1 to TC 7.

The following figure includes the priorities of these test cases (1=highest priority, 3 = lowest priority).

The figure also shows the dependencies between test cases using arrows. For instance, the arrow from TC 4 to TC 5 means that TC 5 can only be executed if TC 4 was previously executed.

Which test case should be executed sixth?

Select ONE option.

34 / 40

34. Which TWO of the following statements provide the BEST rationale for using exploratory testing?

Select TWO options.

35 / 40

35. Which of the following statements BEST describes the acceptance test-driven development (ATDD) approach?

Select ONE option.

36 / 40

36. Which of the following is a typical test objective?

Select ONE option.

37 / 40

37. Which work product can be used by an agile team to show the amount of work that has been completed and the amount of total work remaining for a given iteration?

Select ONE option.

38 / 40

38. Which item correctly identifies a potential risk of performing test automation?

Select ONE option.

39 / 40

39. The reviews being used in your organization have the following attributes:

• There is the role of a scribe
• The main purpose is to evaluate quality
• The meeting is led by the author of the work product
• There is individual preparation
• A review report is produced

Which of the following review types is MOST likely being used?

Select ONE option.

40 / 40

40. You run two test cases, T1 and T2, on the same code. Test T1 achieved 40% statement coverage and test T2 achieved 65% statement coverage.

Which of the following sentences must be necessarily true?

Select ONE option.

0%

Scroll to top